Comment History for CML-5452 (017)
Go to Project Reviews
Entry Date | Activity/Comments |
---|---|
01/31/2023 | Project Final Invoice and Close-Out Package submitted to CLPA. |
01/19/2023 | Mail Received: FROE; Received 01/19/2023 |
01/19/2023 | Mail Received: Final Invoice No.7; Received 01/19/23 |
12/28/2022 | Mail Received: Approved FL; Received 12/27/2022 |
12/21/2022 | Mail Received: FROE; Received 12/20/2022 |
03/14/2022 | Invoice no.6A sent to CLPA 3/9/2022 |
03/10/2022 | Mail Received: progress invoice 6A; received on 3/9/2022. |
03/04/2022 | Mail Received: approved FL; received on 3/4/2022. |
03/04/2022 | Mail Received: progress invoice 6A; received on 3/2/2022. |
02/10/2022 | Mail Received: progress invoice 5A; received on 2/9/2022. |
02/09/2022 | Invoice no.5A sent to CLPA 2/09/2022 |
02/07/2022 | Mail Received: progress invoice 5; received on 2/1/2022. |
01/19/2022 | Invoice no.4A sent to CLPA 01/19/2022 |
01/19/2022 | Mail Received: progress invoice 4A; received on 1/19/2022. |
01/12/2022 | Mail Received: progress invoice 3; received on 1/11/2022. |
12/21/2021 | Invoice no.3 sent to CLPA 12/21/2021 |
12/15/2021 | Mail Received: progress invoice 3; received on 12/14/2021. |
09/27/2021 | Progress invoice 2 sent to LPA |
09/24/2021 | Mail Received: progress invoice 2; received on 9/21/2021. |
09/03/2021 | Mail Received: final invoice 1; received on 8/31/2021. |
08/31/2021 | Progress Invoice No. 1 sent to LPA. |
07/07/2021 | Mail Received: RFA CON PED; received on 7/2/2021. |
06/17/2021 | Mail Received: award package; received on 6/15/2021. |
03/10/2021 | Mail Received: approved PSA & FL; received on 3/10/2021. |
02/28/2021 | Mail Received: PSE & support documents; received on 2/25/2021. |
02/22/2021 | Sent E-76 CON PED Extension Approval Letter to Agency. |
02/01/2021 | Mail Received: RFA PED; received on 1/28/2021. |
01/28/2021 | After Receiving the Revised RFA for PED extension, It was submitted to HQ. |
12/17/2020 | Mail Received: RFA PED extension; Electronic Submittal. |
11/19/2020 | Mail Received: RFA CON; to staff and V-drive. |
06/07/2019 | E-76 CON Approved by HQ & FHWA. Provided E-76 to agency (Jamie Carone) via email. To mail formal letter this week. |
12/05/2018 | Mail Received: DLAP signs Reval for Construction |
11/16/2018 | Mail Received: RFA Con, 1 original, 0 copy. |
10/02/2017 | DLAP signed CE/CE Determination Form |
08/08/2017 | Mail Received: Air Qualityn Technical Report (transmittal memo states 2 copies), 1 copy, 0 original. |
06/15/2017 | Mail Received: Air Quality Report, 2 copies, 0 original. |
05/08/2017 | Mail Received: Air Qulaity Report, 2 copies, 0 original. |
05/03/2017 | Mail Received: Air Quality Report, 3 copies, 0 original. |
12/13/2016 | Mail Received: AQR, 3 originals |
03/22/2016 | Mail Received: HPSR, 4 copies, 0 originals. LA memo attached |
03/09/2016 | Mail Received: APE Map, 1 original, 0 copy. |
10/22/2015 | Mail Received: HPSR, 3 copies, 1 original. LA memo attached |
07/14/2015 | Mail Received: HPSR, 3 copies, 0 originals to Enviormental |
05/11/2015 | Mail Received: Historic Property Survey Rpt. 3 copies, 0 originals, to Enviormental |
03/04/2015 | Mail Received: HPSR, ASR, APE Map, collected by Environmental |
07/10/2014 | Mail Received: Received HPSR, 3 copies sent to ENV |
07/10/2014 | Mail Received: Received final HPSR, send to ENV |
05/04/2014 | Mail Received: Received ISA checklist, sent to ENV |
03/28/2014 | Mail Received: Received APE mapes, 3 copies and copy of approved PES |
03/28/2014 | Mail Received: PES |
03/10/2014 | Mail Received: Received Revised 7B as requested. |
11/25/2013 | Mail Received: Received Right of Way Cert |
11/14/2013 | Mail Received: Received PES, sent to ENV |