Caltrans Logo
 

Review List for EA 08-0C870

Review
No
Review Type
 
Received by
Caltrans
Comments anticipated
to agency
Comments sent
to agency
1 100% Submittal 06/26/2019  08/07/2019  07/26/2019 
2 100% Submittal 09/03/2019  10/15/2019  09/24/2019 
1 60% Submittal 03/05/2018  04/16/2018  04/16/2018 
1 95% Submittal 01/30/2019  03/13/2019  03/14/2019 
1* Design Standard Decision Document 06/28/2019  08/09/2019  07/30/2019 
1 Drainage Report (Final) 06/26/2019  08/07/2019  06/27/2019 
2 Drainage Report (Final) 09/03/2019  10/15/2019  09/23/2019 
1 Drainage Report (Preliminary) 01/30/2019  03/13/2019  03/14/2019 
1 Fact Sheet (Combined) 04/11/2017  05/23/2017  05/16/2017 
2 Fact Sheet (Combined) 06/22/2017  08/03/2017  08/04/2017 
3 Fact Sheet (Combined) 10/09/2017  11/20/2017  10/27/2017 
4* Fact Sheet (Combined) 11/27/2017  01/08/2018  12/22/2017 
1 GADs 04/11/2017  05/23/2017  05/16/2017 
2 GADs 06/22/2017  08/03/2017  08/04/2017 
3 GADs 09/08/2017  10/20/2017  10/06/2017 
1 Geotechnical Design Report (Final) 06/26/2019  08/07/2019  06/26/2019 
1 Geotechnical Design Report (Preliminary) 01/20/2016  03/02/2016  02/24/2016 
2 Geotechnical Design Report (Preliminary) 03/25/2016  05/06/2016  04/12/2016 
3 Geotechnical Design Report (Preliminary) 09/05/2018  10/17/2018  10/12/2018 
4 Geotechnical Design Report (Preliminary) 01/30/2019  03/13/2019  03/14/2019 
1 Life Cycle Cost Analysis 07/10/2017  08/21/2017  07/28/2017 
2 Life Cycle Cost Analysis 10/09/2017  11/20/2017  10/23/2017 
3* Life Cycle Cost Analysis 12/22/2017  02/02/2018  01/09/2018 
1* Life Cycle Cost Analysis (PS&E) 01/04/2018  02/15/2018  01/09/2018 
1 Materials Report (Final) 06/26/2019  08/07/2019  06/26/2019 
1 Materials Report (Preliminary) 05/17/2017  06/28/2017  06/01/2017 
2 Materials Report (Preliminary) 07/10/2017  08/21/2017  08/18/2017 
3 Materials Report (Preliminary) 10/09/2017  11/20/2017  10/23/2017 
4* Materials Report (Preliminary) 11/22/2017  01/03/2018  12/15/2017 
5 Materials Report (Preliminary) 09/05/2018  10/17/2018  10/03/2018 
6 Materials Report (Preliminary) 01/30/2019  03/13/2019  03/14/2019 
1 Operations Analysis 01/09/2017  02/20/2017  02/08/2017 
2 Operations Analysis 03/15/2017  04/26/2017  04/17/2017 
1 Other 12/16/2015  01/27/2016  02/12/2016 
2 Other 02/23/2016  04/05/2016  08/02/2016 
3 Other 04/11/2016  05/23/2016  05/25/2016 
4 Other 06/14/2016  07/26/2016  06/24/2016 
5 Other 10/27/2016  12/08/2016  12/07/2016 
6 Other 07/03/2017  08/14/2017  07/07/2017 
1 Preliminary Environmental Assessment Report (PEAR) 01/20/2016  03/02/2016  04/24/2016 
2 Preliminary Environmental Assessment Report (PEAR) 06/14/2016  07/26/2016  08/02/2016 
1 Project Report (PR) 07/06/2017  08/17/2017  08/12/2017 
2 Project Report (PR) 07/12/2017  08/23/2017  08/25/2017 
3 Project Report (PR) 10/13/2017  11/24/2017  11/28/2017 
1 Project Study Report - Proj. Dev. Sup. (PSR-PDS) 01/20/2016  03/02/2016  03/04/2016 
2 Project Study Report - Proj. Dev. Sup. (PSR-PDS) 06/14/2016  07/26/2016  08/10/2016 
1* Right of Way Data Sheets 07/03/2017  08/14/2017  07/26/2017 
1 Right of Way Requirements 01/21/2018  03/04/2018  02/14/2018 
2 Right of Way Requirements 04/02/2018  05/14/2018  04/19/2018 
3 Right of Way Requirements 07/09/2019  08/20/2019  08/28/2019 
1 SWDR - PA&ED 07/10/2017  08/21/2017  08/25/2017 
2 SWDR - PA&ED 10/09/2017  11/20/2017  10/21/2017 
3 SWDR - PA&ED 11/22/2017  01/03/2018  12/12/2017 
4 SWDR - PA&ED 12/22/2017  02/02/2018  01/09/2018 
1 SWDR - PID 01/20/2016  03/02/2016  02/24/2016 
2 SWDR - PID 06/14/2016  07/26/2016  06/24/2016 
1 SWDR - PS&E 06/26/2019  08/07/2019  06/26/2019 
2 SWDR - PS&E 09/03/2019  10/15/2019  09/23/2019 
1* TMP Datasheet (PA&ED) 07/03/2017  08/14/2017  07/27/2017 
1 Traffic Engineering Performance Assessment (TEPA) 12/02/2015  01/13/2016  01/19/2016 
2 Traffic Engineering Performance Assessment (TEPA) 03/21/2016  05/02/2016  05/25/2016 
3 Traffic Engineering Performance Assessment (TEPA) 06/14/2016  07/26/2016  06/24/2016 

* indicates document was approved.

’Comments anticipated to agency‘ date is based on a 6-week turnaround.