Review List for EA 08-0K520

Review
No
Review Type
 
Received by
Caltrans
Comments anticipated
to agency
Comments sent
to agency
1 100% Submittal 06/15/2012  07/27/2012  07/26/2012 
2* 100% Submittal 07/24/2012  09/04/2012  08/08/2012 
1 95% Submittal 04/25/2008  06/06/2008  06/11/2008 
2 95% Submittal 08/10/2011  09/21/2011  09/23/2011 
1 Combined PSR/PR 01/29/2010  03/12/2010  03/17/2010 
2 Combined PSR/PR 03/29/2010  05/10/2010  05/19/2010 
3* Combined PSR/PR 06/14/2011  07/26/2011  06/15/2011 
1* Drainage Report (Preliminary) 06/16/2008  07/28/2008  07/16/2008 
1 Geotechnical Design Report (Final) 07/17/2007  08/28/2007  08/07/2007 
2 Geotechnical Design Report (Final) 04/09/2008  05/21/2008  05/08/2008 
3 Geotechnical Design Report (Final) 06/13/2008  07/25/2008  08/05/2008 
4 Geotechnical Design Report (Final) 10/28/2008  12/09/2008  11/25/2008 
5* Geotechnical Design Report (Final) 12/23/2008  02/03/2009  02/09/2009 
1 Operations Analysis 03/03/2010  04/14/2010  06/02/2010 
2* Operations Analysis 07/29/2010  09/09/2010  09/16/2010 
1 Other 04/25/2008  06/06/2008  06/10/2008 
2* Other 05/08/2012  06/19/2012  05/24/2012 
3* Other 09/12/2012  10/24/2012  09/12/2012 
4* Other 09/12/2012  10/24/2012  10/18/2012 
1 Project Report (PR) 04/29/2008  06/10/2008  06/10/2008 
2 Project Report (PR) 10/28/2008  12/09/2008  11/20/2008 
3 Project Report (PR) 12/23/2008  02/03/2009  02/09/2009 
4 Project Report (PR) 03/09/2009  04/20/2009  04/16/2009 
5 Project Report (PR) 05/04/2009  06/15/2009  06/17/2009 
1 Right of Way Data Sheets 12/23/2008  02/03/2009  02/09/2009 
2* Right of Way Data Sheets 03/09/2009  04/20/2009  04/15/2009 
1 SWDR - PA&ED 04/16/2008  05/28/2008  06/03/2008 
2 SWDR - PA&ED 12/23/2008  02/03/2009  02/09/2009 
3 SWDR - PA&ED 03/09/2009  04/20/2009  04/09/2009 
4* SWDR - PA&ED 05/04/2009  06/15/2009  06/17/2009 
1 SWDR - PS&E 09/15/2011  10/27/2011  10/11/2011 
2 SWDR - PS&E 06/15/2012  07/27/2012  07/16/2012 
3* SWDR - PS&E 07/23/2012  09/03/2012  08/06/2012 
1 TMP Datasheet (PA&ED) 12/23/2008  02/03/2009  02/09/2009 
2 TMP Datasheet (PA&ED) 03/09/2009  04/20/2009  04/09/2009 

* indicates document was approved.

’Comments anticipated to agency‘ date is based on a 6-week turnaround.