Review List for EA 08-1L460
Review No |
Review Type |
Received by Caltrans |
Comments anticipated to agency |
Comments sent to agency |
---|---|---|---|---|
1 | 30% Submittal | 07/09/2021 | 08/20/2021 | 08/12/2021 |
2 | 30% Submittal | 10/11/2021 | 11/22/2021 | 10/18/2021 |
1 | 95% Submittal | 11/09/2021 | 12/21/2021 | 12/06/2021 |
2 | 95% Submittal | 01/21/2022 | 03/04/2022 | 02/11/2022 |
3 | 95% Submittal | 04/08/2022 | 05/20/2022 | 05/02/2022 |
4 | 95% Submittal | 05/22/2022 | 07/03/2022 | 06/07/2022 |
5 | 95% Submittal | 06/27/2022 | 08/08/2022 | 07/08/2022 |
6* | 95% Submittal | 07/27/2022 | 09/07/2022 | 07/28/2022 |
1 | CEM1302 Positive Work Zone Protection | 07/22/2022 | 09/02/2022 | 08/12/2022 |
1 | Contract Change Order (CCO) | 12/19/2022 | 01/30/2023 | 12/21/2022 |
2 | Contract Change Order (CCO) | 02/01/2023 | 03/15/2023 | 02/08/2023 |
3 | Contract Change Order (CCO) | 06/22/2023 | 08/03/2023 | 06/26/2023 |
4* | Contract Change Order (CCO) | 09/26/2023 | 11/07/2023 | 09/28/2023 |
1 | Design Standard Decision Document | 11/09/2021 | 12/21/2021 | 11/29/2021 |
2 | Design Standard Decision Document | 01/21/2022 | 03/04/2022 | 02/07/2022 |
3 | Design Standard Decision Document | 04/06/2022 | 05/18/2022 | 05/04/2022 |
4 | Design Standard Decision Document | 05/22/2022 | 07/03/2022 | 06/07/2022 |
5 | Design Standard Decision Document | 06/27/2022 | 08/08/2022 | 07/11/2022 |
6 | Design Standard Decision Document | 07/22/2022 | 09/02/2022 | 08/09/2022 |
1 | Drainage Report (Final) | 11/23/2021 | 01/04/2022 | 12/06/2021 |
2 | Drainage Report (Final) | 04/06/2022 | 05/18/2022 | 04/21/2022 |
1 | Geotechnical Design Report (Preliminary) | 03/10/2022 | 04/21/2022 | 03/28/2022 |
1 | Materials Report (Final) | 07/14/2022 | 08/25/2022 | 07/22/2022 |
1 | Other | 01/16/2020 | 02/27/2020 | 01/24/2020 |
2 | Other | 11/01/2021 | 12/13/2021 | 12/06/2021 |
3 | Other | 04/06/2022 | 05/18/2022 | 04/27/2022 |
4 | Other | 04/18/2022 | 05/30/2022 | 05/12/2022 |
5 | Other | 04/25/2022 | 06/06/2022 | 05/16/2022 |
6 | Other | 05/22/2022 | 07/03/2022 | 06/02/2022 |
7 | Other | 05/22/2022 | 07/03/2022 | 06/02/2022 |
8 | Other | 05/22/2022 | 07/03/2022 | 06/02/2022 |
9 | Other | 06/27/2022 | 08/08/2022 | 07/08/2022 |
10* | Other | 06/27/2022 | 08/08/2022 | 07/06/2022 |
11 | Other | 07/22/2022 | 09/02/2022 | 07/26/2022 |
12* | Other | 08/03/2022 | 09/14/2022 | 08/17/2022 |
1 | Right of Way Data Sheets | 07/12/2021 | 08/23/2021 | 08/03/2021 |
1 | SWDR - PA&ED | 07/12/2021 | 08/23/2021 | 08/03/2021 |
1 | SWDR - PS&E | 11/10/2021 | 12/22/2021 | 12/07/2021 |
2 | SWDR - PS&E | 01/21/2022 | 03/04/2022 | 02/01/2022 |
3 | SWDR - PS&E | 02/10/2022 | 03/24/2022 | 02/17/2022 |
4 | SWDR - PS&E | 04/07/2022 | 05/19/2022 | 04/26/2022 |
5 | SWDR - PS&E | 05/22/2022 | 07/03/2022 | 06/02/2022 |
6 | SWDR - PS&E | 06/27/2022 | 08/08/2022 | 07/08/2022 |
7 | SWDR - PS&E | 07/22/2022 | 09/02/2022 | 07/28/2022 |
1 | Traffic Forecasting | 07/09/2021 | 08/20/2021 | 07/27/2021 |
* indicates document was approved.
’Comments anticipated to agency‘ date is based on a 6-week turnaround.