Review List for EA 08-0F543
Review No |
Review Type |
Received by Caltrans |
Comments anticipated to agency |
Comments sent to agency |
---|---|---|---|---|
1 | Design Standard Decision Document | 06/11/2018 | 07/23/2018 | 07/16/2018 |
2 | Design Standard Decision Document | 09/14/2018 | 10/26/2018 | 10/18/2018 |
3 | Design Standard Decision Document | 11/29/2018 | 01/10/2019 | 01/08/2019 |
4 | Design Standard Decision Document | 04/03/2019 | 05/15/2019 | Pending |
5 | Design Standard Decision Document | 06/26/2020 | 08/07/2020 | Pending |
1 | Fact Sheet (Combined) | 03/01/2018 | 04/12/2018 | 03/27/2018 |
1 | Fact Sheet (Ramp Metering) | 06/12/2018 | 07/24/2018 | 01/22/2019 |
1 | GADs | 03/01/2018 | 04/12/2018 | 03/27/2018 |
1 | GADs (Revised/Updated/Supplemental) | 06/11/2018 | 07/23/2018 | 07/16/2018 |
2 | GADs (Revised/Updated/Supplemental) | 09/14/2018 | 10/26/2018 | 10/18/2018 |
3 | GADs (Revised/Updated/Supplemental) | 06/23/2020 | 08/04/2020 | Pending |
1 | Project Report (Supplemental) | 11/29/2018 | 01/10/2019 | 01/02/2019 |
* indicates document was approved.
’Comments anticipated to agency‘ date is based on a 6-week turnaround.