CALIFORNIA DEPARTMENT OF TRANSPORTATION - CONTRACT COST DATA

Select Item No. / Description Unit Dist Qty Unit
Price
Adj
Price
Total Bid Open
Date
Contract
No.
Bid M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 735 $179.00 $782.95 $131565.00 04-17-2001 04-261304 1    
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 610 $737.00 $3223.66 $449570.00 06-07-2001 07-194804 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 57 $100.00 $437.40 $5700.00 06-13-2001 04-181624 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 105 $50.00 $218.70 $5250.00 06-28-2001 07-195324 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 1450 $255.74 $1118.61 $370823.00 07-12-2001 07-129944 1 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 330 $40.00 $174.96 $13200.00 08-23-2001 07-190204 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 1100 $95.00 $415.53 $104500.00 09-06-2001 07-020484 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 11 49 $37.00 $161.84 $1813.00 09-06-2001 11-069104 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 27 $95.00 $415.53 $2565.00 09-19-2001 04-162724 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 210 $175.00 $765.46 $36750.00 09-20-2001 07-490614 1 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) CY 07 4710 $60.00 $262.44 $282600.00 11-01-2001 07-1069U4 1 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 1180 $130.00 $568.62 $153400.00 11-01-2001 07-201304 1 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 3540 $80.00 $349.92 $283200.00 11-15-2001 07-1760U4 1 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 270 $205.00 $896.68 $55350.00 11-28-2001 04-292844 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 440 $300.00 $1312.21 $132000.00 12-12-2001 04-226124 1 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 320 $200.00 $945.35 $64000.00 02-21-2002 07-191304 2 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 320 $140.00 $661.75 $44800.00 02-21-2002 07-191304 3 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 320 $190.00 $898.09 $60800.00 02-21-2002 07-191304 4 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 320 $78.00 $368.69 $24960.00 02-21-2002 07-191304 5 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 320 $145.00 $685.38 $46400.00 02-21-2002 07-191304 6 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 320 $185.00 $874.45 $59200.00 02-21-2002 07-191304 7 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 380 $200.00 $945.35 $76000.00 03-21-2002 07-4H5404 1    
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 380 $200.00 $945.35 $76000.00 03-21-2002 07-4H5404 2    
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 380 $205.00 $968.99 $77900.00 03-21-2002 07-4H5404 3    
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 380 $85.00 $401.78 $32300.00 03-21-2002 07-4H5404 4    
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 380 $200.00 $945.35 $76000.00 03-21-2002 07-4H5404 5    
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 380 $300.00 $1418.03 $114000.00 03-21-2002 07-4H5404 6    
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 380 $212.00 $1002.08 $80560.00 03-21-2002 07-4H5404 7    
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 69 $255.00 $1205.33 $17595.00 04-23-2002 04-443204 1    
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 69 $271.00 $1280.96 $18699.00 04-23-2002 04-443204 2    
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 69 $100.00 $472.68 $6900.00 04-23-2002 04-443204 3    
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 320 $140.00 $661.75 $44800.00 04-25-2002 07-191304 1 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 320 $137.00 $647.57 $43840.00 04-25-2002 07-191304 2 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 320 $120.00 $567.21 $38400.00 04-25-2002 07-191304 3 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 320 $78.00 $368.69 $24960.00 04-25-2002 07-191304 4 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 320 $165.00 $779.92 $52800.00 04-25-2002 07-191304 5 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 320 $140.00 $661.75 $44800.00 04-25-2002 07-191304 6 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 350 $152.00 $718.47 $53200.00 04-25-2002 07-4N2804 1    
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 350 $200.00 $945.35 $70000.00 04-25-2002 07-4N2804 2    
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 350 $224.00 $1058.80 $78400.00 04-25-2002 07-4N2804 3    
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 350 $150.00 $709.02 $52500.00 04-25-2002 07-4N2804 4    
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 350 $147.00 $694.84 $51450.00 04-25-2002 07-4N2804 5    
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 350 $300.00 $1418.03 $105000.00 04-25-2002 07-4N2804 6    
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 350 $680.00 $3214.21 $238000.00 04-25-2002 07-4N2804 7    
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 150 $330.00 $1559.84 $49500.00 05-15-2002 04-237604 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 150 $95.00 $449.04 $14250.00 05-15-2002 04-237604 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 11 1650 $118.00 $557.76 $194700.00 05-16-2002 11-243704 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 11 1650 $150.00 $709.02 $247500.00 05-16-2002 11-243704 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 11 1650 $154.01 $727.97 $254116.50 05-16-2002 11-243704 3 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 11 1650 $165.00 $779.92 $272250.00 05-16-2002 11-243704 4 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 11 1650 $190.00 $898.09 $313500.00 05-16-2002 11-243704 5 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 11 1650 $145.00 $685.38 $239250.00 05-16-2002 11-243704 6 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 11 1650 $200.00 $945.35 $330000.00 05-16-2002 11-243704 7 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 11 1650 $118.00 $557.76 $194700.00 05-16-2002 11-243704 8 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 260 $250.00 $1181.69 $65000.00 05-29-2002 04-175904 1 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 260 $300.00 $1418.03 $78000.00 05-29-2002 04-175904 2 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 260 $260.00 $1228.96 $67600.00 05-29-2002 04-175904 3 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 260 $110.00 $519.95 $28600.00 05-29-2002 04-175904 4 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 260 $165.00 $779.92 $42900.00 05-29-2002 04-175904 5 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 260 $110.00 $519.95 $28600.00 05-29-2002 04-175904 6 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 12 79 $47.46 $224.33 $3750.00 06-20-2002 12-0C9424 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 12 79 $250.00 $1181.69 $19750.00 06-20-2002 12-0C9424 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 12 79 $200.00 $945.35 $15800.00 06-20-2002 12-0C9424 3 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 12 79 $279.00 $1318.77 $22041.00 06-20-2002 12-0C9424 4 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 12 79 $400.00 $1890.71 $31600.00 06-20-2002 12-0C9424 5 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 5740 $116.00 $548.31 $665840.00 07-11-2002 07-147804 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 5740 $50.00 $236.34 $287000.00 07-11-2002 07-147804 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 5740 $100.00 $472.68 $574000.00 07-11-2002 07-147804 3 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 5740 $145.00 $685.38 $832300.00 07-11-2002 07-147804 4 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 5740 $140.00 $661.75 $803600.00 07-11-2002 07-147804 5 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 05 1580 $124.00 $586.12 $195920.00 07-16-2002 05-430114 1   TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 11 2030 $162.00 $765.74 $328860.00 07-25-2002 11-075804 1 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 11 2030 $175.00 $827.19 $355250.00 07-25-2002 11-075804 2 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 11 2030 $210.00 $992.62 $426300.00 07-25-2002 11-075804 3 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 11 2030 $200.00 $945.35 $406000.00 07-25-2002 11-075804 4 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 120 $200.00 $945.35 $24000.00 08-06-2002 04-134764 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 120 $225.00 $1063.52 $27000.00 08-06-2002 04-134764 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 120 $137.00 $647.57 $16440.00 08-06-2002 04-134764 3 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 120 $500.00 $2363.39 $60000.00 08-06-2002 04-134764 4 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 590 $75.00 $354.51 $44250.00 08-29-2002 07-002104 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 590 $260.00 $1228.96 $153400.00 08-29-2002 07-002104 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 590 $138.00 $652.29 $81420.00 08-29-2002 07-002104 3 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 590 $200.00 $945.35 $118000.00 08-29-2002 07-002104 4 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 590 $115.00 $543.58 $67850.00 08-29-2002 07-002104 5 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 590 $80.00 $378.14 $47200.00 08-29-2002 07-002104 6 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 100 $210.00 $992.62 $21000.00 09-05-2002 07-008704 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 100 $150.00 $709.02 $15000.00 09-05-2002 07-008704 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 260 $150.00 $709.02 $39000.00 09-05-2002 07-220404 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 260 $50.00 $236.34 $13000.00 09-05-2002 07-220404 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 260 $190.00 $898.09 $49400.00 09-05-2002 07-220404 3 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 260 $100.00 $472.68 $26000.00 09-05-2002 07-220404 4 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 260 $102.50 $484.49 $26650.00 09-05-2002 07-220404 5 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 260 $200.00 $945.35 $52000.00 09-05-2002 07-220404 6 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 1800 $75.00 $354.51 $135000.00 09-12-2002 07-002354 1 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 1800 $85.00 $401.78 $153000.00 09-12-2002 07-002354 2 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 1800 $140.00 $661.75 $252000.00 09-12-2002 07-002354 3 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 1480 $125.00 $590.85 $185000.00 09-12-2002 07-053354 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 1480 $100.00 $472.68 $148000.00 09-12-2002 07-053354 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 2910 $105.00 $496.31 $305550.00 09-19-2002 07-020744 1 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 880 $75.00 $354.51 $66000.00 09-19-2002 07-496104 1 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 3370 $115.00 $543.58 $387550.00 09-26-2002 07-002534 1 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 3370 $75.00 $354.51 $252750.00 09-26-2002 07-002534 2 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 3370 $150.00 $709.02 $505500.00 09-26-2002 07-002534 3 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 1870 $130.00 $614.48 $243100.00 09-26-2002 07-1198U4 1 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 1870 $115.00 $543.58 $215050.00 09-26-2002 07-1198U4 2 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 1870 $120.00 $567.21 $224400.00 09-26-2002 07-1198U4 3 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 100 $180.00 $850.82 $18000.00 10-02-2002 04-219854 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 100 $132.00 $623.93 $13200.00 10-02-2002 04-219854 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 100 $305.00 $1441.67 $30500.00 10-02-2002 04-219854 3 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 100 $140.00 $661.75 $14000.00 10-02-2002 04-219854 4 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 100 $260.00 $1228.96 $26000.00 10-02-2002 04-219854 5 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 100 $212.00 $1002.08 $21200.00 10-02-2002 04-219854 6 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 100 $50.00 $236.34 $5000.00 10-02-2002 04-219854 7 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 22 $125.00 $590.85 $2750.00 10-03-2002 07-0535C4 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 22 $350.00 $1654.37 $7700.00 10-03-2002 07-0535C4 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 22 $600.00 $2836.06 $13200.00 10-03-2002 07-0535C4 3 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 22 $160.00 $756.28 $3520.00 10-03-2002 07-0535C4 4 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 22 $400.00 $1890.71 $8800.00 10-03-2002 07-0535C4 5 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 3140 $90.00 $425.41 $282600.00 10-03-2002 07-061744 1 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 3140 $100.00 $472.68 $314000.00 10-03-2002 07-061744 2 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 3140 $110.00 $519.95 $345400.00 10-03-2002 07-061744 3 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 3140 $100.00 $472.68 $314000.00 10-03-2002 07-061744 4 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 05 390 $69.40 $328.04 $27066.00 10-22-2002 05-462104 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 05 390 $454.25 $2147.14 $177157.50 10-22-2002 05-462104 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 05 390 $200.00 $945.35 $78000.00 10-22-2002 05-462104 3 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 05 390 $300.00 $1418.03 $117000.00 10-22-2002 05-462104 4 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 520 $300.00 $1418.03 $156000.00 11-14-2002 07-147904 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 30 $250.00 $1120.26 $7500.00 01-08-2003 04-2285U4 1 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 05 45 $100.00 $448.10 $4500.00 01-08-2003 05-314204 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 950 $190.00 $851.40 $180500.00 01-09-2003 07-053514 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 3755 $45.00 $201.65 $168975.00 01-23-2003 07-023144 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 270 $150.00 $672.16 $40500.00 02-25-2003 04-274204 1 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 490 $300.00 $1344.31 $147000.00 05-15-2003 07-120974 1 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 200 $210.00 $941.02 $42000.00 05-29-2003 07-4G5004 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 7 $600.00 $2688.62 $4200.00 05-29-2003 07-4H8604 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 10 1770 $163.00 $730.41 $288510.00 06-04-2003 10-0J2504 1    
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 2720 $125.65 $563.04 $341768.00 06-10-2003 04-272614 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 11 120 $200.00 $896.21 $24000.00 07-24-2003 11-245404 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 11 120 $200.00 $896.21 $24000.00 07-24-2003 11-245404 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 2150 $160.00 $716.97 $344000.00 08-28-2003 07-002304 1 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 2150 $100.00 $448.10 $215000.00 08-28-2003 07-002304 2 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 2150 $98.00 $439.14 $210700.00 08-28-2003 07-002304 3 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 2150 $130.00 $582.54 $279500.00 08-28-2003 07-002304 4 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 2150 $180.00 $806.59 $387000.00 08-28-2003 07-002304 5 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 2150 $258.00 $1156.11 $554700.00 08-28-2003 07-002304 6 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 2150 $120.00 $537.72 $258000.00 08-28-2003 07-002304 7 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 190 $130.00 $582.54 $24700.00 08-28-2003 07-101964 1 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 190 $152.00 $681.12 $28880.00 08-28-2003 07-101964 2 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 190 $130.00 $582.54 $24700.00 08-28-2003 07-101964 3 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 190 $96.20 $431.08 $18278.00 08-28-2003 07-101964 4 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 190 $30.00 $134.43 $5700.00 08-28-2003 07-101964 5 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 190 $100.00 $448.10 $19000.00 08-28-2003 07-101964 6 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 1530 $120.00 $537.72 $183600.00 09-04-2003 07-002594 1 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 1530 $92.00 $412.26 $140760.00 09-04-2003 07-002594 2 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 1530 $105.00 $470.51 $160650.00 09-04-2003 07-002594 3 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 1530 $200.00 $896.21 $306000.00 09-04-2003 07-002594 4 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 1530 $140.00 $627.35 $214200.00 09-04-2003 07-002594 5 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 390 $125.00 $560.13 $48750.00 10-09-2003 07-0510A4 1 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 390 $140.00 $627.35 $54600.00 10-09-2003 07-0510A4 2 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 390 $120.00 $537.72 $46800.00 10-09-2003 07-0510A4 3 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 390 $140.00 $627.35 $54600.00 10-09-2003 07-0510A4 4 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 390 $130.00 $582.54 $50700.00 10-09-2003 07-0510A4 5 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 390 $180.00 $806.59 $70200.00 10-09-2003 07-0510A4 6 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 10 280 $150.00 $672.16 $42000.00 11-18-2003 10-263414 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 10 280 $235.00 $1053.04 $65800.00 11-18-2003 10-263414 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 360 $150.00 $672.16 $54000.00 12-18-2003 07-0239A4 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 360 $61.00 $273.34 $21960.00 12-18-2003 07-0239A4 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 360 $140.00 $627.35 $50400.00 12-18-2003 07-0239A4 3 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 360 $170.00 $761.78 $61200.00 12-18-2003 07-0239A4 4 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 360 $125.00 $560.13 $45000.00 12-18-2003 07-0239A4 5 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 360 $185.00 $828.99 $66600.00 12-18-2003 07-0239A4 6 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 360 $200.00 $896.21 $72000.00 12-18-2003 07-0239A4 7 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 280 $235.00 $695.65 $65800.00 03-03-2004 04-239704 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 280 $180.00 $532.84 $50400.00 03-03-2004 04-239704 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 280 $175.00 $518.04 $49000.00 03-03-2004 04-239704 3 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 280 $200.00 $592.04 $56000.00 03-03-2004 04-239704 4 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 310 $150.00 $444.03 $46500.00 04-08-2004 07-023124 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 310 $135.00 $399.63 $41850.00 04-08-2004 07-023124 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 310 $111.00 $328.58 $34410.00 04-08-2004 07-023124 3 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 310 $123.00 $364.10 $38130.00 04-08-2004 07-023124 4 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 310 $140.00 $414.43 $43400.00 04-08-2004 07-023124 5 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 10 8 $1200.00 $3552.24 $9600.00 04-13-2004 10-0H0204 1    
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 10 8 $400.00 $1184.08 $3200.00 04-13-2004 10-0H0204 2    
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 10 8 $600.00 $1776.12 $4800.00 04-13-2004 10-0H0204 3    
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 2.5 $800.00 $2368.16 $2000.00 04-29-2004 07-208034 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 2.5 $1000.00 $2960.20 $2500.00 04-29-2004 07-208034 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 2.5 $500.00 $1480.10 $1250.00 04-29-2004 07-208034 3 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 2.5 $1122.00 $3321.35 $2805.00 04-29-2004 07-208034 4 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 2.5 $1500.00 $4440.30 $3750.00 04-29-2004 07-208034 5 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 92 $130.00 $384.83 $11960.00 06-10-2004 07-187504 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 92 $200.00 $592.04 $18400.00 06-10-2004 07-187504 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 92 $185.00 $547.64 $17020.00 06-10-2004 07-187504 3 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 58 $850.00 $2516.17 $49300.00 06-10-2004 07-4J9704 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 1300 $225.00 $666.05 $292500.00 06-30-2004 04-270704 1 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 1300 $160.00 $473.63 $208000.00 06-30-2004 04-270704 2 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 1300 $190.00 $562.44 $247000.00 06-30-2004 04-270704 3 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 1300 $200.00 $592.04 $260000.00 06-30-2004 04-270704 4 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 1300 $100.00 $296.02 $130000.00 06-30-2004 04-270704 5 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 1300 $140.00 $414.43 $182000.00 06-30-2004 04-270704 6 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 1300 $181.00 $535.80 $235300.00 06-30-2004 04-270704 7 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 85 $60.00 $177.61 $5100.00 07-21-2004 04-253404 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 85 $300.00 $888.06 $25500.00 07-21-2004 04-253404 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 54 $495.90 $1467.96 $26778.60 07-22-2004 07-234904 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 310 $140.00 $414.43 $43400.00 07-29-2004 07-1199U4 1 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 310 $150.00 $444.03 $46500.00 07-29-2004 07-1199U4 2 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 310 $155.00 $458.83 $48050.00 07-29-2004 07-1199U4 3 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 1500 $150.00 $444.03 $225000.00 09-09-2004 07-135104 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 1500 $55.00 $162.81 $82500.00 09-09-2004 07-135104 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 1500 $110.00 $325.62 $165000.00 09-09-2004 07-135104 3 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 11 870 $415.00 $1228.48 $361050.00 10-14-2004 11-207914 1 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 11 870 $65.00 $192.41 $56550.00 10-14-2004 11-207914 2 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 05 130 $175.00 $518.04 $22750.00 11-16-2004 05-474804 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 740 $340.00 $1006.47 $251600.00 12-16-2004 07-1661A4 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 270 $150.00 $444.03 $40500.00 12-16-2004 07-1693A4 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 270 $140.00 $414.43 $37800.00 12-16-2004 07-1693A4 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 270 $325.00 $962.07 $87750.00 12-16-2004 07-1693A4 3 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 270 $1090.00 $3226.62 $294300.00 12-16-2004 07-1693A4 4 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 770 $125.00 $322.47 $96250.00 01-06-2005 07-122004 1 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 770 $150.00 $386.96 $115500.00 01-06-2005 07-122004 2 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 03 620 $250.00 $644.94 $155000.00 01-25-2005 03-2A8304 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 03 620 $190.00 $490.15 $117800.00 01-25-2005 03-2A8304 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 03 620 $210.00 $541.75 $130200.00 01-25-2005 03-2A8304 3 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 03 620 $288.00 $742.97 $178560.00 01-25-2005 03-2A8304 4 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 03 620 $200.00 $515.95 $124000.00 01-25-2005 03-2A8304 5 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 03 620 $375.00 $967.41 $232500.00 01-25-2005 03-2A8304 6 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 230 $125.00 $322.47 $28750.00 03-01-2005 04-299204 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 230 $115.00 $296.67 $26450.00 03-01-2005 04-299204 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 230 $130.00 $335.37 $29900.00 03-01-2005 04-299204 3 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 230 $130.00 $335.37 $29900.00 03-01-2005 04-299204 4 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 230 $170.00 $438.56 $39100.00 03-01-2005 04-299204 5 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 230 $200.00 $515.95 $46000.00 03-01-2005 04-299204 6 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 10 74 $166.90 $430.56 $12350.60 03-01-2005 10-0J5704 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 10 74 $150.00 $386.96 $11100.00 03-01-2005 10-0J5704 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 10 74 $310.00 $799.72 $22940.00 03-01-2005 10-0J5704 3 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 10 74 $45.00 $116.09 $3330.00 03-01-2005 10-0J5704 4 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 10 74 $240.00 $619.14 $17760.00 03-01-2005 10-0J5704 5 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 10 77 $300.00 $773.93 $23100.00 03-22-2005 10-0J8204 1    
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 10 77 $716.00 $1847.10 $55132.00 03-22-2005 10-0J8204 2    
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 10 77 $660.00 $1702.64 $50820.00 03-22-2005 10-0J8204 3    
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 10 77 $650.00 $1676.84 $50050.00 03-22-2005 10-0J8204 4    
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 10 77 $700.00 $1805.83 $53900.00 03-22-2005 10-0J8204 5    
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 90 $451.11 $1163.75 $40599.90 04-07-2005 07-1Y8604 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 90 $451.11 $1163.75 $40599.90 04-07-2005 07-1Y8604 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 90 $250.00 $644.94 $22500.00 04-07-2005 07-1Y8604 3 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 90 $400.00 $1031.90 $36000.00 04-07-2005 07-1Y8604 4 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 90 $250.00 $644.94 $22500.00 04-07-2005 07-1Y8604 5 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 90 $300.00 $773.93 $27000.00 04-07-2005 07-1Y8604 6 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 12 520 $200.00 $515.95 $104000.00 05-26-2005 12-0A7614 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 12 520 $160.00 $412.76 $83200.00 05-26-2005 12-0A7614 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 12 520 $150.00 $386.96 $78000.00 05-26-2005 12-0A7614 3 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 12 520 $263.00 $678.48 $136760.00 05-26-2005 12-0A7614 4 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 10 4130 $120.00 $309.57 $495600.00 06-07-2005 10-3A4304 1 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 10 4130 $140.00 $361.17 $578200.00 06-07-2005 10-3A4304 2 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 10 4130 $105.00 $270.87 $433650.00 06-07-2005 10-3A4304 3 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 10 4130 $95.00 $245.08 $392350.00 06-07-2005 10-3A4304 4 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 10 4130 $120.00 $309.57 $495600.00 06-07-2005 10-3A4304 5 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 18 $1080.00 $2786.13 $19440.00 08-04-2005 07-4K6704 1    
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 18 $525.00 $1354.37 $9450.00 08-04-2005 07-4K6704 2    
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 18 $300.00 $773.93 $5400.00 08-04-2005 07-4K6704 3    
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 18 $200.00 $515.95 $3600.00 08-04-2005 07-4K6704 4    
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 320 $160.00 $412.76 $51200.00 08-25-2005 07-242004 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 320 $225.00 $580.44 $72000.00 08-25-2005 07-242004 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 320 $260.00 $670.74 $83200.00 08-25-2005 07-242004 3 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 320 $300.00 $773.93 $96000.00 08-25-2005 07-242004 4 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 12 230 $260.00 $670.74 $59800.00 09-15-2005 12-099424 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 12 230 $175.00 $451.46 $40250.00 09-15-2005 12-099424 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 12 230 $300.00 $773.93 $69000.00 09-15-2005 12-099424 3 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 480 $140.00 $361.17 $67200.00 09-27-2005 04-299304 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 480 $110.00 $283.77 $52800.00 09-27-2005 04-299304 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 480 $218.00 $562.39 $104640.00 09-27-2005 04-299304 3 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 480 $180.00 $464.36 $86400.00 09-27-2005 04-299304 4 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 480 $250.00 $644.94 $120000.00 09-27-2005 04-299304 5 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 480 $253.00 $652.68 $121440.00 09-27-2005 04-299304 6 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 480 $69.00 $178.00 $33120.00 09-27-2005 04-299304 7 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 65 $400.00 $1031.90 $26000.00 09-29-2005 07-244504 1 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 65 $800.00 $2063.80 $52000.00 09-29-2005 07-244504 2 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 11 26 $300.00 $773.93 $7800.00 10-06-2005 11-240304 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 11 26 $120.00 $309.57 $3120.00 10-06-2005 11-240304 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 11 26 $1400.00 $3611.65 $36400.00 10-06-2005 11-240304 3 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 11 26 $1000.00 $2579.75 $26000.00 10-06-2005 11-240304 4 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 400 $200.00 $515.95 $80000.00 10-12-2005 04-151294 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 400 $280.00 $722.33 $112000.00 10-12-2005 04-151294 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 120 $300.00 $773.93 $36000.00 10-13-2005 07-182204 1 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 120 $850.00 $2192.79 $102000.00 10-13-2005 07-182204 2 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 11 230 $350.00 $902.91 $80500.00 10-13-2005 11-2379U4 1 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 11 38 $300.00 $773.93 $11400.00 10-13-2005 11-265404 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 380 $450.00 $1160.89 $171000.00 10-27-2005 07-120884 1 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 380 $450.00 $1160.89 $171000.00 10-27-2005 07-120884 2 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 380 $500.00 $1289.88 $190000.00 10-27-2005 07-120884 3 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 83 $350.00 $902.91 $29050.00 10-27-2005 07-120934 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 83 $288.00 $742.97 $23904.00 10-27-2005 07-120934 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 83 $4.10 $10.58 $340.30 10-27-2005 07-120934 3 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 05 1100 $256.40 $661.45 $282040.00 11-02-2005 05-448104 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 05 1100 $255.00 $657.84 $280500.00 11-02-2005 05-448104 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 05 1100 $205.00 $528.85 $225500.00 11-02-2005 05-448104 3 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 05 1100 $287.50 $741.68 $316250.00 11-02-2005 05-448104 4 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 130 $300.00 $773.93 $39000.00 11-03-2005 07-218304 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 130 $225.00 $580.44 $29250.00 11-03-2005 07-218304 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 10 620 $300.00 $773.93 $186000.00 11-16-2005 10-0H2004 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 35 $285.00 $735.23 $9975.00 11-29-2005 04-165934 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 740 $70.00 $180.58 $51800.00 12-01-2005 07-242604 1 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 740 $165.00 $425.66 $122100.00 12-01-2005 07-242604 2 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 50 $240.00 $619.14 $12000.00 12-14-2005 04-130524 1    
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 50 $400.00 $1031.90 $20000.00 12-14-2005 04-130524 2    
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 50 $191.00 $492.73 $9550.00 12-14-2005 04-130524 3    
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 380 $180.00 $448.56 $68400.00 01-05-2006 07-232604 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 380 $250.00 $623.00 $95000.00 01-05-2006 07-232604 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 380 $300.00 $747.60 $114000.00 01-05-2006 07-232604 3 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 380 $225.00 $560.70 $85500.00 01-05-2006 07-232604 4 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 05 650 $200.00 $498.40 $130000.00 01-24-2006 05-129104 1 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 05 650 $245.00 $610.54 $159250.00 01-24-2006 05-129104 2 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 05 650 $150.00 $373.80 $97500.00 01-24-2006 05-129104 3 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 05 650 $200.00 $498.40 $130000.00 01-24-2006 05-129104 4 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 05 650 $170.00 $423.64 $110500.00 01-24-2006 05-129104 5 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 66 $300.00 $747.60 $19800.00 01-31-2006 04-271604 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 66 $250.00 $623.00 $16500.00 01-31-2006 04-271604 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 66 $400.00 $996.80 $26400.00 01-31-2006 04-271604 3 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 225 $100.00 $249.20 $22500.00 02-07-2006 04-165944 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 225 $250.00 $623.00 $56250.00 02-07-2006 04-165944 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 225 $255.00 $635.46 $57375.00 02-07-2006 04-165944 3 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 225 $250.00 $623.00 $56250.00 02-07-2006 04-165944 4 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 2250 $165.00 $411.18 $371250.00 02-08-2006 04-246804 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 2250 $290.00 $722.68 $652500.00 02-08-2006 04-246804 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 2250 $250.00 $623.00 $562500.00 02-08-2006 04-246804 3 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 2250 $280.00 $697.76 $630000.00 02-08-2006 04-246804 4 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 2250 $325.00 $809.90 $731250.00 02-08-2006 04-246804 5 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 2250 $260.00 $647.92 $585000.00 02-08-2006 04-246804 6 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 12 11400 $150.00 $373.80 $1710000.00 02-09-2006 12-101674 1 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 12 11400 $143.00 $356.36 $1630200.00 02-09-2006 12-101674 2 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 12 11400 $140.00 $348.88 $1596000.00 02-09-2006 12-101674 3 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 250 $200.00 $498.40 $50000.00 02-15-2006 04-246934 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 250 $400.00 $996.80 $100000.00 02-15-2006 04-246934 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 250 $160.00 $398.72 $40000.00 02-15-2006 04-246934 3 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 250 $350.00 $872.20 $87500.00 02-15-2006 04-246934 4 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 250 $250.00 $623.00 $62500.00 02-15-2006 04-246934 5 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 11100 $135.00 $336.42 $1498500.00 03-02-2006 07-183114 1 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 1290 $140.00 $348.88 $180600.00 03-02-2006 07-224404 1 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 1290 $180.00 $448.56 $232200.00 03-02-2006 07-224404 2 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 1290 $150.00 $373.80 $193500.00 03-02-2006 07-224404 3 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 1290 $169.90 $423.39 $219171.00 03-02-2006 07-224404 4 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 1290 $138.00 $343.90 $178020.00 03-02-2006 07-224404 5 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 08 465 $196.00 $488.43 $91140.00 03-30-2006 08-474104 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 08 465 $70.00 $174.44 $32550.00 03-30-2006 08-474104 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 630 $650.00 $1619.80 $409500.00 04-26-2006 04-1A2404 1    
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 330 $200.00 $498.40 $66000.00 05-04-2006 07-4J0704 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 330 $215.00 $535.78 $70950.00 05-04-2006 07-4J0704 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 330 $225.00 $560.70 $74250.00 05-04-2006 07-4J0704 3 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 08 3480 $106.00 $264.15 $368880.00 05-04-2006 08-0C1804 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 08 3480 $100.00 $249.20 $348000.00 05-04-2006 08-0C1804 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 08 3480 $115.00 $286.58 $400200.00 05-04-2006 08-0C1804 3 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 08 3480 $110.00 $274.12 $382800.00 05-04-2006 08-0C1804 4 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 08 3480 $100.00 $249.20 $348000.00 05-04-2006 08-0C1804 5 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 1740 $200.00 $498.40 $348000.00 05-10-2006 04-272014 1 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 1740 $200.00 $498.40 $348000.00 05-10-2006 04-272014 2 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 11 230 $555.00 $1383.06 $127650.00 05-11-2006 11-2379U4 1 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 11 230 $260.00 $647.92 $59800.00 05-11-2006 11-2379U4 2 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 11 230 $330.00 $822.36 $75900.00 05-11-2006 11-2379U4 3 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 11 230 $975.00 $2429.71 $224250.00 05-11-2006 11-2379U4 4 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 10 1260 $205.00 $510.86 $258300.00 05-31-2006 10-0K5604 1    
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 10 1260 $240.00 $598.08 $302400.00 05-31-2006 10-0K5604 2    
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 10 670 $272.00 $677.83 $182240.00 06-07-2006 10-0K8704 1    
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 10 670 $290.00 $722.68 $194300.00 06-07-2006 10-0K8704 2    
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 10 670 $350.00 $872.20 $234500.00 06-07-2006 10-0K8704 3    
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 10 670 $275.00 $685.30 $184250.00 06-07-2006 10-0K8704 4    
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 1840 $150.00 $373.80 $276000.00 06-14-2006 04-470804 1 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 1840 $160.00 $398.72 $294400.00 06-14-2006 04-470804 2 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 1840 $180.00 $448.56 $331200.00 06-14-2006 04-470804 3 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 1840 $135.00 $336.42 $248400.00 06-14-2006 04-470804 4 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 1840 $150.00 $373.80 $276000.00 06-14-2006 04-470804 5 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 10 1990 $200.00 $498.40 $398000.00 06-27-2006 10-0F3004 1 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 10 1990 $175.00 $436.10 $348250.00 06-27-2006 10-0F3004 2 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 10 1990 $259.00 $645.43 $515410.00 06-27-2006 10-0F3004 3 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 10 1990 $179.00 $446.07 $356210.00 06-27-2006 10-0F3004 4 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 50 $686.00 $1709.52 $34300.00 08-24-2006 07-1P5704 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 50 $400.00 $996.80 $20000.00 08-24-2006 07-1P5704 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 50 $1000.00 $2492.01 $50000.00 08-24-2006 07-1P5704 3 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 710 $189.00 $470.99 $134190.00 08-24-2006 07-232304 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 710 $235.00 $585.62 $166850.00 08-24-2006 07-232304 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 710 $260.00 $647.92 $184600.00 08-24-2006 07-232304 3 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 360 $300.00 $747.60 $108000.00 08-30-2006 04-0A1304 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 360 $1100.00 $2741.21 $396000.00 08-30-2006 04-0A1304 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 360 $265.00 $660.38 $95400.00 08-30-2006 04-0A1304 3 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) TONN 01 7970 $130.00 $323.96 $1036100.00 09-19-2006 01-438404 1 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) TONN 01 7970 $120.00 $299.04 $956400.00 09-19-2006 01-438404 2 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 70 $220.00 $548.24 $15400.00 10-26-2006 07-218304 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 70 $200.00 $498.40 $14000.00 10-26-2006 07-218304 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 70 $143.15 $356.73 $10020.50 10-26-2006 07-218304 3 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 70 $539.57 $1344.61 $37769.90 10-26-2006 07-218304 4 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 70 $300.00 $747.60 $21000.00 10-26-2006 07-218304 5 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 08 465 $326.00 $812.39 $151590.00 10-26-2006 08-474104 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 08 465 $212.00 $528.31 $98580.00 10-26-2006 08-474104 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 08 465 $200.00 $498.40 $93000.00 10-26-2006 08-474104 3 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 6590 $260.00 $647.92 $1713400.00 11-14-2006 04-270834 1 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 6590 $235.00 $585.62 $1548650.00 11-14-2006 04-270834 2 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 6590 $200.00 $498.40 $1318000.00 11-14-2006 04-270834 3 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 6590 $320.00 $797.44 $2108800.00 11-14-2006 04-270834 4 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 6590 $200.00 $498.40 $1318000.00 11-14-2006 04-270834 5 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 740 $275.00 $685.30 $203500.00 11-16-2006 07-1661A4 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 740 $340.00 $847.28 $251600.00 11-16-2006 07-1661A4 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 740 $180.00 $448.56 $133200.00 11-16-2006 07-1661A4 3 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 740 $220.00 $548.24 $162800.00 11-16-2006 07-1661A4 4 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 740 $200.00 $498.40 $148000.00 11-16-2006 07-1661A4 5 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 740 $215.00 $535.78 $159100.00 11-16-2006 07-1661A4 6 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 6790 $170.00 $423.64 $1154300.00 11-28-2006 04-264204 1 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 1500 $230.00 $573.16 $345000.00 11-29-2006 04-246804 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 1500 $335.00 $834.82 $502500.00 11-29-2006 04-246804 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 1500 $295.00 $735.14 $442500.00 11-29-2006 04-246804 3 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 1500 $275.00 $685.30 $412500.00 11-29-2006 04-246804 4 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 1500 $425.00 $1059.10 $637500.00 11-29-2006 04-246804 5 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 1250 $120.00 $300.57 $150000.00 01-03-2007 04-2937U4 1 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 1250 $185.00 $463.39 $231250.00 01-03-2007 04-2937U4 2 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 1250 $240.00 $601.15 $300000.00 01-03-2007 04-2937U4 3 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 1250 $180.00 $450.86 $225000.00 01-03-2007 04-2937U4 4 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 1250 $240.00 $601.15 $300000.00 01-03-2007 04-2937U4 5 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 1250 $175.00 $438.34 $218750.00 01-03-2007 04-2937U4 6 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 1250 $30.00 $75.14 $37500.00 01-03-2007 04-2937U4 7 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 1250 $300.00 $751.44 $375000.00 01-03-2007 04-2937U4 8 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 1250 $193.00 $483.42 $241250.00 01-03-2007 04-2937U4 9 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 1250 $275.00 $688.82 $343750.00 01-03-2007 04-2937U4 10 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 4400 $135.00 $338.15 $594000.00 01-11-2007 07-188504 1 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 4400 $100.00 $250.48 $440000.00 01-11-2007 07-188504 2 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 4400 $122.00 $305.58 $536800.00 01-11-2007 07-188504 3 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 4400 $100.00 $250.48 $440000.00 01-11-2007 07-188504 4 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 1900 $245.00 $613.67 $465500.00 01-24-2007 04-270524 1 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 1900 $350.00 $876.68 $665000.00 01-24-2007 04-270524 2 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 1900 $225.00 $563.58 $427500.00 01-24-2007 04-270524 3 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 1900 $260.00 $651.24 $494000.00 01-24-2007 04-270524 4 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 1200 $175.00 $438.34 $210000.00 02-28-2007 04-1A9904 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 1200 $175.00 $438.34 $210000.00 02-28-2007 04-1A9904 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 1200 $235.00 $588.62 $282000.00 02-28-2007 04-1A9904 3 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 1200 $245.00 $613.67 $294000.00 02-28-2007 04-1A9904 4 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 1200 $250.00 $626.20 $300000.00 02-28-2007 04-1A9904 5 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 1200 $245.00 $613.67 $294000.00 02-28-2007 04-1A9904 6 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 1200 $200.00 $500.96 $240000.00 02-28-2007 04-1A9904 7 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 1200 $365.00 $914.25 $438000.00 02-28-2007 04-1A9904 8 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 11 300 $285.00 $713.86 $85500.00 03-01-2007 11-271204 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 11 300 $220.00 $551.05 $66000.00 03-01-2007 11-271204 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 11 300 $385.00 $964.34 $115500.00 03-01-2007 11-271204 3 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 11 300 $272.00 $681.30 $81600.00 03-01-2007 11-271204 4 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 500 $202.00 $505.97 $101000.00 03-07-2007 04-269604 1 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 500 $250.00 $626.20 $125000.00 03-07-2007 04-269604 2 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 500 $400.00 $1001.91 $200000.00 03-07-2007 04-269604 3 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 500 $125.00 $313.10 $62500.00 03-07-2007 04-269604 4 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 500 $265.00 $663.77 $132500.00 03-07-2007 04-269604 5 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 500 $440.00 $1102.11 $220000.00 03-07-2007 04-269604 6 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 500 $250.00 $626.20 $125000.00 03-07-2007 04-269604 7 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 04 500 $400.00 $1001.91 $200000.00 03-07-2007 04-269604 8 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 7670 $150.00 $375.72 $1150500.00 05-10-2007 07-183114 1 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 7670 $150.00 $375.72 $1150500.00 05-10-2007 07-183114 2 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 34 $200.00 $500.96 $6800.00 05-10-2007 07-4K4704 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 34 $225.00 $563.58 $7650.00 05-10-2007 07-4K4704 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 34 $325.00 $814.06 $11050.00 05-10-2007 07-4K4704 3 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 34 $430.00 $1077.06 $14620.00 05-10-2007 07-4K4704 4 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 34 $176.00 $440.84 $5984.00 05-10-2007 07-4K4704 5 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 02 140 $325.00 $814.06 $45500.00 06-06-2007 02-1C4004 1    
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 02 140 $340.00 $851.63 $47600.00 06-06-2007 02-1C4004 2    
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 02 140 $440.00 $1102.11 $61600.00 06-06-2007 02-1C4004 3    
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 02 140 $450.00 $1127.15 $63000.00 06-06-2007 02-1C4004 4    
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 440 $275.00 $688.82 $121000.00 06-28-2007 07-129934 1 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 440 $332.50 $832.84 $146300.00 06-28-2007 07-129934 2 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 440 $320.00 $801.53 $140800.00 06-28-2007 07-129934 3 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 440 $400.00 $1001.91 $176000.00 06-28-2007 07-129934 4 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 440 $260.00 $651.24 $114400.00 06-28-2007 07-129934 5 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 440 $350.00 $876.68 $154000.00 06-28-2007 07-129934 6 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 440 $355.00 $889.20 $156200.00 06-28-2007 07-129934 7 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 05 1240 $165.00 $413.29 $204600.00 08-22-2007 05-402804 1 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 05 1240 $100.00 $250.48 $124000.00 08-22-2007 05-402804 2 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 05 1240 $120.00 $300.57 $148800.00 08-22-2007 05-402804 3 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 05 1240 $200.00 $500.96 $248000.00 08-22-2007 05-402804 4 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 240 $235.00 $588.62 $56400.00 08-23-2007 07-241404 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 240 $275.00 $688.82 $66000.00 08-23-2007 07-241404 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 240 $220.00 $551.05 $52800.00 08-23-2007 07-241404 3 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 240 $185.00 $463.39 $44400.00 08-23-2007 07-241404 4 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 240 $200.00 $500.96 $48000.00 08-23-2007 07-241404 5 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 240 $330.00 $826.58 $79200.00 08-23-2007 07-241404 6 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 240 $300.00 $751.44 $72000.00 08-23-2007 07-241404 7 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 240 $315.00 $789.01 $75600.00 08-23-2007 07-241404 8 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 240 $400.00 $1001.91 $96000.00 08-23-2007 07-241404 9 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 240 $183.00 $458.38 $43920.00 08-23-2007 07-241404 10 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 240 $200.00 $500.96 $48000.00 08-23-2007 07-241404 11 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 12 1660 $150.00 $375.72 $249000.00 08-30-2007 12-0A7624 1 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 12 1660 $157.00 $393.25 $260620.00 08-30-2007 12-0A7624 2 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 12 1660 $150.00 $375.72 $249000.00 08-30-2007 12-0A7624 3 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 12 1660 $180.00 $450.86 $298800.00 08-30-2007 12-0A7624 4 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 12 1660 $175.00 $438.34 $290500.00 08-30-2007 12-0A7624 5 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 12 1660 $100.00 $250.48 $166000.00 08-30-2007 12-0A7624 6 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 12 1660 $163.00 $408.28 $270580.00 08-30-2007 12-0A7624 7 M TRO
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 12 2000 $230.00 $576.10 $460000.00 09-06-2007 12-078004 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 12 2000 $169.93 $425.64 $339860.00 09-06-2007 12-078004 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 12 2000 $170.00 $425.81 $340000.00 09-06-2007 12-078004 3 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 12 2000 $200.00 $500.96 $400000.00 09-06-2007 12-078004 4 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 12 2000 $170.00 $425.81 $340000.00 09-06-2007 12-078004 5 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 12 2000 $225.00 $563.58 $450000.00 09-06-2007 12-078004 6 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 12 2000 $178.00 $445.85 $356000.00 09-06-2007 12-078004 7 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 12 2000 $155.00 $388.24 $310000.00 09-06-2007 12-078004 8 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 12 2000 $300.90 $753.69 $601800.00 09-06-2007 12-078004 9 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 05 470 $85.00 $212.91 $39950.00 09-12-2007 05-460704 1 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 05 470 $150.00 $375.72 $70500.00 09-12-2007 05-460704 2 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 05 470 $240.00 $601.15 $112800.00 09-12-2007 05-460704 3 M  
190105 - ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) M3 07 190 $170.00 $425.81 $32300.00 10-25-2007 07-231404 1 M TRO
MORE THAN 500 RESULTS RETURNED. ONLY 500 ROWS SHOWN.
SUMMARY Unmodified Adjusted    
Average Price/Unit: $ Avg No. Units
Std Dev. (of Unit Price): ±$ Rows Selected
Weighted Avg.: $ Rows Returned
Minimum Price/Unit: $    
Maximum Price/Unit: $    

| Back | New Search |

PARAMETERS: Item = 190105; District=All; Year=All; Convert=No; Bidders=All Bidders
TIMESTAMP: 11/13/2026 05:28:47
CURRENT 12-MO INDEX (CHCCI (2020 Base)): 146.53