Review List for EA 08-1N960

Review
No
Review Type
 
Received by
Caltrans
Comments anticipated
to agency
Comments sent
to agency
1 60% Submittal 09/27/2023  11/08/2023  10/15/2023 
1 95% Submittal 09/27/2023  11/08/2023  11/30/2023 
1 CEM1302 Positive Work Zone Protection 11/28/2023  01/09/2024  12/12/2023 
1* Project Report (PR) 09/15/2023  10/27/2023  09/29/2023 

* indicates document was approved.