1 Drainage Report (Preliminary) 04/08/2024  05/20/2024  Pending 
1 GADs 02/07/2023  03/21/2023  03/16/2023 
2 GADs 08/09/2023  09/20/2023  09/18/2023 
1 Highway Safety Manual (HSM) 09/15/2023  10/27/2023  10/18/2023 
2 Highway Safety Manual (HSM) 01/15/2024  02/26/2024  02/13/2024 
1 Operations Analysis 11/14/2022  12/26/2022  12/16/2022 
2 Operations Analysis 01/11/2023  02/22/2023  03/01/2023 
3 Operations Analysis 03/09/2023  04/20/2023  05/19/2023 
1 Other 04/11/2022  05/23/2022  05/12/2022 
2 Other 05/26/2022  07/07/2022  06/24/2022 
3 Other 07/05/2022  08/16/2022  07/26/2022 
4* Other 07/28/2022  09/08/2022  08/25/2022 
5 Other 11/06/2023  12/18/2023  12/26/2023 
6 Other 04/15/2024  05/27/2024  Pending 
1 Project Study Report - Proj. Dev. Sup. (PSR-PDS) 11/15/2020  12/27/2020  Pending 
1 Traffic Forecasting 01/12/2022  02/23/2022  02/02/2022 
2* Traffic Forecasting 02/09/2022  03/23/2022  02/25/2022 

* indicates document was approved.