Review List for EA 08-1E460

Review
No
Review Type
 
Received by
Caltrans
Comments anticipated
to agency
Comments sent
to agency
1* 100% Submittal 12/12/2017  01/23/2018  12/13/2017 
1* 60% Submittal 01/30/2017  03/13/2017  02/17/2017 
1* 95% Submittal 04/26/2017  06/07/2017  05/17/2017 
2* 95% Submittal 08/24/2017  10/05/2017  09/07/2017 
1* Decision Documents 03/08/2017  04/19/2017  03/22/2017 
2* Decision Documents 04/03/2017  05/15/2017  04/17/2017 
1* Drainage Report (Preliminary) 10/13/2016  11/24/2016  10/27/2016 
1* Project Report (PR) 03/08/2016  04/19/2016  03/25/2016 
2* Project Report (PR) 05/04/2016  06/15/2016  06/02/2016 

* indicates document was approved.

’Comments anticipated to agency‘ date is based on a 6-week turnaround.