Review List for EA 08-46462
Review No |
Review Type |
Received by Caltrans |
Comments anticipated to agency |
Comments sent to agency |
---|---|---|---|---|
1 | 100% Submittal | 10/17/2011 | 11/28/2011 | 11/01/2011 |
1 | 60% Submittal | 02/18/2010 | 04/01/2010 | 04/06/2010 |
1 | 95% Submittal | 04/05/2011 | 05/17/2011 | 04/07/2011 |
2 | 95% Submittal | 05/17/2011 | 06/28/2011 | 06/29/2011 |
1 | Drainage Report (Final) | 05/17/2011 | 06/28/2011 | 06/09/2011 |
1 | Encroachment Permit ($1-$3 Mil) | 06/14/2011 | 07/26/2011 | 09/07/2011 |
2 | Encroachment Permit ($1-$3 Mil) | 07/14/2011 | 08/25/2011 | 08/01/2011 |
1 | Fact Sheet (Advisory) | 12/14/2012 | 01/25/2013 | 01/16/2013 |
1 | Fact Sheet (Supp/Advisory) | 09/21/2012 | 11/02/2012 | 10/04/2012 |
2 | Fact Sheet (Supp/Advisory) | 10/09/2012 | 11/20/2012 | 10/16/2012 |
3* | Fact Sheet (Supp/Advisory) | 10/19/2012 | 11/30/2012 | 10/31/2012 |
1 | Geotechnical Design Report (Final) | 12/02/2010 | 01/13/2011 | 01/26/2011 |
2 | Geotechnical Design Report (Final) | 05/17/2011 | 06/28/2011 | 06/16/2011 |
3 | Geotechnical Design Report (Final) | 11/02/2011 | 12/14/2011 | 11/18/2011 |
1 | Geotechnical Design Report (Preliminary) | 02/23/2010 | 04/06/2010 | 03/30/2010 |
1 | Life Cycle Cost Analysis | 02/22/2010 | 04/05/2010 | 04/07/2010 |
1 | Life Cycle Cost Analysis (PS&E) | 12/02/2010 | 01/13/2011 | 12/16/2010 |
2 | Life Cycle Cost Analysis (PS&E) | 05/17/2011 | 06/28/2011 | 06/21/2011 |
3 | Life Cycle Cost Analysis (PS&E) | 11/07/2011 | 12/19/2011 | 11/21/2011 |
1 | Materials Report (Final) | 12/02/2010 | 01/13/2011 | 12/22/2010 |
2 | Materials Report (Final) | 05/17/2011 | 06/28/2011 | 06/16/2011 |
3 | Materials Report (Final) | 11/08/2011 | 12/20/2011 | 11/28/2011 |
1 | Materials Report (Preliminary) | 02/22/2010 | 04/05/2010 | 03/30/2010 |
1 | Other | 11/08/2012 | 12/20/2012 | 12/12/2012 |
2 | Other | 01/16/2013 | 02/27/2013 | 02/07/2013 |
1 | SWDR - PA&ED | 12/02/2010 | 01/13/2011 | 12/13/2010 |
1 | SWDR - PS&E | 05/17/2011 | 06/28/2011 | 06/09/2011 |
2 | SWDR - PS&E | 12/14/2011 | 01/25/2012 | 01/04/2012 |
1* | TMP Datasheet (PA&ED) | 02/23/2010 | 04/06/2010 | 03/30/2010 |
* indicates document was approved.
’Comments anticipated to agency‘ date is based on a 6-week turnaround.