to agency
1 60% Submittal 02/11/2015  03/25/2015  03/18/2015 
1 95% Submittal 02/25/2016  04/07/2016  03/29/2016 
2 95% Submittal 05/29/2016  07/10/2016  06/29/2016 
1 Combined Draft PSR/PR 11/06/2012  12/18/2012  12/15/2012 
1 Draft PR 01/06/2014  02/17/2014  02/07/2014 
1 Drainage Report (Final) 02/11/2015  03/25/2015  03/18/2015 
1 Drainage Report (Preliminary) 07/09/2013  08/20/2013  07/29/2013 
1 Fact Sheet (Mandatory) 07/09/2013  08/20/2013  07/29/2013 
1 Fact Sheet (Supp/Advisory) 06/14/2016  07/26/2016  06/29/2016 
2 Fact Sheet (Supp/Advisory) 09/30/2016  11/11/2016  10/20/2016 
3 Fact Sheet (Supp/Advisory) 10/25/2016  12/06/2016  01/25/2017 
1 GADs 10/15/2012  11/26/2012  12/01/2012 
1 Geotechnical Design Report (Final) 02/11/2015  03/25/2015  03/18/2015 
1 Life Cycle Cost Analysis 02/15/2013  03/29/2013  04/15/2015 
1 Materials Report (Final) 02/11/2015  03/25/2015  03/18/2015 
1 Materials Report (Preliminary) 02/15/2013  03/29/2013  03/15/2013 
1* Other 10/09/2012  11/20/2012  10/31/2012 
2 Other 02/18/2016  03/31/2016  03/15/2016 
3 Other 08/17/2016  09/28/2016  09/08/2016 
4 Other 09/30/2016  11/11/2016  10/20/2016 
5 Other 10/25/2016  12/06/2016  11/10/2016 
6 Other 11/08/2016  12/20/2016  11/28/2016 
7 Other 03/03/2017  04/14/2017  03/10/2017 
1 Project Report (PR) 01/30/2015  03/13/2015  03/08/2015 
1 SWDR - PA&ED 10/08/2012  11/19/2012  10/31/2012 
2 SWDR - PA&ED 01/15/2013  02/26/2013  02/18/2013 
3 SWDR - PA&ED 01/28/2014  03/11/2014  02/25/2014 
1 SWDR - PS&E 02/11/2015  03/25/2015  03/11/2015 
2 SWDR - PS&E 05/11/2016  06/22/2016  06/02/2016 
1 TMP Datasheet (PS&E) 02/11/2015  03/25/2015  03/18/2015 