Review List for EA 08-0J083
Review No |
Review Type |
Received by Caltrans |
Comments anticipated to agency |
Comments sent to agency |
---|---|---|---|---|
1 | Design Standard Decision Document | 03/07/2022 | 04/18/2022 | 04/05/2022 |
1 | Drainage Report (Preliminary) | 02/15/2022 | 03/29/2022 | 03/11/2022 |
2 | Drainage Report (Preliminary) | 03/29/2023 | 05/10/2023 | 04/18/2023 |
1 | GADs | 02/03/2022 | 03/17/2022 | 03/14/2022 |
2 | GADs | 02/24/2023 | 04/07/2023 | 03/28/2023 |
1 | Materials Report (Preliminary) | 03/29/2023 | 05/10/2023 | 04/19/2023 |
1 | Operations Analysis | 02/01/2022 | 03/15/2022 | 03/16/2022 |
2 | Operations Analysis | 05/17/2022 | 06/28/2022 | 06/07/2022 |
1 | Other | 10/19/2021 | 11/30/2021 | 11/10/2021 |
2 | Other | 02/22/2022 | 04/05/2022 | 03/11/2022 |
3 | Other | 10/10/2023 | 11/21/2023 | 10/26/2023 |
1 | Project Report (PR) | 07/19/2023 | 08/30/2023 | 08/07/2023 |
2 | Project Report (PR) | 10/31/2023 | 12/12/2023 | 11/07/2023 |
1 | SWDR - PA&ED | 03/02/2022 | 04/13/2022 | 04/04/2022 |
1 | Traffic Forecasting | 05/17/2021 | 06/28/2021 | 06/10/2021 |
2* | Traffic Forecasting | 10/19/2021 | 11/30/2021 | 01/19/2022 |
* indicates document was approved.
’Comments anticipated to agency‘ date is based on a 6-week turnaround.