08/20/2021 | Mail Received: FROE; received on 8/16/2021. |
05/13/2021 | Progress Invoice No. 2 sent to LPA |
05/13/2021 | Mail Received: progress invoice 2; received on 5/13/2021. |
05/05/2021 | sent the revised allocation extension request back to Roberta Jensen |
04/22/2021 | Received approved Finance Letter |
04/22/2021 | Mail Received: approved FL: received on 4/21/2021. |
03/03/2021 | Mail Received: RFA CON adjust; received on 3/1/2021. |
12/10/2020 | Mail Received: progress invoice 1; to staff and V-drive. |
03/10/2020 | Mail Received: award package; 1 original, 1 copy. |
10/11/2019 | Mail Received: RFA CON; 1 original, 0 copy. |
05/15/2019 | Mail Received: DLAP signs Reval for Construction & Scope reduction |
02/19/2019 | Mail Received: R/W Cert. Signed by Senior R/W Agent |
01/17/2019 | Mail Received: RW Cert package; 1 original, 1 copy. |
12/13/2018 | Mail Received: HPSR,1 copy, 0 original, no date stamp per Cultural 106 unit. |
03/28/2018 | Mail Received: LHS & SFER (2 copies) |
02/07/2018 | DLAP signed PES |
01/29/2018 | Mail Received: PES Form, 1 original, 5 copies |