Review List for EA 08-1M750
Review No |
Review Type |
Received by Caltrans |
Comments anticipated to agency |
Comments sent to agency |
---|---|---|---|---|
1 | 100% Submittal | 01/25/2022 | 03/08/2022 | 02/08/2022 |
1 | 95% Submittal | 12/13/2021 | 01/24/2022 | 12/30/2021 |
1 | Design Standard Decision Document | 11/12/2021 | 12/24/2021 | 12/02/2021 |
2 | Design Standard Decision Document | 12/20/2021 | 01/31/2022 | 01/06/2022 |
3 | Design Standard Decision Document | 01/26/2022 | 03/09/2022 | 02/10/2022 |
1 | Drainage Report (Final) | 01/06/2022 | 02/17/2022 | 01/18/2022 |
2 | Drainage Report (Final) | 01/28/2022 | 03/11/2022 | Pending |
1 | Geotechnical Design Report (Final) | 12/13/2021 | 01/24/2022 | 12/29/2021 |
2 | Geotechnical Design Report (Final) | 01/25/2022 | 03/08/2022 | 02/08/2022 |
1 | Materials Report (Final) | 12/13/2021 | 01/24/2022 | 12/28/2021 |
2 | Materials Report (Final) | 01/25/2022 | 03/08/2022 | 02/08/2022 |
1 | Operations Analysis | 12/10/2021 | 01/21/2022 | 12/20/2021 |
1 | Other | 11/25/2021 | 01/06/2022 | 12/09/2021 |
2 | Other | 12/13/2021 | 01/24/2022 | 12/28/2021 |
3 | Other | 01/25/2022 | 03/08/2022 | 02/08/2022 |
4 | Other | 01/26/2022 | 03/09/2022 | 02/10/2022 |
1 | SWDR - PS&E | 01/06/2022 | 02/17/2022 | 01/19/2022 |
2 | SWDR - PS&E | 01/28/2022 | 03/11/2022 | 02/16/2022 |
* indicates document was approved.
’Comments anticipated to agency‘ date is based on a 6-week turnaround.