Review List for EA 08-1C970

Review
No
Review Type
 
Received by
Caltrans
Comments anticipated
to agency
Comments sent
to agency
1* Drainage Report (Preliminary) 08/07/2015  09/18/2015  08/25/2015 
1 Fact Sheet (Combined) 09/23/2015  11/04/2015  10/07/2015 
2 Fact Sheet (Combined) 01/04/2016  02/15/2016  01/22/2016 
3 Fact Sheet (Combined) 02/22/2016  04/04/2016  03/11/2016 
4 Fact Sheet (Combined) 03/01/2016  04/12/2016  03/30/2016 
5 Fact Sheet (Combined) 04/06/2016  05/18/2016  05/02/2016 
6 Fact Sheet (Combined) 04/27/2016  06/08/2016  09/08/2016 
7 Fact Sheet (Combined) 06/28/2016  08/09/2016  07/12/2016 
1 GADs 09/23/2015  11/04/2015  11/13/2015 
2 GADs 12/28/2015  02/08/2016  02/03/2016 
3 GADs 09/09/2016  10/21/2016  09/18/2016 
4 GADs 09/22/2016  11/03/2016  09/29/2016 
1 Life Cycle Cost Analysis 03/23/2016  05/04/2016  04/25/2016 
2 Life Cycle Cost Analysis 09/16/2016  10/28/2016  10/05/2016 
3 Life Cycle Cost Analysis 10/21/2016  12/02/2016  10/26/2016 
1 Materials Report (Preliminary) 07/21/2014  09/01/2014  09/02/2014 
2* Materials Report (Preliminary) 12/08/2014  01/19/2015  01/13/2015 
1 Operations Analysis 07/28/2014  09/08/2014  09/02/2014 
2 Operations Analysis 09/25/2014  11/06/2014  10/13/2014 
3* Operations Analysis 12/19/2014  01/30/2015  01/26/2015 
1 Other 09/15/2015  10/27/2015  10/20/2015 
2 Other 12/28/2015  02/08/2016  02/04/2016 
3 Other 03/23/2016  05/04/2016  04/21/2016 
1 Project Study Report - Project Report (PSR-PR) 07/22/2016  09/02/2016  08/26/2016 
2 Project Study Report - Project Report (PSR-PR) 09/19/2016  10/31/2016  10/13/2016 
1 SWDR - PA&ED 05/27/2015  07/08/2015  06/16/2015 
2 SWDR - PA&ED 09/15/2015  10/27/2015  10/13/2015 
3 SWDR - PA&ED 02/24/2016  04/06/2016  03/08/2016 
4 SWDR - PA&ED 07/18/2016  08/29/2016  08/25/2016 

* indicates document was approved.

’Comments anticipated to agency‘ date is based on a 6-week turnaround.