Review List for EA 08-0A450

Review
No
Review Type
 
Received by
Caltrans
Comments anticipated
to agency
Comments sent
to agency
1 100% Submittal 09/16/2011  10/28/2011  09/28/2011 
2 100% Submittal 10/04/2011  11/15/2011  10/05/2011 
1 30% Submittal 11/14/2007  12/26/2007  01/08/2008 
2 30% Submittal 03/11/2008  04/22/2008  04/25/2008 
1 60% Submittal 09/24/2008  11/05/2008  11/18/2008 
1 95% Submittal 04/07/2009  05/19/2009  06/03/2009 
2 95% Submittal 01/19/2010  03/02/2010  03/26/2010 
3* 95% Submittal 06/09/2010  07/21/2010  07/08/2010 
1 Drainage Report (Final) 11/20/2007  01/01/2008  12/31/2007 
2 Drainage Report (Final) 09/24/2008  11/05/2008  11/06/2008 
3 Drainage Report (Final) 05/07/2009  06/18/2009  06/15/2009 
4 Drainage Report (Final) 01/25/2010  03/08/2010  04/27/2010 
5 Drainage Report (Final) 06/23/2010  08/04/2010  07/12/2010 
6* Drainage Report (Final) 07/13/2010  08/24/2010  07/19/2010 
1 Geotechnical Design Report (Final) 05/22/2008  07/03/2008  07/02/2008 
2 Geotechnical Design Report (Final) 08/14/2008  09/25/2008  10/01/2008 
3 Geotechnical Design Report (Final) 11/18/2008  12/30/2008  01/14/2009 
4* Geotechnical Design Report (Final) 09/09/2009  10/21/2009  10/21/2009 
1 Materials Report (Final) 05/22/2008  07/03/2008  06/30/2008 
2 Materials Report (Final) 08/14/2008  09/25/2008  09/29/2008 
3 Materials Report (Final) 11/18/2008  12/30/2008  12/14/2009 
4 Materials Report (Final) 09/09/2009  10/21/2009  10/21/2009 
5 Materials Report (Final) 08/02/2010  09/13/2010  08/17/2010 
6* Materials Report (Final) 08/25/2010  10/06/2010  09/08/2010 
1 Project Report (PR) 03/06/2007  04/17/2007  04/05/2007 
2 Project Report (PR) 04/24/2007  06/05/2007  05/07/2007 
3* Project Report (PR) 05/11/2007  06/22/2007  05/14/2007 
1 Right of Way Requirements 04/18/2007  05/30/2007  05/30/2007 
2 Right of Way Requirements 07/26/2007  09/06/2007  09/18/2007 
3 Right of Way Requirements 10/11/2007  11/22/2007  11/13/2007 
4 Right of Way Requirements 11/27/2007  01/08/2008  12/05/2007 
5* Right of Way Requirements 04/01/2008  05/13/2008  05/13/2008 
6 Right of Way Requirements 06/15/2009  07/27/2009  09/02/2009 
1 SWDR - PS&E 11/20/2007  01/01/2008  01/04/2008 
2 SWDR - PS&E 09/24/2008  11/05/2008  10/30/2008 
3 SWDR - PS&E 04/23/2009  06/04/2009  04/23/2009 
4 SWDR - PS&E 05/07/2009  06/18/2009  06/15/2009 
5 SWDR - PS&E 01/25/2010  03/08/2010  03/17/2010 
6 SWDR - PS&E 07/13/2010  08/24/2010  07/28/2010 
7* SWDR - PS&E 08/03/2010  09/14/2010  08/09/2010 
1 TMP Datasheet (PS&E) 11/19/2007  12/31/2007  01/04/2008 
2 TMP Datasheet (PS&E) 03/21/2008  05/02/2008  05/08/2008 
3 TMP Datasheet (PS&E) 10/23/2008  12/04/2008  01/14/2009 
4* TMP Datasheet (PS&E) 06/17/2010  07/29/2010  07/02/2010 

* indicates document was approved.

’Comments anticipated to agency‘ date is based on a 6-week turnaround.