1 30% Submittal 03/20/2023  05/01/2023  04/03/2023 
1 60% Submittal 06/07/2023  07/19/2023  06/22/2023 
1 95% Submittal 10/02/2023  11/13/2023  10/31/2023 
1 CEM1302 Positive Work Zone Protection 01/31/2024  03/13/2024  02/15/2024 
1 Draft PR 06/01/2022  07/13/2022  06/10/2022 
1 Project Information Report (PIR) 05/25/2017  07/06/2017  06/08/2017 
1 Project Report (PR) 09/14/2022  10/26/2022  09/23/2022 