Caltrans Logo
 

Review List for EA 08-1G470

Review
No
Review Type
 
Received by
Caltrans
Comments anticipated
to agency
Comments sent
to agency
1 60% Submittal 08/18/2021  09/29/2021  09/01/2021 
1 95% Submittal 11/16/2021  12/28/2021  12/03/2021 
1 Design Standard Decision Document 02/24/2021  04/07/2021  03/10/2021 
2 Design Standard Decision Document 04/04/2022  05/16/2022  04/18/2022 
1 Draft PR 08/21/2020  10/02/2020  09/04/2020 
1 Project Report (PR) 02/25/2021  04/08/2021  03/05/2021 
1 Project Report (Supplemental) 02/23/2022  04/06/2022  03/04/2022 
1 Project Study Report - Proj. Dev. Sup. (PSR-PDS) 08/23/2016  10/04/2016  09/15/2016 

* indicates document was approved.

’Comments anticipated to agency‘ date is based on a 6-week turnaround.