Review List for EA 08-0N69U
Review No |
Review Type |
Received by Caltrans |
Comments anticipated to agency |
Comments sent to agency |
---|---|---|---|---|
1 | 30% Submittal | 03/25/2015 | 05/06/2015 | 04/08/2015 |
1 | 60% Submittal | 11/07/2016 | 12/19/2016 | 12/05/2016 |
1 | 95% Submittal | 03/09/2017 | 04/20/2017 | 03/27/2017 |
1 | Design Standard Decision Document | 05/15/2015 | 06/26/2015 | 05/29/2015 |
2 | Design Standard Decision Document | 02/22/2016 | 04/04/2016 | 03/07/2016 |
3 | Design Standard Decision Document | 04/20/2016 | 06/01/2016 | 04/25/2016 |
4 | Design Standard Decision Document | 05/27/2016 | 07/08/2016 | 06/03/2016 |
1 | Draft PR | 04/15/2014 | 05/27/2014 | 05/06/2014 |
1 | Fact Sheet (Combined) | 01/06/2016 | 02/17/2016 | 01/20/2016 |
1 | GADs | 05/15/2015 | 06/26/2015 | 05/29/2015 |
2 | GADs | 01/06/2016 | 02/17/2016 | 01/20/2016 |
1 | Project Report (PR) | 02/22/2016 | 04/04/2016 | 03/14/2016 |
2 | Project Report (PR) | 04/20/2016 | 06/01/2016 | 05/22/2016 |
* indicates document was approved.
’Comments anticipated to agency‘ date is based on a 6-week turnaround.