Review List for EA 08-0R250

Review
No
Review Type
 
Received by
Caltrans
Comments anticipated
to agency
Comments sent
to agency
1 1st PS&E Review 05/02/2012  06/13/2012  06/12/2012 
1 2nd PS&E Review 07/16/2012  08/27/2012  08/20/2012 
1 4th PS&E Review 02/26/2013  04/09/2013  03/31/2013 
1 5th PS&E Review 05/20/2013  07/01/2013  06/10/2013 
1 6th PS&E Review 06/26/2013  08/07/2013  07/11/2013 
2 6th PS&E Review 08/29/2013  10/10/2013  09/06/2013 
3 6th PS&E Review 04/10/2014  05/22/2014  09/11/2025 
1 Design Exception Review 09/10/2012  10/22/2012  10/18/2012 
2 Design Exception Review 03/06/2013  04/17/2013  03/23/2013 
1 ED - Cultural Review 04/03/2013  05/15/2013  04/11/2013 
2 ED - Cultural Review 04/18/2013  05/30/2013  04/22/2013 
1 ED - HRCR & ASR 02/12/2013  03/26/2013  02/28/2013 
1 ED - NES (MI) 07/12/2012  08/23/2012  08/01/2012 
2 ED - NES (MI) 08/09/2012  09/20/2012  10/25/2012 
1 Environmental Document Review 03/19/2012  04/30/2012  04/23/2012 
2 Environmental Document Review 08/06/2012  09/17/2012  09/24/2012 
3 Environmental Document Review 08/22/2012  10/03/2012  11/19/2012 
4 Environmental Document Review 11/19/2012  12/31/2012  01/09/2013 
5 Environmental Document Review 01/31/2013  03/14/2013  02/25/2013 
6 Environmental Document Review 02/05/2013  03/19/2013  02/28/2013 
7 Environmental Document Review 09/26/2013  11/07/2013  11/06/2013 
8 Environmental Document Review 12/12/2013  01/23/2014  12/24/2013 
1 GDR 08/21/2012  10/02/2012  09/05/2012 
1 Geometric Approval Document (GAD) 03/07/2012  04/18/2012  04/04/2012 
2 Geometric Approval Document (GAD) 04/11/2012  05/23/2012  04/30/2012 
3 Geometric Approval Document (GAD) 02/11/2013  03/25/2013  02/20/2013 
1 Goetech Boring Permit 11/08/2011  12/20/2011  03/21/2012 
1 ISA Checklist 05/24/2012  07/05/2012  06/18/2012 
1 MAR 08/06/2012  09/17/2012  10/18/2012 
2 MAR 08/09/2012  09/20/2012  08/09/2012 
3 MAR 10/30/2012  12/11/2012  12/11/2012 
4 MAR 01/10/2013  02/21/2013  01/24/2013 
1 PS&E Review 11/09/2012  12/21/2012  12/11/2012 
1 Traffic Impact Analysis (TIA) 07/02/2012  08/13/2012  08/08/2012 
1 Workplan Task Management Agreement 07/07/2014  08/18/2014  09/11/2025 

* indicates document was approved.

’Comments anticipated to agency‘ date is based on a 6-week turnaround.