Caltrans Logo
 

Review List for EA 08-1J880

Review
No
Review Type
 
Received by
Caltrans
Comments anticipated
to agency
Comments sent
to agency
1 30% Submittal 01/24/2020  03/06/2020  02/11/2020 
1 95% Submittal 11/09/2020  12/21/2020  12/09/2020 
2 95% Submittal 07/06/2021  08/17/2021  08/06/2021 
3 95% Submittal 04/24/2022  06/05/2022  07/20/2022 
4 95% Submittal 11/29/2022  01/10/2023  12/28/2022 
5 95% Submittal 03/08/2023  04/19/2023  03/21/2023 
1 CEM1302 Positive Work Zone Protection 11/29/2022  01/10/2023  12/27/2022 
2 CEM1302 Positive Work Zone Protection 03/07/2023  04/18/2023  03/16/2023 
3 CEM1302 Positive Work Zone Protection 03/27/2023  05/08/2023  04/04/2023 
1 Design Standard Decision Document 08/11/2020  09/22/2020  08/26/2020 
2 Design Standard Decision Document 09/23/2020  11/04/2020  10/07/2020 
3 Design Standard Decision Document 11/19/2020  12/31/2020  12/02/2020 
4 Design Standard Decision Document 12/08/2020  01/19/2021  12/24/2020 
5 Design Standard Decision Document 12/28/2020  02/08/2021  01/07/2021 
6* Design Standard Decision Document 02/08/2021  03/22/2021  02/16/2021 
1 Drainage Report (Preliminary) 11/09/2020  12/21/2020  11/30/2020 
2* Drainage Report (Preliminary) 01/21/2021  03/04/2021  01/21/2021 
1* Environmental Document Review 03/26/2018  05/07/2018  05/16/2018 
1* Geotechnical Design Report (Final) 09/02/2019  10/14/2019  09/05/2019 
1 Geotechnical Design Report (GDR) 05/30/2019  07/11/2019  Pending 
2 Geotechnical Design Report (GDR) 08/08/2019  09/19/2019  08/26/2019 
1 Goetech Boring Permit 03/14/2018  04/25/2018  04/20/2018 
1 Materials Report (Final) 01/07/2021  02/18/2021  01/21/2021 
1 Other 11/17/2021  12/29/2021  12/09/2021 
2 Other 12/16/2021  01/27/2022  12/27/2021 
3 Other 01/18/2022  03/01/2022  01/25/2022 
4 Other 01/26/2022  03/09/2022  02/01/2022 
5* Other 06/09/2022  07/21/2022  06/14/2022 
1* Permits 04/26/2018  06/07/2018  05/04/2018 
1 Right of Way Data Sheets 09/24/2020  11/05/2020  10/20/2020 
2 Right of Way Data Sheets 10/27/2020  12/08/2020  11/09/2020 
3 Right of Way Data Sheets 02/02/2021  03/16/2021  03/02/2021 
1 SWDR - PS&E 11/09/2020  12/21/2020  12/08/2020 
2 SWDR - PS&E 12/14/2020  01/25/2021  12/29/2020 
3 SWDR - PS&E 01/22/2021  03/05/2021  01/28/2021 
4 SWDR - PS&E 02/12/2021  03/26/2021  03/02/2021 
5 SWDR - PS&E 10/04/2021  11/15/2021  10/13/2021 
6* SWDR - PS&E 11/15/2021  12/27/2021  11/24/2021 
1 TMP Datasheet (PS&E) 11/09/2020  12/21/2020  11/30/2020 
1 Traffic Forecasting 01/28/2021  03/11/2021  03/08/2021 

* indicates document was approved.

’Comments anticipated to agency‘ date is based on a 6-week turnaround.