Review List for EA 08-1E340

Review
No
Review Type
 
Received by
Caltrans
Comments anticipated
to agency
Comments sent
to agency
1 100% Submittal 09/13/2018  10/25/2018  09/25/2018 
1 60% Submittal 10/03/2022  11/14/2022  10/17/2022 
1 95% Submittal 01/23/2023  03/06/2023  02/06/2023 
1 CEM1302 Positive Work Zone Protection 05/24/2023  07/05/2023  06/23/2023 
1 Project Information Report (PIR) 04/21/2017  06/02/2017  05/05/2017 
1 Project Report (PR) 04/21/2022  06/02/2022  04/29/2022 

* indicates document was approved.

’Comments anticipated to agency‘ date is based on a 6-week turnaround.