1 Design Standard Decision Document 01/17/2018  02/28/2018  02/12/2018 
2* Design Standard Decision Document 06/08/2018  07/20/2018  07/06/2018 
1 Draft PR 07/30/2018  09/10/2018  08/16/2018 
2 Draft PR 08/29/2018  10/10/2018  09/27/2018 
3 Draft PR 10/15/2018  11/26/2018  10/26/2018 
1 Drainage Report (Preliminary) 01/31/2019  03/14/2019  02/25/2019 
2 Drainage Report (Preliminary) 01/31/2019  03/14/2019  02/25/2019 
1 Fact Sheet (Combined) 04/11/2018  05/23/2018  05/09/2018 
1 GADs 01/17/2018  02/28/2018  02/12/2018 
2 GADs 04/11/2018  05/23/2018  05/09/2018 
3* GADs 06/08/2018  07/20/2018  07/06/2018 
1* Geotechnical Design Report (Preliminary) 06/05/2018  07/17/2018  06/20/2018 
1* Life Cycle Cost Analysis 07/12/2018  08/23/2018  08/02/2018 
1 Materials Report (Preliminary) 06/05/2018  07/17/2018  06/20/2018 
2* Materials Report (Preliminary) 07/12/2018  08/23/2018  08/01/2018 
1 Operations Analysis 08/25/2017  10/06/2017  10/01/2017 
2* Operations Analysis 11/09/2017  12/21/2017  11/26/2018 
1 Project Report (PR) 03/03/2019  04/14/2019  Pending 
2 Project Report (PR) 04/03/2019  05/15/2019  Pending 
1* Right of Way Data Sheets 08/14/2018  09/25/2018  08/23/2018 
1 Right of Way Requirements 08/02/2018  09/13/2018  08/28/2018 
1 SWDR - PA&ED 07/24/2018  09/04/2018  08/09/2018 
2 SWDR - PA&ED 08/23/2018  10/04/2018  09/24/2018 
3 SWDR - PA&ED 10/10/2018  11/21/2018  10/24/2018 
4* SWDR - PA&ED 10/26/2018  12/07/2018  11/01/2018 
1 Traffic Forecasting 03/16/2017  04/27/2017  03/30/2017 
2 Traffic Forecasting 05/16/2017  06/27/2017  06/21/2017 