Review List for EA 08-46350

Review
No
Review Type
 
Received by
Caltrans
Comments anticipated
to agency
Comments sent
to agency
1 60% Submittal 04/10/2006  05/22/2006  06/23/2006 
1 95% Submittal 01/16/2008  02/27/2008  02/27/2008 
2 95% Submittal 04/14/2008  05/26/2008  05/30/2008 
3 95% Submittal 07/28/2008  09/08/2008  09/17/2008 
4* 95% Submittal 10/22/2008  12/03/2008  11/24/2008 
1 Drainage Report (Final) 01/15/2008  02/26/2008  02/27/2008 
2* Drainage Report (Final) 04/16/2008  05/28/2008  05/13/2008 
1 Fact Sheet (Advisory) 01/06/2006  02/17/2006  01/31/2006 
1 Geotechnical Design Report (Final) 03/07/2006  04/18/2006  05/16/2006 
1 Materials Report (Final) 03/07/2006  04/18/2006  05/16/2006 
2 Materials Report (Final) 01/15/2008  02/26/2008  02/27/2008 
3 Materials Report (Final) 04/16/2008  05/28/2008  05/30/2008 
4 Materials Report (Final) 07/28/2008  09/08/2008  09/17/2008 
5* Materials Report (Final) 10/29/2008  12/10/2008  11/06/2008 
1 Right of Way Requirements 03/01/2006  04/12/2006  03/20/2007 
1 Slope Approval Letter 09/20/2006  11/01/2006  10/10/2006 
1 SWDR - PS&E 01/15/2008  02/26/2008  02/27/2008 
2 SWDR - PS&E 04/16/2008  05/28/2008  05/13/2008 
3* SWDR - PS&E 07/28/2008  09/08/2008  09/19/2008 
1 TMP Datasheet (PS&E) 01/15/2008  02/26/2008  02/27/2008 

* indicates document was approved.