Review List for EA 08-0K400

Review
No
Review Type
 
Received by
Caltrans
Comments anticipated
to agency
Comments sent
to agency
1 1st PS&E Review 10/10/2017  11/21/2017  11/09/2017 
1 95% Submittal 03/31/2022  05/12/2022  05/18/2022 
2 95% Submittal 08/09/2022  09/20/2022  08/29/2022 
3 95% Submittal 11/22/2022  01/03/2023  12/23/2022 
4 95% Submittal 03/17/2023  04/28/2023  04/13/2023 
5 95% Submittal 06/12/2023  07/24/2023  07/07/2023 
6 95% Submittal 07/20/2023  08/31/2023  08/07/2023 
7 95% Submittal 08/21/2023  10/02/2023  09/14/2023 
8 95% Submittal 09/29/2023  11/10/2023  10/10/2023 
1 CEM1302 Positive Work Zone Protection 11/22/2022  01/03/2023  12/23/2022 
1 Design Standard Decision Document 11/22/2022  01/03/2023  12/20/2022 
2 Design Standard Decision Document 01/18/2023  03/01/2023  02/03/2023 
3 Design Standard Decision Document 03/17/2023  04/28/2023  04/13/2023 
4 Design Standard Decision Document 06/12/2023  07/24/2023  07/07/2023 
5 Design Standard Decision Document 07/20/2023  08/31/2023  08/16/2023 
6* Design Standard Decision Document 08/21/2023  10/02/2023  08/24/2023 
1 Drainage Report 10/10/2017  11/21/2017  10/30/2017 
1 Drainage Report (Final) 08/09/2022  09/20/2022  08/24/2022 
2 Drainage Report (Final) 11/22/2022  01/03/2023  12/20/2022 
3 Drainage Report (Final) 03/31/2023  05/12/2023  04/25/2023 
4 Drainage Report (Final) 06/12/2023  07/24/2023  07/06/2023 
1 Drainage Report (Preliminary) 04/15/2022  05/27/2022  05/09/2022 
1 EMWD 24"Recycled Water Plans 10/10/2017  11/21/2017  11/21/2017 
1 Encroachment Permit ($1-$3 Mil) 06/25/2007  08/06/2007  07/18/2007 
2 Encroachment Permit ($1-$3 Mil) 12/05/2007  01/16/2008  12/19/2007 
1 Encroachment Policy Exception 05/10/2018  06/21/2018  05/21/2018 
1 Environmental Document Review 12/08/2016  01/19/2017  09/11/2025 
1 Environmental Reports 07/16/2007  08/27/2007  08/15/2007 
1 Fact Sheet 06/15/2017  07/27/2017  07/18/2017 
2 Fact Sheet 08/01/2017  09/12/2017  08/30/2017 
1 Geometric Approval Document (GAD) 09/26/2016  11/07/2016  11/01/2016 
2 Geometric Approval Document (GAD) 01/27/2017  03/10/2017  02/13/2017 
3 Geometric Approval Document (GAD) 04/17/2017  05/29/2017  05/24/2017 
4 Geometric Approval Document (GAD) 04/17/2017  05/29/2017  05/24/2017 
5 Geometric Approval Document (GAD) 06/15/2017  07/27/2017  07/18/2017 
6 Geometric Approval Document (GAD) 07/31/2017  09/11/2017  08/30/2017 
7 Geometric Approval Document (GAD) 01/11/2018  02/22/2018  02/06/2018 
1 Material Report Review 10/16/2017  11/27/2017  11/02/2017 
2 Material Report Review 04/16/2018  05/28/2018  05/01/2018 
1 Materials Report 08/13/2018  09/24/2018  08/28/2018 
1 Materials Report (Preliminary) 09/28/2023  11/09/2023  10/10/2023 
2 Materials Report (Preliminary) 10/17/2023  11/28/2023  10/26/2023 
3 Materials Report (Preliminary) 11/08/2023  12/20/2023  11/20/2023 
1 Other 01/18/2023  03/01/2023  02/03/2023 
2 Other 03/17/2023  04/28/2023  04/13/2023 
3 Other 06/12/2023  07/24/2023  07/07/2023 
1 OTHERS 02/01/2018  03/15/2018  03/15/2018 
2 OTHERS 04/17/2018  05/29/2018  05/03/2018 
3 OTHERS 04/19/2018  05/31/2018  04/19/2018 
4 OTHERS 05/11/2018  06/22/2018  07/02/3028 
1 PS&E Review 04/16/2018  05/28/2018  06/01/2018 
2 PS&E Review 08/13/2018  09/24/2018  Pending 
1* Right of Way Requirements 05/04/2022  06/15/2022  05/19/2022 
1 SWDR - PS&E 08/09/2022  09/20/2022  08/25/2022 
2 SWDR - PS&E 11/22/2022  01/03/2023  12/23/2022 
3 SWDR - PS&E 03/17/2023  04/28/2023  04/13/2023 
4 SWDR - PS&E 06/12/2023  07/24/2023  07/07/2023 
5 SWDR - PS&E 07/20/2023  08/31/2023  08/15/2023 
1 SWDR Review 10/10/2017  11/21/2017  10/30/2017 
2 SWDR Review 04/18/2018  05/30/2018  04/19/2018 
3 SWDR Review 08/13/2018  09/24/2018  08/28/2018 
1 Traffic Impact Analysis (TIA) 05/05/2016  06/16/2016  05/31/2016 
2 Traffic Impact Analysis (TIA) 07/21/2016  09/01/2016  08/11/2016 
3 Traffic Impact Analysis (TIA) 01/27/2017  03/10/2017  02/13/2017 
1 Utility Plans 10/10/2017  11/21/2017  10/26/2017 
2 Utility Plans 04/17/2018  05/29/2018  05/07/2018 

* indicates document was approved.

’Comments anticipated to agency‘ date is based on a 6-week turnaround.