Review List for EA 08-0E620
Review No |
Review Type |
Received by Caltrans |
Comments anticipated to agency |
Comments sent to agency |
---|---|---|---|---|
1 | Drainage Report (Preliminary) | 07/27/2009 | 09/07/2009 | 09/02/2009 |
2 | Drainage Report (Preliminary) | 11/23/2009 | 01/04/2010 | 12/29/2009 |
3 | Drainage Report (Preliminary) | 01/25/2010 | 03/08/2010 | 03/02/2010 |
4* | Drainage Report (Preliminary) | 03/11/2010 | 04/22/2010 | 03/23/2010 |
1 | Fact Sheet (Mandatory) | 07/27/2009 | 09/07/2009 | 09/17/2009 |
2 | Fact Sheet (Mandatory) | 11/23/2009 | 01/04/2010 | 01/27/2010 |
3 | Fact Sheet (Mandatory) | 03/25/2010 | 05/06/2010 | 05/19/2010 |
1 | Geotechnical Design Report (Preliminary) | 03/25/2010 | 05/06/2010 | 05/06/2010 |
1 | Life Cycle Cost Analysis | 08/25/2009 | 10/06/2009 | 10/29/2009 |
2 | Life Cycle Cost Analysis | 11/23/2009 | 01/04/2010 | 01/05/2010 |
3 | Life Cycle Cost Analysis | 03/25/2010 | 05/06/2010 | 04/22/2010 |
1 | Materials Report (Preliminary) | 04/26/2010 | 06/07/2010 | 06/02/2010 |
1 | Operations Analysis | 07/20/2009 | 08/31/2009 | 09/01/2009 |
2* | Operations Analysis | 01/14/2010 | 02/25/2010 | 02/01/2010 |
1 | Right of Way Data Sheets | 11/23/2009 | 01/04/2010 | 01/05/2010 |
2 | Right of Way Data Sheets | 01/25/2010 | 03/08/2010 | 03/02/2010 |
3 | Right of Way Data Sheets | 03/11/2010 | 04/22/2010 | 04/20/2010 |
1 | SWDR - PA&ED | 07/27/2009 | 09/07/2009 | 09/03/2009 |
2 | SWDR - PA&ED | 11/23/2009 | 01/04/2010 | 01/07/2010 |
3 | SWDR - PA&ED | 01/25/2010 | 03/08/2010 | 03/02/2010 |
4* | SWDR - PA&ED | 03/11/2010 | 04/22/2010 | 03/30/2010 |
1 | TMP Datasheet (PA&ED) | 08/25/2009 | 10/06/2009 | 10/20/2009 |
1* | Traffic Forecasting | 05/29/2008 | 07/10/2008 | 06/18/2008 |
* indicates document was approved.
’Comments anticipated to agency‘ date is based on a 6-week turnaround.