Review List for EA 08-1J540
Review No |
Review Type |
Received by Caltrans |
Comments anticipated to agency |
Comments sent to agency |
---|---|---|---|---|
1 | 60% Submittal | 10/04/2022 | 11/15/2022 | 10/18/2022 |
1 | 95% Submittal | 02/10/2023 | 03/24/2023 | 02/24/2023 |
1 | CEM1302 Positive Work Zone Protection | 10/11/2022 | 11/22/2022 | 10/25/2022 |
1* | Design Standard Decision Document | 11/03/2021 | 12/15/2021 | 11/19/2021 |
2* | Design Standard Decision Document | 08/30/2022 | 10/11/2022 | 09/13/2022 |
1 | Drainage Report (Preliminary) | 02/10/2023 | 03/24/2023 | 02/24/2023 |
1 | Other | 06/27/2022 | 08/08/2022 | 07/11/2022 |
2 | Other | 08/31/2022 | 10/12/2022 | 09/14/2022 |
1* | Project Initiation Report (PIR) | 04/25/2018 | 06/06/2018 | 05/09/2018 |
2* | Project Initiation Report (PIR) | 05/14/2018 | 06/25/2018 | 05/25/2018 |
1* | Project Report (PR) | 11/23/2021 | 01/04/2022 | 12/10/2021 |
1 | Project Report (Supplemental) | 04/06/2023 | 05/18/2023 | 04/20/2023 |
1 | SWDR - PS&E | 02/10/2023 | 03/24/2023 | 02/24/2023 |
* indicates document was approved.
’Comments anticipated to agency‘ date is based on a 6-week turnaround.