Comment History for CMSTPLN-6208 (018)

Go to Project Reviews

Entry Date Activity/Comments
08/21/2023 in the new WPS
04/04/2023 HOT TOPIC: PM to work with Budgets (not Local Assistance) to provide the final calculations, work on project restructure and final reconciliation to cover the overruns from 3 phase to 4 phase in CMAQ.

(CT PM Nassim was working with Ian Eickenhorst at one point).)

Additionally,
PM to work on the BAR for the Lapsed SBV funds.

PM was working on a coop amendment.

Right of Way (Shenequa) to provide revised Parcel Listing (if needed) to match Budgets Calculations.

PM to submit to Local Assistance the Cost Adj E76 Package for processing and recommendation for Project Close-Out.
02/09/2017 CWA Cycle 14 Time Extension request approved by DOF. New reversion date is 06-30-2019. Agency notified.
10/07/2015 Files returned to D8.
09/25/2013 Project files to Sean for transfer PM.
09/16/2013 E-76 Seq 3 8/13/2013 AC Conversion sent to PM and local agency.
09/13/2013 E-76 approved in FMIS.
09/09/2013 Request award info to PM for enter in LP2000.
08/20/2013 E-76 to HQ.
08/19/2013 Received hard copy of FL + Estimate
08/15/2013 Request to PM official hard copies of the estimate and Local Assistance Finance letter. Other comments, see e-mail dated 8/15/2013.
08/14/2013 Request for project status.
08/05/2013 Follow-up with SANBAG. Estimate reviewed at HQ. New estimated due to Local Assistance on 8/7/2013.
07/31/2013 Telecon with SANBAG discuss estimate.
07/29/2013 Comments on Finance letter and Estimate (Capital) obtained from FADS. Request PM and SANBAG to check previously submitted to FHWA to authorize the E-76 for Local Assistance and Capital. Sent marked up estimate generated by Capital submitted with E-76. Suggested to use original format sent with previous E-76. Attached CMAQ items provided by SANBAG w/ corrected the cost per award. the bid. Sent of FL for Local and Capital. Request to check Supplemental and State Furnished. Cost was not provided to Local Assistance. Cost was just listed in the FL 4-4-2013 with no back-up.
07/23/2013
04/16/2013 E-76 Rejected: HQ detail estimate does not reconcile with Funding amend 3 submitted to Local Assistance. HQ issue with RR will check with D8 PM. No update to date for Local to be able to process AC conversion.
04/04/2013 Received corrected FL. Show federal participating as $37M.
04/04/2013 Question from HQ difference in CMIA COOP Vs. FL. COOP 08-1530 funding summary show total of $15,460,000. Finance letter shows $18,357,000. Increase in CAPITAL Support in the new finance letter to $7,134,000. Increased by 3M.
04/03/2013 Question from HQ. Federal Participating in the FL ($34M) does not match back-up ($37M).
04/02/2013 Update on status sent to SANBAG + Caltrans Management.
03/21/2013 Discussed with SANBAG HOV CMAQ participating items. SANBAG clarified becaus project consists of three separate projects: HOV, PROJECT II, and SHOPP, only $34,820,443 is Federally participating for the HOV Project.
03/21/2013 E-76 submitted for Approval.
02/26/2013 The CMAQ eligible participating items needs to be identified to equal $34,727,211 as listed in the NEW finance letter.
02/25/2013 Request clarification. Breakdown for the supplemental work,
contingency calculation, trainees cost from $30,000 to $8,828,700,
breakdown on the agency furnished material, Agency furnished material reduced from $9,291,200 to $441,008. Reference attached
Finance letter (02-13-2013 Finance Letter.pdf) to convert funds.
Finance letter (08-15-2012 6208(018)FIN.pdf) and estimate (07-12-2012 6208(018)EST.pdf) submitted to FHWA to authorized the project.
02/06/2013 Need to submit for fund conversion: Bid Summary, Detail Estimate, Agreement Checklist and Finance letter converting funds.
02/06/2013 Sent award package requirements (Bid summary, Detail Estimate, Agreement Checklist, FL) to PM.
02/06/2013 Per e-mail from SANBAG (AZ) i-County finance letter should show lump sum for both capital and support.
02/05/2013 Meeting to discuss CMAQ AC conversion. Accounting will not open phase until Federal funds for support (CE) are converted.
08/20/2012 Notice to Proceed issued to PM.
08/16/2012 E-76 Approval
07/23/2012 E-Copy of RFA to SANBAG, PM, Fred.
07/19/2012 E-76 to HQ.
06/19/2012 Returned package to SANBAG for revision.
05/22/2012 Sent courtesy comments on RFA dated 5/7/2012. Request segregate CMAQ eligible items.
05/09/2012 Mail Received: RFA CON received dated 5/7/2012
04/16/2012 Mail Received: Field Review form received

* indicates document was approved.