Review List for EA 08-0C70U

Review
No
Review Type
 
Received by
Caltrans
Comments anticipated
to agency
Comments sent
to agency
1 100% Submittal 09/21/2018  11/02/2018  10/05/2018 
2 100% Submittal 12/17/2018  01/28/2019  01/29/2019 
3 100% Submittal 02/27/2019  04/10/2019  03/14/2019 
1 60% Submittal 03/06/2017  04/17/2017  04/24/2017 
1 95% Submittal 07/30/2018  09/10/2018  08/17/2018 
1 Contract Change Order (CCO) 08/11/2021  09/22/2021  08/26/2021 
2 Contract Change Order (CCO) 08/31/2021  10/12/2021  09/22/2021 
3 Contract Change Order (CCO) 01/11/2022  02/22/2022  01/26/2022 
4 Contract Change Order (CCO) 03/02/2022  04/13/2022  03/15/2022 
5 Contract Change Order (CCO) 08/31/2022  10/12/2022  09/21/2022 
6 Contract Change Order (CCO) 02/06/2023  03/20/2023  02/08/2023 
7 Contract Change Order (CCO) 01/22/2024  03/04/2024  Pending 
1 Design Standard Decision Document 08/01/2018  09/12/2018  08/17/2018 
2* Design Standard Decision Document 09/14/2018  10/26/2018  10/12/2018 
3 Design Standard Decision Document 03/11/2021  04/22/2021  03/19/2021 
4 Design Standard Decision Document 03/25/2021  05/06/2021  04/14/2021 
5 Design Standard Decision Document 04/22/2021  06/03/2021  05/03/2021 
1* Drainage Report (Final) 07/30/2018  09/10/2018  08/16/2018 
1 Drainage Report (Preliminary) 03/06/2017  04/17/2017  03/30/2017 
1 Geotechnical Design Report (Final) 07/30/2018  09/10/2018  08/16/2018 
1 Geotechnical Design Report (Preliminary) 03/06/2017  04/17/2017  03/28/2017 
1* Materials Report (Final) 07/30/2018  09/10/2018  08/16/2018 
1 Materials Report (Preliminary) 03/12/2017  04/23/2017  04/11/2017 
1 Other 05/31/2018  07/12/2018  06/21/2018 
2* Other 07/02/2018  08/13/2018  07/11/2018 
3 Other 09/21/2018  11/02/2018  10/05/2018 
4 Other 09/21/2018  11/02/2018  10/05/2018 
5 Other 01/19/2021  03/02/2021  02/16/2021 
1 Project Report (Supplemental) 04/02/2018  05/14/2018  04/13/2018 
2* Project Report (Supplemental) 05/22/2018  07/03/2018  05/30/2018 
1 Request for Information (RFI) 03/17/2022  04/28/2022  03/18/2022 
1 Right of Way Requirements 06/22/2017  08/03/2017  07/12/2017 
1 SWDR - PS&E 03/06/2017  04/17/2017  04/10/2017 
2* SWDR - PS&E 07/30/2018  09/10/2018  08/17/2018 
1 TMP Datasheet (PS&E) 03/06/2017  04/17/2017  05/04/2017 

* indicates document was approved.

’Comments anticipated to agency‘ date is based on a 6-week turnaround.