Review List for EA 08-0F162

Review
No
Review Type
 
Received by
Caltrans
Comments anticipated
to agency
Comments sent
to agency
1* 100% Submittal 04/16/2012  05/28/2012  05/07/2012 
1 60% Submittal 08/23/2011  10/04/2011  09/27/2011 
1 95% Submittal 12/22/2011  02/02/2012  02/23/2012 
1 Draft PR 07/27/2009  09/07/2009  09/01/2009 
2* Draft PR 09/29/2010  11/10/2010  10/01/2010 
1 Drainage Report (Preliminary) 02/04/2009  03/18/2009  03/05/2009 
2* Drainage Report (Preliminary) 07/07/2009  08/18/2009  08/12/2009 
3 Drainage Report (Preliminary) 10/10/2011  11/21/2011  11/07/2011 
4 Drainage Report (Preliminary) 12/22/2011  02/02/2012  01/10/2012 
1 Fact Sheet (Advisory) 12/21/2010  02/01/2011  02/10/2011 
2 Fact Sheet (Advisory) 03/15/2011  04/26/2011  03/17/2011 
3* Fact Sheet (Advisory) 03/23/2011  05/04/2011  04/07/2011 
4 Fact Sheet (Advisory) 12/22/2011  02/02/2012  02/16/2012 
5 Fact Sheet (Advisory) 03/27/2012  05/08/2012  04/23/2012 
1 Fact Sheet (Mandatory) 12/21/2010  02/01/2011  02/10/2011 
2* Fact Sheet (Mandatory) 03/15/2011  04/26/2011  03/17/2011 
3 Fact Sheet (Mandatory) 12/22/2011  02/02/2012  02/16/2012 
4 Fact Sheet (Mandatory) 03/27/2012  05/08/2012  04/25/2012 
1 Fact Sheet (Supp/Advisory) 11/01/2011  12/13/2011  11/21/2011 
1 Fact Sheet (Supp/Mandatory) 10/10/2011  11/21/2011  11/21/2011 
1 GADs 03/12/2009  04/23/2009  03/19/2009 
2 GADs 05/14/2009  06/25/2009  06/25/2009 
1 GADs (Revised/Updated/Supplemental) 08/11/2009  09/22/2009  09/15/2009 
2 GADs (Revised/Updated/Supplemental) 01/11/2010  02/22/2010  03/04/2010 
3 GADs (Revised/Updated/Supplemental) 04/08/2010  05/20/2010  05/25/2010 
4* GADs (Revised/Updated/Supplemental) 08/31/2010  10/12/2010  09/20/2010 
1 Geotechnical Design Report (Preliminary) 03/13/2012  04/24/2012  03/28/2012 
1 Materials Report (Preliminary) 11/08/2011  12/20/2011  11/22/2011 
2 Materials Report (Preliminary) 03/13/2012  04/24/2012  03/28/2012 
1 Operations Analysis 09/11/2008  10/23/2008  10/29/2008 
2 Operations Analysis 01/21/2009  03/04/2009  02/20/2009 
1* Operations Analysis (Revised/Updated/Supplemental) 04/06/2009  05/18/2009  04/08/2009 
1 Other 02/03/2009  03/17/2009  02/25/2009 
2 Other 02/17/2009  03/31/2009  03/04/2009 
3 Other 03/26/2009  05/07/2009  05/13/2009 
4 Other 04/14/2009  05/26/2009  05/07/2009 
5* Other 01/25/2011  03/08/2011  02/09/2011 
1 Project Report (PR) 12/15/2010  01/26/2011  01/12/2011 
2 Project Report (PR) 01/27/2011  03/10/2011  03/03/2011 
3 Project Report (PR) 03/15/2011  04/26/2011  03/25/2011 
4* Project Report (PR) 03/29/2011  05/10/2011  04/04/2011 
1 Right of Way Requirements 04/14/2011  05/26/2011  05/10/2011 
1 Structures (APS/BSDS) 09/17/2008  10/29/2008  10/16/2008 
2 Structures (APS/BSDS) 01/13/2009  02/24/2009  01/20/2009 
3 Structures (APS/BSDS) 01/28/2009  03/11/2009  02/13/2009 
4 Structures (APS/BSDS) 04/01/2009  05/13/2009  05/13/2009 
5* Structures (APS/BSDS) 04/07/2009  05/19/2009  05/13/2009 
6* Structures (APS/BSDS) 04/13/2009  05/25/2009  05/13/2009 
1 SWDR - PA&ED 05/19/2009  06/30/2009  06/18/2009 
2 SWDR - PA&ED 08/11/2009  09/22/2009  09/15/2009 
3 SWDR - PA&ED 02/23/2011  04/06/2011  03/15/2011 
4* SWDR - PA&ED 03/23/2011  05/04/2011  04/05/2011 
1 SWDR - PS&E 08/30/2011  10/11/2011  09/13/2011 
2 SWDR - PS&E 12/29/2011  02/09/2012  01/17/2012 
3* SWDR - PS&E 04/16/2012  05/28/2012  05/07/2012 
1* TMP Datasheet (PS&E) 04/16/2012  05/28/2012  05/08/2012 

* indicates document was approved.

’Comments anticipated to agency‘ date is based on a 6-week turnaround.