Review List for EA 08-43272

Review
No
Review Type
 
Received by
Caltrans
Comments anticipated
to agency
Comments sent
to agency
1 30% Submittal 10/01/2012  11/12/2012  11/13/2012 
1 60% Submittal 08/02/2013  09/13/2013  09/17/2013 
1 Design Standard Decision Document 08/09/2018  09/20/2018  08/28/2018 
1 Drainage Report (Final) 08/02/2013  09/13/2013  09/17/2013 
1 Fact Sheet (Combined) 01/26/2018  03/09/2018  03/14/2018 
1 Fact Sheet (Supp/Advisory) 08/14/2013  09/25/2013  09/16/2013 
1 Fact Sheet (Supp/Mandatory) 08/02/2013  09/13/2013  09/17/2013 
1 GADs 01/26/2018  03/09/2018  03/14/2018 
2 GADs 05/16/2018  06/27/2018  06/07/2018 
3 GADs 08/13/2018  09/24/2018  09/04/2018 
1 Geotechnical Design Report (Final) 08/02/2013  09/13/2013  09/17/2013 
1 Landscaping 12/10/2013  01/21/2014  01/13/2014 
1 Life Cycle Cost Analysis (PS&E) 08/12/2013  09/23/2013  09/17/2013 
1 Materials Report (Final) 08/02/2013  09/13/2013  09/29/2013 
1 Operations Analysis 10/26/2017  12/07/2017  12/05/2017 
2 Operations Analysis 02/07/2018  03/21/2018  03/09/2018 
1 Other 05/08/2012  06/19/2012  05/21/2012 
2 Other 08/02/2013  09/13/2013  09/17/2013 
3 Other 04/12/2017  05/24/2017  05/03/2017 
4 Other 07/01/2017  08/12/2017  08/18/2017 
5* Other 08/30/2017  10/11/2017  09/26/2017 
1 Right of Way Data Sheets 07/20/2018  08/31/2018  07/31/2018 
1 Right of Way Requirements 12/07/2012  01/18/2013  01/14/2013 
2 Right of Way Requirements 08/02/2013  09/13/2013  09/17/2013 
3 Right of Way Requirements 05/09/2018  06/20/2018  05/29/2018 
1 SWDR - PS&E 08/02/2013  09/13/2013  09/17/2013 
1 TMP Datasheet (PS&E) 10/01/2012  11/12/2012  10/23/2012 
2 TMP Datasheet (PS&E) 08/02/2013  09/13/2013  09/26/2013 
1 Traffic Forecasting 12/15/2016  01/26/2017  12/13/2017 
2* Traffic Forecasting 05/12/2017  06/23/2017  05/19/2017 

* indicates document was approved.

’Comments anticipated to agency‘ date is based on a 6-week turnaround.