Review List for EA 08-34770
Review No |
Review Type |
Received by Caltrans |
Comments anticipated to agency |
Comments sent to agency |
---|---|---|---|---|
1 | 30% Submittal | 12/03/2014 | 01/14/2015 | 01/30/2015 |
1 | 60% Submittal | 05/14/2015 | 06/25/2015 | 07/13/2015 |
1 | 95% Submittal | 03/08/2016 | 04/19/2016 | 05/31/2016 |
1 | Decision Documents | 12/18/2017 | 01/29/2018 | 01/02/2018 |
2 | Decision Documents | 07/06/2018 | 08/17/2018 | 07/20/2018 |
1 | Fact Sheet (Combined) | 06/10/2015 | 07/22/2015 | 09/01/2015 |
2 | Fact Sheet (Combined) | 07/27/2017 | 09/07/2017 | 09/08/2017 |
3 | Fact Sheet (Combined) | 09/06/2017 | 10/18/2017 | 09/20/2017 |
4 | Fact Sheet (Combined) | 09/19/2017 | 10/31/2017 | 09/22/2017 |
1 | GADs | 06/18/2015 | 07/30/2015 | 07/20/2015 |
1 | Project Report (PR) | 04/01/2014 | 05/13/2014 | 04/22/2014 |
* indicates document was approved.
’Comments anticipated to agency‘ date is based on a 6-week turnaround.