Review List for EA 08-1F362

Review
No
Review Type
 
Received by
Caltrans
Comments anticipated
to agency
Comments sent
to agency
1 95% Submittal 10/19/2018  11/30/2018  11/10/2018 
2 95% Submittal 10/19/2018  11/30/2018  11/10/2018 
1 Draft PR 08/11/2017  09/22/2017  08/25/2017 
2 Draft PR 08/15/2017  09/26/2017  08/29/2017 
3 Draft PR 08/16/2017  09/27/2017  08/30/2017 
1 Project Report (PR) 08/02/2017  09/13/2017  08/16/2017 
2 Project Report (PR) 08/03/2017  09/14/2017  08/17/2017 
3 Project Report (PR) 08/03/2017  09/14/2017  08/17/2017 
4 Project Report (PR) 08/07/2017  09/18/2017  08/21/2017 
5 Project Report (PR) 08/30/2017  10/11/2017  09/04/2017 

* indicates document was approved.