Review List for EA 08-0M590
Review No |
Review Type |
Received by Caltrans |
Comments anticipated to agency |
Comments sent to agency |
---|---|---|---|---|
1 | Design Standard Decision Document | 05/15/2020 | 06/26/2020 | 06/18/2020 |
2 | Design Standard Decision Document | 07/15/2020 | 08/26/2020 | 08/11/2020 |
3 | Design Standard Decision Document | 10/09/2020 | 11/20/2020 | 10/27/2020 |
1 | Draft PR | 03/21/2019 | 05/02/2019 | 05/03/2019 |
2 | Draft PR | 07/31/2019 | 09/11/2019 | 09/18/2019 |
3 | Draft PR | 09/20/2019 | 11/01/2019 | 10/10/2019 |
4 | Draft PR | 12/09/2019 | 01/20/2020 | 01/10/2020 |
5 | Draft PR | 01/30/2020 | 03/12/2020 | 02/13/2020 |
1 | GADs | 12/22/2023 | 02/02/2024 | 02/07/2024 |
2 | GADs | 04/15/2024 | 05/27/2024 | Pending |
1 | Geotechnical Design Report (Preliminary) | 01/19/2016 | 03/01/2016 | 03/03/2016 |
2 | Geotechnical Design Report (Preliminary) | 09/28/2018 | 11/09/2018 | 11/01/2018 |
3 | Geotechnical Design Report (Preliminary) | 11/12/2018 | 12/24/2018 | 01/24/2019 |
4* | Geotechnical Design Report (Preliminary) | 01/25/2019 | 03/08/2019 | 02/08/2019 |
1 | Life Cycle Cost Analysis | 06/12/2019 | 07/24/2019 | Pending |
2 | Life Cycle Cost Analysis | 07/31/2019 | 09/11/2019 | 08/20/2019 |
3* | Life Cycle Cost Analysis | 09/06/2019 | 10/18/2019 | 11/04/2019 |
1 | Materials Report (Preliminary) | 06/09/2015 | 07/21/2015 | 07/08/2015 |
2 | Materials Report (Preliminary) | 11/12/2018 | 12/24/2018 | 01/04/2019 |
3 | Materials Report (Preliminary) | 05/23/2019 | 07/04/2019 | 06/21/2019 |
1 | Operations Analysis | 06/12/2014 | 07/24/2014 | 08/14/2014 |
2 | Operations Analysis | 09/12/2014 | 10/24/2014 | 10/15/2014 |
3* | Operations Analysis | 01/30/2015 | 03/13/2015 | 02/19/2015 |
1 | Operations Analysis (Revised/Updated/Supplemental) | 10/29/2018 | 12/10/2018 | 12/03/2018 |
2* | Operations Analysis (Revised/Updated/Supplemental) | 02/04/2019 | 03/18/2019 | 03/01/2019 |
1 | Other | 10/13/2014 | 11/24/2014 | 11/03/2014 |
2* | Other | 11/18/2014 | 12/30/2014 | 12/02/2014 |
3 | Other | 07/09/2015 | 08/20/2015 | 08/03/2015 |
4 | Other | 07/10/2015 | 08/21/2015 | 09/04/2015 |
5 | Other | 08/12/2015 | 09/23/2015 | 10/07/2015 |
6 | Other | 01/04/2016 | 02/15/2016 | 02/16/2016 |
1 | Project Report (PR) | 08/20/2020 | 10/01/2020 | 09/30/2020 |
2 | Project Report (PR) | 10/14/2020 | 11/25/2020 | 10/30/2020 |
3* | Project Report (PR) | 11/05/2020 | 12/17/2020 | 11/19/2020 |
1 | Quality Management Plan | 05/03/2023 | 06/14/2023 | 06/19/2023 |
2* | Quality Management Plan | 12/21/2023 | 02/01/2024 | 01/30/2024 |
1 | Right of Way Data Sheets | 07/17/2015 | 08/28/2015 | 08/03/2015 |
2 | Right of Way Data Sheets | 10/08/2015 | 11/19/2015 | 11/02/2015 |
3* | Right of Way Data Sheets | 11/21/2015 | 01/02/2016 | 01/22/2016 |
4 | Right of Way Data Sheets | 03/07/2018 | 04/18/2018 | 04/29/2019 |
1 | SWDR - PA&ED | 05/20/2015 | 07/01/2015 | 07/09/2015 |
2 | SWDR - PA&ED | 08/06/2020 | 09/17/2020 | 09/08/2020 |
3 | SWDR - PA&ED | 10/06/2020 | 11/17/2020 | 10/26/2020 |
4 | SWDR - PA&ED | 11/06/2020 | 12/18/2020 | 11/17/2020 |
5* | SWDR - PA&ED | 11/20/2020 | 01/01/2021 | 11/30/2020 |
1 | TMP Datasheet (PA&ED) | 07/10/2015 | 08/21/2015 | 09/02/2015 |
2* | TMP Datasheet (PA&ED) | 09/29/2015 | 11/10/2015 | 11/30/2015 |
3 | TMP Datasheet (PA&ED) | 11/26/2018 | 01/07/2019 | 01/04/2019 |
4 | TMP Datasheet (PA&ED) | 01/21/2019 | 03/04/2019 | 03/01/2019 |
5* | TMP Datasheet (PA&ED) | 03/11/2019 | 04/22/2019 | 04/10/2019 |
1 | Traffic Forecasting | 12/13/2013 | 01/24/2014 | 12/26/2013 |
2* | Traffic Forecasting | 02/13/2014 | 03/27/2014 | 03/27/2014 |
* indicates document was approved.
’Comments anticipated to agency‘ date is based on a 6-week turnaround.