Review List for EA 08-1J210
Review No |
Review Type |
Received by Caltrans |
Comments anticipated to agency |
Comments sent to agency |
---|---|---|---|---|
1 | 65% Submittal (Supplemental ) | 07/20/2020 | 08/31/2020 | 08/17/2020 |
1 | 95% Submittal | 10/02/2020 | 11/13/2020 | 10/30/2020 |
1 | Design Standard Decision Document | 07/02/2020 | 08/13/2020 | 07/20/2020 |
1 | Project Initiation Report (PIR) | 07/19/2017 | 08/30/2017 | 07/21/2017 |
1 | Project Report (PR) | 03/27/2020 | 05/08/2020 | 04/14/2020 |
* indicates document was approved.