Review List for Proj Num ATPL-5307 (024)

Latest Comment: Progress invoice #5R (CON & CON-E) sent to LPA. Invoice updated due to PE Phase lapse of the expenditure deadline. - (01/09/2019) see comment history...

Review
No
Review Type
 
Received by
Caltrans
Comments anticipated
to agency
Comments sent
to agency
1 Environmental Document 03/07/2017  04/18/2017  Pending 
2 Environmental Document 04/07/2017  05/19/2017  Pending 
1 Preliminary Environmental Study (PES) 06/22/2016  08/03/2016  Pending 
1 Right of Way Certification 04/07/2017  05/19/2017  Pending 
2 Right of Way Certification 05/11/2017  06/22/2017  Pending 

* indicates document was approved.

’Comments anticipated to agency‘ date is based on a 6-week turnaround.