Review List for EA 08-0M94L

Review
No
Review Type
 
Received by
Caltrans
Comments anticipated
to agency
Comments sent
to agency
1 100% Submittal 06/22/2021  08/03/2021  Pending 
2 100% Submittal 02/28/2023  04/11/2023  Pending 
3 100% Submittal 08/05/2023  09/16/2023  Pending 
4 100% Submittal 04/11/2024  05/23/2024  Pending 
1 30% Submittal 03/16/2020  04/27/2020  04/16/2020 
1 65% Submittal (Supplemental ) 11/23/2020  01/04/2021  Pending 
1 95% Submittal 03/18/2021  04/29/2021  Pending 
1 Landscaping 01/16/2024  02/27/2024  Pending 
2 Landscaping 01/24/2024  03/06/2024  Pending 
1 Project Report (PR) 03/26/2020  05/07/2020  Pending 
2 Project Report (PR) 07/20/2020  08/31/2020  Pending 

* indicates document was approved.

’Comments anticipated to agency‘ date is based on a 6-week turnaround.