Review List for EA 08-1G880
Review No |
Review Type |
Received by Caltrans |
Comments anticipated to agency |
Comments sent to agency |
---|---|---|---|---|
1 | 60% Submittal | 03/08/2022 | 04/19/2022 | 03/22/2022 |
1 | 95% Submittal | 06/28/2022 | 08/09/2022 | 07/12/2022 |
1 | CEM1302 Positive Work Zone Protection | 10/03/2022 | 11/14/2022 | 10/17/2022 |
1 | Draft PR | 07/14/2021 | 08/25/2021 | 07/28/2021 |
1 | Project Information Report (PIR) | 05/16/2017 | 06/27/2017 | 05/23/2017 |
2 | Project Information Report (PIR) | 05/16/2017 | 06/27/2017 | 05/23/2017 |
* indicates document was approved.
’Comments anticipated to agency‘ date is based on a 6-week turnaround.