Review List for EA 08-0G980

Review
No
Review Type
 
Received by
Caltrans
Comments anticipated
to agency
Comments sent
to agency
1 30% Submittal 05/28/2008  07/09/2008  07/14/2008 
1 60% Submittal 09/04/2008  10/16/2008  10/23/2008 
1 95% Submittal 01/12/2009  02/23/2009  02/18/2009 
2 95% Submittal 04/20/2009  06/01/2009  06/16/2009 
3 95% Submittal 07/16/2009  08/27/2009  08/26/2009 
4* 95% Submittal 01/04/2010  02/15/2010  02/17/2010 
1 Drainage Report (Final) 09/04/2008  10/16/2008  10/23/2008 
2 Drainage Report (Final) 01/12/2009  02/23/2009  02/23/2009 
3 Drainage Report (Final) 04/22/2009  06/03/2009  05/19/2009 
4* Drainage Report (Final) 06/01/2009  07/13/2009  06/17/2009 
1 Drainage Report (Preliminary) 05/28/2008  07/09/2008  07/14/2008 
1 Erosion Control Plan (4:1) 05/28/2008  07/09/2008  06/23/2008 
1 Fact Sheet (Supp/Mandatory) 05/28/2008  07/09/2008  07/08/2008 
2 Fact Sheet (Supp/Mandatory) 09/04/2008  10/16/2008  10/27/2008 
3* Fact Sheet (Supp/Mandatory) 11/06/2008  12/18/2008  11/17/2008 
1 Geotechnical Design Report (Final) 09/04/2008  10/16/2008  10/23/2008 
2* Geotechnical Design Report (Final) 01/12/2009  02/23/2009  02/23/2009 
1 Materials Report (Final) 01/12/2009  02/23/2009  02/23/2009 
2* Materials Report (Final) 11/18/2009  12/30/2009  12/09/2009 
1 Materials Report (Preliminary) 05/28/2008  07/09/2008  06/23/2008 
2 Materials Report (Preliminary) 09/04/2008  10/16/2008  10/27/2008 
1* Other 07/27/2009  09/07/2009  08/10/2009 
2 Other 04/12/2011  05/24/2011  04/28/2011 
1 SWDR - PS&E 05/28/2008  07/09/2008  06/30/2008 
2 SWDR - PS&E 08/28/2008  10/09/2008  09/24/2008 
3 SWDR - PS&E 10/02/2008  11/13/2008  11/06/2008 
4* SWDR - PS&E 12/04/2008  01/15/2009  01/23/2009 
1 TMP Datasheet (PS&E) 05/28/2008  07/09/2008  06/30/2008 
2* TMP Datasheet (PS&E) 09/04/2008  10/16/2008  10/09/2008 

* indicates document was approved.

’Comments anticipated to agency‘ date is based on a 6-week turnaround.