Caltrans Logo
 

Review List for EA 08-1H160

Review
No
Review Type
 
Received by
Caltrans
Comments anticipated
to agency
Comments sent
to agency
1 100% Submittal 04/16/2021  05/28/2021  04/29/2021 
1 60% Submittal 07/03/2019  08/14/2019  08/01/2019 
1 95% Submittal 10/20/2020  12/01/2020  12/11/2020 
2 95% Submittal 01/22/2021  03/05/2021  02/19/2021 
1 Design Standard Decision Document 06/21/2018  08/02/2018  07/19/2018 
2 Design Standard Decision Document 09/10/2018  10/22/2018  10/02/2018 
3 Design Standard Decision Document 12/05/2018  01/16/2019  01/03/2019 
4* Design Standard Decision Document 02/07/2019  03/21/2019  02/19/2019 
5 Design Standard Decision Document 09/30/2020  11/11/2020  11/04/2020 
1 Drainage Report (Final) 07/03/2019  08/14/2019  08/01/2019 
2 Drainage Report (Final) 01/25/2021  03/08/2021  02/19/2021 
1* Drainage Report (Preliminary) 08/17/2018  09/28/2018  09/06/2018 
1 GADs 06/21/2018  08/02/2018  07/19/2018 
2 GADs 09/10/2018  10/22/2018  10/02/2018 
3* GADs 12/05/2018  01/16/2019  01/03/2019 
1 Geotechnical Design Report (Final) 07/03/2019  08/14/2019  08/01/2019 
2 Geotechnical Design Report (Final) 08/18/2020  09/29/2020  09/01/2020 
1 Geotechnical Design Report (Preliminary) 08/16/2018  09/27/2018  09/06/2018 
2 Geotechnical Design Report (Preliminary) 10/08/2018  11/19/2018  10/22/2018 
3* Geotechnical Design Report (Preliminary) 11/08/2018  12/20/2018  11/21/2018 
1 Life Cycle Cost Analysis 12/11/2018  01/22/2019  12/27/2018 
2* Life Cycle Cost Analysis 01/21/2019  03/04/2019  02/05/2019 
1 Materials Report (Final) 07/03/2019  08/14/2019  08/01/2019 
2 Materials Report (Final) 08/18/2020  09/29/2020  09/08/2020 
1 Materials Report (Preliminary) 08/16/2018  09/27/2018  09/06/2018 
2 Materials Report (Preliminary) 12/11/2018  01/22/2019  12/27/2018 
3 Materials Report (Preliminary) 01/17/2019  02/28/2019  02/05/2019 
4* Materials Report (Preliminary) 02/08/2019  03/22/2019  02/19/2019 
1 Operations Analysis 04/17/2018  05/29/2018  05/09/2018 
2 Operations Analysis 05/24/2018  07/05/2018  06/12/2018 
3 Operations Analysis 07/26/2018  09/06/2018  08/03/2018 
4* Operations Analysis 07/30/2018  09/10/2018  08/13/2018 
5* Operations Analysis 09/04/2018  10/16/2018  09/20/2018 
1* Other 05/04/2017  06/15/2017  07/14/2017 
2 Other 06/06/2018  07/18/2018  06/21/2018 
3 Other 09/26/2018  11/07/2018  10/07/2018 
4* Other 10/23/2018  12/04/2018  11/20/2018 
1* Preliminary Environmental Assessment Report (PEAR) 08/03/2017  09/14/2017  09/20/2017 
1 Project Report (PR) 01/23/2019  03/06/2019  02/20/2019 
2 Project Report (PR) 03/14/2019  04/25/2019  04/09/2019 
3 Project Report (PR) 04/23/2019  06/04/2019  05/06/2019 
4* Project Report (PR) 05/26/2019  07/07/2019  06/11/2019 
1* Project Study Report - Proj. Dev. Sup. (PSR-PDS) 08/03/2017  09/14/2017  09/20/2017 
2* Project Study Report - Proj. Dev. Sup. (PSR-PDS) 10/16/2017  11/27/2017  11/07/2017 
1 Quality Management Plan 10/26/2020  12/07/2020  01/20/2021 
1 Right of Way Data Sheets 01/21/2019  03/04/2019  02/19/2019 
1 SWDR - PA&ED 09/06/2018  10/18/2018  10/03/2018 
2 SWDR - PA&ED 10/08/2018  11/19/2018  10/22/2018 
3 SWDR - PA&ED 10/25/2018  12/06/2018  11/12/2018 
4* SWDR - PA&ED 02/07/2019  03/21/2019  02/21/2019 
1* SWDR - PID 08/03/2017  09/14/2017  09/20/2017 
2* SWDR - PID 10/16/2017  11/27/2017  11/28/2017 
3* SWDR - PID 11/09/2017  12/21/2017  11/28/2017 
1 SWDR - PS&E 07/03/2019  08/14/2019  08/01/2019 
2 SWDR - PS&E 10/20/2020  12/01/2020  12/11/2020 
3 SWDR - PS&E 01/22/2021  03/05/2021  02/19/2021 
4 SWDR - PS&E 04/15/2021  05/27/2021  04/27/2021 
5 SWDR - PS&E 05/21/2021  07/02/2021  Pending 
1 TMP Datasheet (PA&ED) 01/21/2019  03/04/2019  02/20/2019 
1 TMP Datasheet (PS&E) 07/03/2019  08/14/2019  08/01/2019 
2 TMP Datasheet (PS&E) 11/02/2020  12/14/2020  12/16/2020 
1* Traffic Engineering Performance Assessment (TEPA) 07/12/2017  08/23/2017  07/25/2017 
2 Traffic Engineering Performance Assessment (TEPA) 06/04/2018  07/16/2018  06/20/2018 
1 Traffic Forecasting 12/28/2017  02/08/2018  02/05/2018 
2 Traffic Forecasting 02/07/2018  03/21/2018  02/22/2018 
3* Traffic Forecasting 02/27/2018  04/10/2018  03/07/2018 

* indicates document was approved.

’Comments anticipated to agency‘ date is based on a 6-week turnaround.