Review List for EA 08-0Q740
Review No |
Review Type |
Received by Caltrans |
Comments anticipated to agency |
Comments sent to agency |
---|---|---|---|---|
1 | 30% Submittal | 05/14/2014 | 06/25/2014 | 05/20/2014 |
1 | 60% Submittal | 03/17/2014 | 04/28/2014 | 03/24/2014 |
1 | 65% Submittal (Supplemental ) | 02/03/2014 | 03/17/2014 | 02/10/2014 |
2 | 65% Submittal (Supplemental ) | 02/25/2014 | 04/08/2014 | 03/11/2014 |
1 | 95% Submittal | 02/25/2014 | 04/08/2014 | 03/06/2014 |
2 | 95% Submittal | 03/03/2014 | 04/14/2014 | 03/17/2014 |
3 | 95% Submittal | 03/28/2014 | 05/09/2014 | 04/11/2014 |
4 | 95% Submittal | 04/03/2014 | 05/15/2014 | 04/17/2014 |
5 | 95% Submittal | 05/01/2014 | 06/12/2014 | 05/13/2014 |
6 | 95% Submittal | 05/30/2014 | 07/11/2014 | 06/13/2014 |
7 | 95% Submittal | 06/20/2014 | 08/01/2014 | 07/07/2014 |
8 | 95% Submittal | 06/27/2014 | 08/08/2014 | 07/11/2014 |
9 | 95% Submittal | 07/25/2014 | 09/05/2014 | 08/08/2014 |
1 | Decision Documents | 06/12/2014 | 07/24/2014 | 06/13/2014 |
1 | Drainage Report (Final) | 03/10/2014 | 04/21/2014 | 03/20/2014 |
1 | Drainage Report (Preliminary) | 02/03/2014 | 03/17/2014 | 02/10/2014 |
1 | Geotechnical Design Report (Final) | 05/14/2014 | 06/25/2014 | 06/06/2014 |
1 | RFC | 08/29/2014 | 10/10/2014 | 09/12/2014 |
1 | SWDR - PS&E | 03/10/2014 | 04/21/2014 | 03/14/2014 |
2 | SWDR - PS&E | 04/10/2014 | 05/22/2014 | 04/11/2014 |
3 | SWDR - PS&E | 05/08/2014 | 06/19/2014 | 06/05/2014 |
1 | TMP Datasheet (PS&E) | 03/10/2014 | 04/21/2014 | 03/17/2014 |
2 | TMP Datasheet (PS&E) | 04/03/2014 | 05/15/2014 | 04/10/2014 |
3 | TMP Datasheet (PS&E) | 05/01/2014 | 06/12/2014 | 05/08/2014 |
* indicates document was approved.
’Comments anticipated to agency‘ date is based on a 6-week turnaround.