Review List for EA 08-0K122
Review No |
Review Type |
Received by Caltrans |
Comments anticipated to agency |
Comments sent to agency |
---|---|---|---|---|
1 | 60% Submittal | 12/13/2018 | 01/24/2019 | 01/11/2019 |
1 | 95% Submittal | 07/16/2019 | 08/27/2019 | 07/31/2019 |
2 | 95% Submittal | 08/23/2019 | 10/04/2019 | 09/06/2019 |
3 | 95% Submittal | 01/21/2020 | 03/03/2020 | 01/28/2020 |
1 | Design Standard Decision Document | 12/11/2019 | 01/22/2020 | 12/25/2019 |
2 | Design Standard Decision Document | 01/16/2020 | 02/27/2020 | 01/23/2020 |
1 | Other | 12/13/2019 | 01/24/2020 | 12/27/2019 |
1 | Project Report (Supplemental) | 03/14/2018 | 04/25/2018 | 04/20/2018 |
* indicates document was approved.
’Comments anticipated to agency‘ date is based on a 6-week turnaround.