Review List for EA 08-1K060
Review No |
Review Type |
Received by Caltrans |
Comments anticipated to agency |
Comments sent to agency |
---|---|---|---|---|
1 | Design Standard Decision Document | 11/02/2018 | 12/14/2018 | 11/07/2018 |
2 | Design Standard Decision Document | 11/28/2018 | 01/09/2019 | 12/12/2018 |
3 | Design Standard Decision Document | 01/10/2019 | 02/21/2019 | 01/24/2019 |
4 | Design Standard Decision Document | 02/26/2019 | 04/09/2019 | 02/26/2019 |
1 | Geotechnical Design Report (GDR) | 08/23/2018 | 10/04/2018 | 09/06/2018 |
1 | OTHERS | 11/02/2018 | 12/14/2018 | 02/12/2019 |
2 | OTHERS | 03/07/2019 | 04/18/2019 | 03/21/2019 |
1 | PEER Review | 05/21/2018 | 07/02/2018 | 06/10/2018 |
2 | PEER Review | 11/02/2018 | 12/14/2018 | 11/26/2018 |
1 | PS&E Review | 05/30/2018 | 07/11/2018 | 07/11/2018 |
2 | PS&E Review | 11/02/2018 | 12/14/2018 | 11/19/2018 |
3 | PS&E Review | 01/10/2019 | 02/21/2019 | 01/24/2019 |
4 | PS&E Review | 01/30/2019 | 03/13/2019 | 02/28/2019 |
5 | PS&E Review | 03/07/2019 | 04/18/2019 | 03/12/2019 |
1 | SWDR Review | 07/13/2018 | 08/24/2018 | 07/27/2018 |
2 | SWDR Review | 11/02/2018 | 12/14/2018 | 12/03/2018 |
3 | SWDR Review | 01/10/2019 | 02/21/2019 | 01/24/2019 |
4 | SWDR Review | 03/07/2019 | 04/18/2019 | Pending |
* indicates document was approved.
’Comments anticipated to agency‘ date is based on a 6-week turnaround.