Review List for EA 08-1K100

Review
No
Review Type
 
Received by
Caltrans
Comments anticipated
to agency
Comments sent
to agency
1 100% Submittal 03/28/2022  05/09/2022  04/28/2022 
2 100% Submittal 03/28/2022  05/09/2022  04/28/2022 
3 100% Submittal 05/31/2022  07/12/2022  06/14/2022 
4* 100% Submittal 09/21/2022  11/02/2022  10/21/2022 
1 95% Submittal 08/31/2020  10/12/2020  10/01/2020 
2 95% Submittal 08/17/2021  09/28/2021  10/08/2021 
3 95% Submittal 11/17/2021  12/29/2021  12/28/2021 
1 CEM1302 Positive Work Zone Protection 05/31/2022  07/12/2022  06/21/2022 
2 CEM1302 Positive Work Zone Protection 07/13/2022  08/24/2022  07/26/2022 
3 CEM1302 Positive Work Zone Protection 09/21/2022  11/02/2022  09/30/2022 
4 CEM1302 Positive Work Zone Protection 10/11/2022  11/22/2022  Pending 
1 Encroachment Permit ($1-$3 Mil) 07/07/2022  08/18/2022  07/29/2022 
1 Geotechnical Design Report (Final) 08/17/2021  09/28/2021  09/08/2021 
2 Geotechnical Design Report (Final) 12/02/2021  01/13/2022  12/27/2021 
3 Geotechnical Design Report (Final) 03/28/2022  05/09/2022  04/28/2022 
4* Geotechnical Design Report (Final) 05/31/2022  07/12/2022  06/21/2022 
1 Geotechnical Design Report (Preliminary) 09/23/2020  11/04/2020  10/26/2020 
1 Other 08/17/2021  09/28/2021  09/08/2021 
2 Other 08/17/2021  09/28/2021  09/08/2021 
3 Other 08/17/2021  09/28/2021  09/08/2021 
4 Other 08/19/2021  09/30/2021  09/18/2021 
5 Other 11/15/2021  12/27/2021  12/27/2021 
6 Other 11/17/2021  12/29/2021  12/27/2021 
7 Other 11/17/2021  12/29/2021  12/27/2021 
8 Other 11/17/2021  12/29/2021  12/27/2021 
9 Other 12/02/2021  01/13/2022  12/27/2021 
10* Other 03/28/2022  05/09/2022  04/28/2022 
11* Other 03/28/2022  05/09/2022  04/28/2022 
12 Other 03/28/2022  05/09/2022  04/28/2022 
13 Other 04/12/2022  05/24/2022  05/11/2022 
14* Other 05/20/2022  07/01/2022  06/14/2022 
15 Other 05/20/2022  07/01/2022  06/15/2022 
16* Other 06/01/2022  07/13/2022  06/21/2022 
17 Other 07/13/2022  08/24/2022  07/29/2022 
18 Other 07/26/2022  09/06/2022  08/09/2022 
19 Other 09/21/2022  11/02/2022  09/22/2022 
1 PEER Review 06/18/2018  07/30/2018  08/28/2018 
1 PS&E Review 06/18/2018  07/30/2018  07/02/2018 
2 PS&E Review 09/17/2018  10/29/2018  09/20/2018 
1 SWDR - PS&E 08/17/2021  09/28/2021  09/08/2021 
2 SWDR - PS&E 11/17/2021  12/29/2021  12/27/2021 
1 SWDR Review 06/26/2018  08/07/2018  07/10/2018 
2 SWDR Review 09/17/2018  10/29/2018  09/25/2018 

* indicates document was approved.

’Comments anticipated to agency‘ date is based on a 6-week turnaround.