Caltrans Logo
 

Review List for EA 08-1M190

Review
No
Review Type
 
Received by
Caltrans
Comments anticipated
to agency
Comments sent
to agency
1 30% Submittal 12/21/2021  02/01/2022  01/10/2022 
2 30% Submittal 02/28/2022  04/11/2022  03/24/2022 
1 95% Submittal 06/28/2023  08/09/2023  07/26/2023 
2 95% Submittal 10/18/2023  11/29/2023  11/29/2023 
1 CEM1302 Positive Work Zone Protection 10/18/2023  11/29/2023  11/15/2023 
1 Design Standard Decision Document 08/14/2023  09/25/2023  08/31/2023 
2 Design Standard Decision Document 11/08/2023  12/20/2023  12/06/2023 
1 Operations Analysis 09/22/2021  11/03/2021  10/28/2021 
2 Operations Analysis 12/20/2021  01/31/2022  01/06/2022 
3 Operations Analysis 03/14/2022  04/25/2022  04/06/2022 
4 Operations Analysis 09/06/2022  10/18/2022  10/07/2022 
5 Operations Analysis 02/27/2023  04/10/2023  03/17/2023 
6* Operations Analysis 05/02/2023  06/13/2023  05/03/2023 
1 Other 12/22/2021  02/02/2022  01/03/2022 
2 Other 02/28/2022  04/11/2022  03/24/2022 
3 Other 10/18/2023  11/29/2023  11/13/2023 
4 Other 12/04/2023  01/15/2024  01/25/2024 
1 SWDR - PS&E 03/14/2022  04/25/2022  03/29/2022 
2 SWDR - PS&E 04/28/2022  06/09/2022  05/18/2022 
3 SWDR - PS&E 06/28/2023  08/09/2023  07/26/2023 
1 Traffic Forecasting 05/14/2021  06/25/2021  06/04/2021 
2 Traffic Forecasting 07/07/2021  08/18/2021  08/06/2021 

* indicates document was approved.

’Comments anticipated to agency‘ date is based on a 6-week turnaround.