Review List for EA 08-20320

Review
No
Review Type
 
Received by
Caltrans
Comments anticipated
to agency
Comments sent
to agency
1 95% Submittal 05/15/2008  06/26/2008  07/14/2008 
2 95% Submittal 12/19/2008  01/30/2009  02/10/2009 
3* 95% Submittal 03/12/2009  04/23/2009  03/19/2009 
1 Drainage Report (Final) 05/15/2008  06/26/2008  06/18/2008 
2 Drainage Report (Final) 12/18/2008  01/29/2009  02/23/2009 
3* Drainage Report (Final) 03/12/2009  04/23/2009  03/19/2009 
1 Fact Sheet (Advisory) 05/15/2008  06/26/2008  06/26/2008 
1 Fact Sheet (Mandatory) 05/15/2008  06/26/2008  06/26/2008 
1* Fact Sheet (Supp/Mandatory) 09/17/2008  10/29/2008  09/29/2008 
1 Geotechnical Design Report (Final) 05/15/2008  06/26/2008  06/23/2008 
2* Geotechnical Design Report (Final) 03/12/2009  04/23/2009  03/19/2009 
1 Materials Report (Final) 05/15/2008  06/26/2008  06/18/2008 
2* Materials Report (Final) 03/12/2009  04/23/2009  03/19/2009 
1 Other 05/24/2010  07/05/2010  06/28/2010 
1 SWDR - PS&E 05/15/2008  06/26/2008  06/23/2008 
2 SWDR - PS&E 12/19/2008  01/30/2009  02/17/2009 
3* SWDR - PS&E 03/12/2009  04/23/2009  03/19/2009 
1 TMP Datasheet (PS&E) 05/15/2008  06/26/2008  06/10/2008 
2 TMP Datasheet (PS&E) 03/12/2009  04/23/2009  03/19/2009 

* indicates document was approved.

’Comments anticipated to agency‘ date is based on a 6-week turnaround.