Review List for EA 08-1C570
Review No |
Review Type |
Received by Caltrans |
Comments anticipated to agency |
Comments sent to agency |
---|---|---|---|---|
1 | 60% Submittal | 04/07/2022 | 05/19/2022 | 04/25/2022 |
1 | 95% Submittal | 08/05/2022 | 09/16/2022 | 08/22/2022 |
1 | Project Information Report (PIR) | 05/22/2017 | 07/03/2017 | 06/05/2017 |
1 | Project Initiation Report (PIR) | 09/05/2018 | 10/17/2018 | 09/19/2018 |
2 | Project Initiation Report (PIR) | 06/04/2019 | 07/16/2019 | 06/05/2019 |
1 | Project Report (PR) | 07/23/2021 | 09/03/2021 | 08/09/2021 |
2 | Project Report (PR) | 08/06/2021 | 09/17/2021 | 08/12/2021 |
3 | Project Report (PR) | 08/24/2021 | 10/05/2021 | 09/03/2021 |
* indicates document was approved.
’Comments anticipated to agency‘ date is based on a 6-week turnaround.