Review List for EA 08-32303
Review No |
Review Type |
Received by Caltrans |
Comments anticipated to agency |
Comments sent to agency |
---|---|---|---|---|
1 | 100% Submittal | 03/03/2020 | 04/14/2020 | 04/08/2020 |
2* | 100% Submittal | 05/27/2020 | 07/08/2020 | 06/25/2020 |
1 | 95% Submittal | 09/24/2019 | 11/05/2019 | 11/13/2019 |
1 | Design Standard Decision Document | 10/11/2019 | 11/22/2019 | 12/18/2019 |
2 | Design Standard Decision Document | 01/28/2020 | 03/10/2020 | 02/25/2020 |
3* | Design Standard Decision Document | 04/29/2020 | 06/10/2020 | 05/20/2020 |
1 | Drainage Report (Final) | 09/24/2019 | 11/05/2019 | 10/24/2019 |
2 | Drainage Report (Final) | 03/03/2020 | 04/14/2020 | 03/27/2020 |
3* | Drainage Report (Final) | 05/27/2020 | 07/08/2020 | 06/09/2020 |
1 | Geotechnical Design Report (Final) | 09/24/2019 | 11/05/2019 | 10/24/2019 |
2* | Geotechnical Design Report (Final) | 02/05/2020 | 03/18/2020 | 02/19/2020 |
1 | Materials Report (Final) | 09/24/2019 | 11/05/2019 | 10/09/2019 |
2* | Materials Report (Final) | 01/21/2020 | 03/03/2020 | 02/19/2020 |
1 | Operations Analysis (Revised/Updated/Supplemental) | 06/12/2019 | 07/24/2019 | Pending |
1 | Project Report (Supplemental) | 11/04/2019 | 12/16/2019 | 01/24/2020 |
2 | Project Report (Supplemental) | 03/16/2020 | 04/27/2020 | 04/22/2020 |
3* | Project Report (Supplemental) | 05/15/2020 | 06/26/2020 | 06/03/2020 |
1 | SWDR - PS&E | 09/24/2019 | 11/05/2019 | 10/26/2019 |
2 | SWDR - PS&E | 03/03/2020 | 04/14/2020 | 04/08/2020 |
3 | SWDR - PS&E | 05/27/2020 | 07/08/2020 | 06/12/2020 |
4 | SWDR - PS&E | 08/26/2020 | 10/07/2020 | 09/08/2020 |
5* | SWDR - PS&E | 09/14/2020 | 10/26/2020 | 09/24/2020 |
1* | TMP Datasheet (PS&E) | 09/24/2019 | 11/05/2019 | 11/06/2019 |
1 | Traffic Forecasting | 03/27/2019 | 05/08/2019 | 04/22/2019 |
2 | Traffic Forecasting | 05/28/2019 | 07/09/2019 | 06/19/2019 |
* indicates document was approved.
’Comments anticipated to agency‘ date is based on a 6-week turnaround.