| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
10 |
110 |
$290.00 |
$1268.47 |
$31900.00 |
12-04-2001 |
10-2A5904 |
1 |
|
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
04 |
530 |
$200.00 |
$945.35 |
$106000.00 |
12-11-2002 |
04-173304 |
1 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
04 |
130 |
$250.00 |
$1120.26 |
$32500.00 |
01-08-2003 |
04-2285U4 |
1 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
04 |
480 |
$300.00 |
$1344.31 |
$144000.00 |
09-23-2003 |
04-270304 |
1 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
04 |
480 |
$100.00 |
$448.10 |
$48000.00 |
09-23-2003 |
04-270304 |
2 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
04 |
480 |
$288.00 |
$1290.54 |
$138240.00 |
09-23-2003 |
04-270304 |
3 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
04 |
480 |
$440.00 |
$1971.66 |
$211200.00 |
09-23-2003 |
04-270304 |
4 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
04 |
480 |
$270.00 |
$1209.88 |
$129600.00 |
09-23-2003 |
04-270304 |
5 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
0.5 |
$6000.00 |
$17761.21 |
$3000.00 |
04-29-2004 |
07-208034 |
1 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
0.5 |
$1000.00 |
$2960.20 |
$500.00 |
04-29-2004 |
07-208034 |
2 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
0.5 |
$500.00 |
$1480.10 |
$250.00 |
04-29-2004 |
07-208034 |
3 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
0.5 |
$4600.00 |
$13616.93 |
$2300.00 |
04-29-2004 |
07-208034 |
4 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
0.5 |
$1500.00 |
$4440.30 |
$750.00 |
04-29-2004 |
07-208034 |
5 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
04 |
90 |
$300.00 |
$888.06 |
$27000.00 |
06-30-2004 |
04-270704 |
1 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
04 |
90 |
$190.00 |
$562.44 |
$17100.00 |
06-30-2004 |
04-270704 |
2 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
04 |
90 |
$240.00 |
$710.45 |
$21600.00 |
06-30-2004 |
04-270704 |
3 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
04 |
90 |
$300.00 |
$888.06 |
$27000.00 |
06-30-2004 |
04-270704 |
4 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
04 |
90 |
$200.00 |
$592.04 |
$18000.00 |
06-30-2004 |
04-270704 |
5 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
04 |
90 |
$300.00 |
$888.06 |
$27000.00 |
06-30-2004 |
04-270704 |
6 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
04 |
90 |
$362.00 |
$1071.59 |
$32580.00 |
06-30-2004 |
04-270704 |
7 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
95 |
$270.00 |
$696.53 |
$25650.00 |
08-25-2005 |
07-242004 |
1 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
95 |
$420.00 |
$1083.50 |
$39900.00 |
08-25-2005 |
07-242004 |
2 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
95 |
$280.00 |
$722.33 |
$26600.00 |
08-25-2005 |
07-242004 |
3 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
95 |
$300.00 |
$773.93 |
$28500.00 |
08-25-2005 |
07-242004 |
4 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
04 |
46 |
$225.00 |
$580.44 |
$10350.00 |
11-02-2005 |
04-263904 |
1 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
04 |
46 |
$286.00 |
$737.81 |
$13156.00 |
11-02-2005 |
04-263904 |
2 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
04 |
46 |
$280.00 |
$722.33 |
$12880.00 |
11-02-2005 |
04-263904 |
3 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
04 |
46 |
$230.00 |
$593.34 |
$10580.00 |
11-02-2005 |
04-263904 |
4 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
490 |
$70.00 |
$180.58 |
$34300.00 |
12-01-2005 |
07-242604 |
1 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
490 |
$303.00 |
$781.67 |
$148470.00 |
12-01-2005 |
07-242604 |
2 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
04 |
95 |
$255.00 |
$657.84 |
$24225.00 |
12-07-2005 |
04-245414 |
1 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
04 |
95 |
$250.00 |
$644.94 |
$23750.00 |
12-07-2005 |
04-245414 |
2 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
04 |
95 |
$260.00 |
$670.74 |
$24700.00 |
12-07-2005 |
04-245414 |
3 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
04 |
125 |
$160.00 |
$398.72 |
$20000.00 |
02-08-2006 |
04-246804 |
1 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
04 |
125 |
$300.00 |
$747.60 |
$37500.00 |
02-08-2006 |
04-246804 |
2 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
04 |
125 |
$500.00 |
$1246.00 |
$62500.00 |
02-08-2006 |
04-246804 |
3 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
04 |
125 |
$300.00 |
$747.60 |
$37500.00 |
02-08-2006 |
04-246804 |
4 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
04 |
125 |
$450.00 |
$1121.40 |
$56250.00 |
02-08-2006 |
04-246804 |
5 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
04 |
125 |
$280.00 |
$697.76 |
$35000.00 |
02-08-2006 |
04-246804 |
6 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
04 |
65 |
$350.00 |
$872.20 |
$22750.00 |
05-10-2006 |
04-272014 |
1 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
04 |
65 |
$100.00 |
$249.20 |
$6500.00 |
05-10-2006 |
04-272014 |
2 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
140 |
$300.00 |
$747.60 |
$42000.00 |
06-01-2006 |
07-4K6604 |
1 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
70 |
$515.00 |
$1283.38 |
$36050.00 |
08-24-2006 |
07-232304 |
1 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
70 |
$335.00 |
$834.82 |
$23450.00 |
08-24-2006 |
07-232304 |
2 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
70 |
$400.00 |
$996.80 |
$28000.00 |
08-24-2006 |
07-232304 |
3 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
54 |
$665.00 |
$1657.18 |
$35910.00 |
09-14-2006 |
07-182104 |
1 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
54 |
$150.00 |
$373.80 |
$8100.00 |
09-14-2006 |
07-182104 |
2 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
54 |
$400.00 |
$996.80 |
$21600.00 |
09-14-2006 |
07-182104 |
3 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
54 |
$500.00 |
$1246.00 |
$27000.00 |
09-14-2006 |
07-182104 |
4 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
54 |
$325.00 |
$809.90 |
$17550.00 |
09-14-2006 |
07-182104 |
5 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
54 |
$439.00 |
$1093.99 |
$23706.00 |
09-14-2006 |
07-182104 |
6 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
100 |
$220.00 |
$548.24 |
$22000.00 |
10-26-2006 |
07-218304 |
1 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
100 |
$600.00 |
$1495.20 |
$60000.00 |
10-26-2006 |
07-218304 |
2 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
100 |
$225.13 |
$561.03 |
$22513.00 |
10-26-2006 |
07-218304 |
3 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
100 |
$601.22 |
$1498.24 |
$60122.00 |
10-26-2006 |
07-218304 |
4 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
100 |
$350.00 |
$872.20 |
$35000.00 |
10-26-2006 |
07-218304 |
5 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
04 |
125 |
$230.00 |
$573.16 |
$28750.00 |
11-29-2006 |
04-246804 |
1 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
04 |
125 |
$360.00 |
$897.12 |
$45000.00 |
11-29-2006 |
04-246804 |
2 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
04 |
125 |
$475.00 |
$1183.70 |
$59375.00 |
11-29-2006 |
04-246804 |
3 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
04 |
125 |
$650.00 |
$1619.80 |
$81250.00 |
11-29-2006 |
04-246804 |
4 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
04 |
125 |
$700.00 |
$1744.40 |
$87500.00 |
11-29-2006 |
04-246804 |
5 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
04 |
930 |
$405.00 |
$1014.44 |
$376650.00 |
01-24-2007 |
04-270524 |
1 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
04 |
930 |
$360.00 |
$901.72 |
$334800.00 |
01-24-2007 |
04-270524 |
2 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
04 |
930 |
$250.00 |
$626.20 |
$232500.00 |
01-24-2007 |
04-270524 |
3 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
04 |
930 |
$270.00 |
$676.29 |
$251100.00 |
01-24-2007 |
04-270524 |
4 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
1560 |
$114.00 |
$285.55 |
$177840.00 |
01-25-2007 |
07-1294V4 |
1 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
1560 |
$360.00 |
$901.72 |
$561600.00 |
01-25-2007 |
07-1294V4 |
2 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
1560 |
$280.00 |
$701.34 |
$436800.00 |
01-25-2007 |
07-1294V4 |
3 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
1560 |
$160.00 |
$400.77 |
$249600.00 |
01-25-2007 |
07-1294V4 |
4 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
1560 |
$230.00 |
$576.10 |
$358800.00 |
01-25-2007 |
07-1294V4 |
5 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
1560 |
$240.00 |
$601.15 |
$374400.00 |
01-25-2007 |
07-1294V4 |
6 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
1560 |
$300.00 |
$751.44 |
$468000.00 |
01-25-2007 |
07-1294V4 |
7 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
140 |
$360.00 |
$901.72 |
$50400.00 |
02-15-2007 |
07-4K6604 |
1 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
140 |
$550.00 |
$1377.63 |
$77000.00 |
02-15-2007 |
07-4K6604 |
2 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
140 |
$300.00 |
$751.44 |
$42000.00 |
02-15-2007 |
07-4K6604 |
3 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
140 |
$350.00 |
$876.68 |
$49000.00 |
02-15-2007 |
07-4K6604 |
4 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
140 |
$500.00 |
$1252.39 |
$70000.00 |
02-15-2007 |
07-4K6604 |
5 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
140 |
$550.00 |
$1377.63 |
$77000.00 |
02-15-2007 |
07-4K6604 |
6 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
140 |
$475.00 |
$1189.77 |
$66500.00 |
02-15-2007 |
07-4K6604 |
7 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
140 |
$325.00 |
$814.06 |
$45500.00 |
02-15-2007 |
07-4K6604 |
8 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
04 |
120 |
$250.00 |
$626.20 |
$30000.00 |
06-27-2007 |
04-016014 |
1 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
04 |
120 |
$225.00 |
$563.58 |
$27000.00 |
06-27-2007 |
04-016014 |
2 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
04 |
120 |
$300.00 |
$751.44 |
$36000.00 |
06-27-2007 |
04-016014 |
3 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
14 |
$275.00 |
$735.32 |
$3850.00 |
02-14-2008 |
07-246704 |
1 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
14 |
$490.00 |
$1310.21 |
$6860.00 |
02-14-2008 |
07-246704 |
2 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
14 |
$500.00 |
$1336.95 |
$7000.00 |
02-14-2008 |
07-246704 |
3 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
14 |
$730.00 |
$1951.95 |
$10220.00 |
02-14-2008 |
07-246704 |
4 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
14 |
$250.00 |
$668.48 |
$3500.00 |
02-14-2008 |
07-246704 |
5 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
14 |
$400.00 |
$1069.56 |
$5600.00 |
02-14-2008 |
07-246704 |
6 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
14 |
$500.00 |
$1336.95 |
$7000.00 |
02-14-2008 |
07-246704 |
7 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
14 |
$250.00 |
$668.48 |
$3500.00 |
02-14-2008 |
07-246704 |
8 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
14 |
$310.00 |
$828.91 |
$4340.00 |
02-14-2008 |
07-246704 |
9 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
14 |
$250.00 |
$668.48 |
$3500.00 |
02-14-2008 |
07-246704 |
10 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
380 |
$275.00 |
$735.32 |
$104500.00 |
03-27-2008 |
07-4S7404 |
1 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
380 |
$280.00 |
$748.69 |
$106400.00 |
03-27-2008 |
07-4S7404 |
2 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
380 |
$230.00 |
$615.00 |
$87400.00 |
03-27-2008 |
07-4S7404 |
3 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
380 |
$385.00 |
$1029.45 |
$146300.00 |
03-27-2008 |
07-4S7404 |
4 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
12 |
20 |
$306.00 |
$818.21 |
$6120.00 |
08-28-2008 |
12-0G2204 |
1 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
12 |
20 |
$300.00 |
$802.17 |
$6000.00 |
08-28-2008 |
12-0G2204 |
2 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
12 |
20 |
$417.00 |
$1115.02 |
$8340.00 |
08-28-2008 |
12-0G2204 |
3 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
12 |
20 |
$204.00 |
$545.48 |
$4080.00 |
08-28-2008 |
12-0G2204 |
4 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
12 |
20 |
$400.00 |
$1069.56 |
$8000.00 |
08-28-2008 |
12-0G2204 |
5 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
12 |
20 |
$500.00 |
$1336.95 |
$10000.00 |
08-28-2008 |
12-0G2204 |
6 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
790 |
$238.00 |
$636.39 |
$188020.00 |
10-09-2008 |
07-2395U4 |
1 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
790 |
$190.00 |
$508.04 |
$150100.00 |
10-09-2008 |
07-2395U4 |
2 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
790 |
$100.00 |
$267.39 |
$79000.00 |
10-09-2008 |
07-2395U4 |
3 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
65 |
$220.00 |
$588.26 |
$14300.00 |
12-11-2008 |
07-4K1504 |
1 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
65 |
$130.00 |
$347.61 |
$8450.00 |
12-11-2008 |
07-4K1504 |
2 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
65 |
$175.00 |
$467.93 |
$11375.00 |
12-11-2008 |
07-4K1504 |
3 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
65 |
$325.00 |
$869.02 |
$21125.00 |
12-11-2008 |
07-4K1504 |
4 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
65 |
$265.00 |
$708.58 |
$17225.00 |
12-11-2008 |
07-4K1504 |
5 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
65 |
$200.00 |
$534.78 |
$13000.00 |
12-11-2008 |
07-4K1504 |
6 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
65 |
$300.00 |
$802.17 |
$19500.00 |
12-11-2008 |
07-4K1504 |
7 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
65 |
$250.00 |
$668.48 |
$16250.00 |
12-11-2008 |
07-4K1504 |
8 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
65 |
$130.00 |
$347.61 |
$8450.00 |
12-11-2008 |
07-4K1504 |
9 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
5 |
$150.00 |
$477.82 |
$750.00 |
02-26-2009 |
07-4T0004 |
1 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
5 |
$360.00 |
$1146.76 |
$1800.00 |
02-26-2009 |
07-4T0004 |
2 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
5 |
$350.00 |
$1114.90 |
$1750.00 |
02-26-2009 |
07-4T0004 |
3 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
5 |
$300.00 |
$955.63 |
$1500.00 |
02-26-2009 |
07-4T0004 |
4 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
5 |
$951.65 |
$3031.42 |
$4758.25 |
02-26-2009 |
07-4T0004 |
5 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
5 |
$1200.00 |
$3822.52 |
$6000.00 |
02-26-2009 |
07-4T0004 |
6 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
5 |
$800.00 |
$2548.35 |
$4000.00 |
02-26-2009 |
07-4T0004 |
7 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
5 |
$600.00 |
$1911.26 |
$3000.00 |
02-26-2009 |
07-4T0004 |
8 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
5 |
$519.00 |
$1653.24 |
$2595.00 |
02-26-2009 |
07-4T0004 |
9 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
5 |
$500.00 |
$1592.72 |
$2500.00 |
02-26-2009 |
07-4T0004 |
10 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
4480 |
$265.00 |
$844.14 |
$1187200.00 |
03-19-2009 |
07-117074 |
1 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
4480 |
$350.00 |
$1114.90 |
$1568000.00 |
03-19-2009 |
07-117074 |
2 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
4480 |
$250.00 |
$796.36 |
$1120000.00 |
03-19-2009 |
07-117074 |
3 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
4480 |
$330.00 |
$1051.19 |
$1478400.00 |
03-19-2009 |
07-117074 |
4 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
4480 |
$220.00 |
$700.80 |
$985600.00 |
03-19-2009 |
07-117074 |
5 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
4480 |
$210.00 |
$668.94 |
$940800.00 |
03-19-2009 |
07-117074 |
6 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
4480 |
$275.00 |
$875.99 |
$1232000.00 |
03-19-2009 |
07-117074 |
7 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
4480 |
$240.00 |
$764.50 |
$1075200.00 |
03-19-2009 |
07-117074 |
8 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
4480 |
$155.00 |
$493.74 |
$694400.00 |
03-19-2009 |
07-117074 |
9 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
790 |
$135.00 |
$430.03 |
$106650.00 |
05-29-2009 |
07-2395U4 |
1 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
790 |
$200.00 |
$637.09 |
$158000.00 |
05-29-2009 |
07-2395U4 |
2 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
790 |
$190.00 |
$605.23 |
$150100.00 |
05-29-2009 |
07-2395U4 |
3 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
790 |
$165.00 |
$525.60 |
$130350.00 |
05-29-2009 |
07-2395U4 |
4 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
1570 |
$180.00 |
$573.38 |
$282600.00 |
10-01-2009 |
07-2411U4 |
1 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
1570 |
$147.00 |
$468.26 |
$230790.00 |
10-01-2009 |
07-2411U4 |
2 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
1570 |
$200.00 |
$637.09 |
$314000.00 |
10-01-2009 |
07-2411U4 |
3 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
1570 |
$100.00 |
$318.54 |
$157000.00 |
10-01-2009 |
07-2411U4 |
4 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
1570 |
$205.00 |
$653.01 |
$321850.00 |
10-01-2009 |
07-2411U4 |
5 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
1570 |
$310.00 |
$987.48 |
$486700.00 |
10-01-2009 |
07-2411U4 |
6 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
1570 |
$300.00 |
$955.63 |
$471000.00 |
10-01-2009 |
07-2411U4 |
7 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
1390 |
$140.00 |
$445.96 |
$194600.00 |
02-18-2010 |
07-1219U4 |
1 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
1390 |
$180.00 |
$573.38 |
$250200.00 |
02-18-2010 |
07-1219U4 |
2 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
1390 |
$100.00 |
$318.54 |
$139000.00 |
02-18-2010 |
07-1219U4 |
3 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
1390 |
$139.00 |
$442.78 |
$193210.00 |
02-18-2010 |
07-1219U4 |
4 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
1390 |
$184.00 |
$586.12 |
$255760.00 |
02-18-2010 |
07-1219U4 |
5 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
1390 |
$320.00 |
$1019.34 |
$444800.00 |
02-18-2010 |
07-1219U4 |
6 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
1390 |
$275.00 |
$875.99 |
$382250.00 |
02-18-2010 |
07-1219U4 |
7 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
1390 |
$200.00 |
$637.09 |
$278000.00 |
02-18-2010 |
07-1219U4 |
8 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
340 |
$165.00 |
$525.60 |
$56100.00 |
04-08-2010 |
07-1218V4 |
1 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
340 |
$50.00 |
$159.27 |
$17000.00 |
04-08-2010 |
07-1218V4 |
2 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
340 |
$205.00 |
$653.01 |
$69700.00 |
04-08-2010 |
07-1218V4 |
3 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
340 |
$125.00 |
$398.18 |
$42500.00 |
04-08-2010 |
07-1218V4 |
4 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
340 |
$165.00 |
$525.60 |
$56100.00 |
04-08-2010 |
07-1218V4 |
5 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
340 |
$185.00 |
$589.31 |
$62900.00 |
04-08-2010 |
07-1218V4 |
6 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
340 |
$230.00 |
$732.65 |
$78200.00 |
04-08-2010 |
07-1218V4 |
7 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
340 |
$250.00 |
$796.36 |
$85000.00 |
04-08-2010 |
07-1218V4 |
8 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
340 |
$235.00 |
$748.58 |
$79900.00 |
04-08-2010 |
07-1218V4 |
9 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
12 |
2060 |
$122.00 |
$388.62 |
$251320.00 |
04-15-2010 |
12-071624 |
1 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
12 |
2060 |
$136.00 |
$433.22 |
$280160.00 |
04-15-2010 |
12-071624 |
2 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
12 |
2060 |
$245.00 |
$780.43 |
$504700.00 |
04-15-2010 |
12-071624 |
3 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
12 |
2060 |
$123.00 |
$391.81 |
$253380.00 |
04-15-2010 |
12-071624 |
4 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
12 |
2060 |
$80.00 |
$254.83 |
$164800.00 |
04-15-2010 |
12-071624 |
5 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
12 |
2060 |
$90.00 |
$286.69 |
$185400.00 |
04-15-2010 |
12-071624 |
6 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
12 |
2060 |
$160.00 |
$509.67 |
$329600.00 |
04-15-2010 |
12-071624 |
7 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
12 |
2060 |
$190.00 |
$605.23 |
$391400.00 |
04-15-2010 |
12-071624 |
8 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
12 |
2060 |
$180.00 |
$573.38 |
$370800.00 |
04-15-2010 |
12-071624 |
9 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
12 |
2060 |
$140.00 |
$445.96 |
$288400.00 |
04-15-2010 |
12-071624 |
10 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
1440 |
$1.00 |
$3.19 |
$1440.00 |
05-13-2010 |
07-1786A4 |
1 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
1440 |
$150.00 |
$477.82 |
$216000.00 |
05-13-2010 |
07-1786A4 |
2 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
1440 |
$165.00 |
$525.60 |
$237600.00 |
05-13-2010 |
07-1786A4 |
3 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
1440 |
$160.00 |
$509.67 |
$230400.00 |
05-13-2010 |
07-1786A4 |
4 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
1440 |
$215.00 |
$684.87 |
$309600.00 |
05-13-2010 |
07-1786A4 |
5 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
1440 |
$226.00 |
$719.91 |
$325440.00 |
05-13-2010 |
07-1786A4 |
6 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
1440 |
$55.00 |
$175.20 |
$79200.00 |
05-13-2010 |
07-1786A4 |
7 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
1440 |
$250.00 |
$796.36 |
$360000.00 |
05-13-2010 |
07-1786A4 |
8 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
1440 |
$240.00 |
$764.50 |
$345600.00 |
05-13-2010 |
07-1786A4 |
9 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
1440 |
$34.00 |
$108.30 |
$48960.00 |
05-13-2010 |
07-1786A4 |
10 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
1440 |
$280.00 |
$891.92 |
$403200.00 |
05-13-2010 |
07-1786A4 |
11 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
1440 |
$269.64 |
$858.92 |
$388281.60 |
05-13-2010 |
07-1786A4 |
12 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
340 |
$165.00 |
$525.60 |
$56100.00 |
06-10-2010 |
07-1218V4 |
1 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
340 |
$50.00 |
$159.27 |
$17000.00 |
06-10-2010 |
07-1218V4 |
2 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
340 |
$181.00 |
$576.56 |
$61540.00 |
06-10-2010 |
07-1218V4 |
3 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
340 |
$235.00 |
$748.58 |
$79900.00 |
06-10-2010 |
07-1218V4 |
4 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
12 |
3260 |
$253.00 |
$805.91 |
$824780.00 |
07-01-2010 |
12-071634 |
1 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
12 |
3260 |
$130.00 |
$414.11 |
$423800.00 |
07-01-2010 |
12-071634 |
2 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
12 |
3260 |
$125.00 |
$398.18 |
$407500.00 |
07-01-2010 |
12-071634 |
3 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
12 |
3260 |
$150.00 |
$477.82 |
$489000.00 |
07-01-2010 |
12-071634 |
4 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
12 |
3260 |
$188.00 |
$598.86 |
$612880.00 |
07-01-2010 |
12-071634 |
5 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
12 |
3260 |
$145.00 |
$461.89 |
$472700.00 |
07-01-2010 |
12-071634 |
6 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
510 |
$175.00 |
$557.45 |
$89250.00 |
08-05-2010 |
07-121844 |
1 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
510 |
$150.00 |
$477.82 |
$76500.00 |
08-05-2010 |
07-121844 |
2 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
510 |
$160.00 |
$509.67 |
$81600.00 |
08-05-2010 |
07-121844 |
3 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
510 |
$335.00 |
$1067.12 |
$170850.00 |
08-05-2010 |
07-121844 |
4 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
510 |
$295.00 |
$939.70 |
$150450.00 |
08-05-2010 |
07-121844 |
5 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
510 |
$200.00 |
$637.09 |
$102000.00 |
08-05-2010 |
07-121844 |
6 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
510 |
$125.00 |
$398.18 |
$63750.00 |
08-05-2010 |
07-121844 |
7 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
M3 |
07 |
510 |
$350.00 |
$1114.90 |
$178500.00 |
08-05-2010 |
07-121844 |
8 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
220 |
$135.00 |
$383.36 |
$29700.00 |
09-08-2011 |
07-2332A4 |
1 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
220 |
$230.00 |
$653.14 |
$50600.00 |
09-08-2011 |
07-2332A4 |
2 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
220 |
$150.00 |
$425.96 |
$33000.00 |
09-08-2011 |
07-2332A4 |
3 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
220 |
$120.00 |
$340.77 |
$26400.00 |
09-08-2011 |
07-2332A4 |
4 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
220 |
$135.00 |
$383.36 |
$29700.00 |
09-08-2011 |
07-2332A4 |
5 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
220 |
$130.00 |
$369.16 |
$28600.00 |
09-08-2011 |
07-2332A4 |
6 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
220 |
$200.00 |
$567.95 |
$44000.00 |
09-08-2011 |
07-2332A4 |
7 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
220 |
$157.50 |
$447.26 |
$34650.00 |
09-08-2011 |
07-2332A4 |
8 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
220 |
$200.00 |
$567.95 |
$44000.00 |
09-08-2011 |
07-2332A4 |
9 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
220 |
$225.00 |
$638.94 |
$49500.00 |
09-08-2011 |
07-2332A4 |
10 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
220 |
$362.00 |
$1027.98 |
$79640.00 |
09-08-2011 |
07-2332A4 |
11 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
04 |
470 |
$220.00 |
$633.33 |
$103400.00 |
02-28-2012 |
04-4S5504 |
1 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
04 |
470 |
$120.00 |
$345.45 |
$56400.00 |
02-28-2012 |
04-4S5504 |
2 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
04 |
470 |
$180.00 |
$518.18 |
$84600.00 |
02-28-2012 |
04-4S5504 |
3 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
04 |
470 |
$250.00 |
$719.70 |
$117500.00 |
02-28-2012 |
04-4S5504 |
4 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
04 |
470 |
$96.50 |
$277.80 |
$45355.00 |
02-28-2012 |
04-4S5504 |
5 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
04 |
470 |
$120.00 |
$345.45 |
$56400.00 |
02-28-2012 |
04-4S5504 |
6 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
04 |
470 |
$242.00 |
$696.67 |
$113740.00 |
02-28-2012 |
04-4S5504 |
7 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
3390 |
$305.75 |
$761.93 |
$1036492.50 |
10-04-2012 |
07-1218W4 |
1 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
3390 |
$147.00 |
$366.33 |
$498330.00 |
10-04-2012 |
07-1218W4 |
2 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
3390 |
$155.00 |
$386.26 |
$525450.00 |
10-04-2012 |
07-1218W4 |
3 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
3390 |
$95.00 |
$236.74 |
$322050.00 |
10-04-2012 |
07-1218W4 |
4 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
3390 |
$280.00 |
$697.76 |
$949200.00 |
10-04-2012 |
07-1218W4 |
5 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
04 |
410 |
$225.00 |
$517.98 |
$92250.00 |
05-13-2014 |
04-235844 |
1 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
04 |
410 |
$215.00 |
$494.96 |
$88150.00 |
05-13-2014 |
04-235844 |
2 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
04 |
410 |
$235.00 |
$541.00 |
$96350.00 |
05-13-2014 |
04-235844 |
3 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
04 |
410 |
$60.00 |
$138.13 |
$24600.00 |
05-13-2014 |
04-235844 |
4 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
04 |
410 |
$225.00 |
$517.98 |
$92250.00 |
05-13-2014 |
04-235844 |
5 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
04 |
410 |
$400.00 |
$920.85 |
$164000.00 |
05-13-2014 |
04-235844 |
6 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
04 |
410 |
$200.00 |
$460.42 |
$82000.00 |
05-13-2014 |
04-235844 |
7 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
04 |
410 |
$290.00 |
$667.62 |
$118900.00 |
05-13-2014 |
04-235844 |
8 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
04 |
410 |
$200.00 |
$460.42 |
$82000.00 |
05-13-2014 |
04-235844 |
9 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
04 |
120 |
$220.00 |
$467.33 |
$26400.00 |
07-21-2015 |
04-3G7104 |
1 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
04 |
120 |
$450.00 |
$955.91 |
$54000.00 |
07-21-2015 |
04-3G7104 |
2 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
64 |
$240.00 |
$461.81 |
$15360.00 |
10-29-2015 |
07-255104 |
1 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
64 |
$160.00 |
$307.88 |
$10240.00 |
10-29-2015 |
07-255104 |
2 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
64 |
$785.00 |
$1510.52 |
$50240.00 |
10-29-2015 |
07-255104 |
3 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
64 |
$440.00 |
$846.66 |
$28160.00 |
10-29-2015 |
07-255104 |
4 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
64 |
$250.00 |
$481.06 |
$16000.00 |
10-29-2015 |
07-255104 |
5 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
64 |
$550.00 |
$1058.33 |
$35200.00 |
10-29-2015 |
07-255104 |
6 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
64 |
$1.00 |
$1.92 |
$64.00 |
10-29-2015 |
07-255104 |
7 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
51 |
$288.00 |
$554.18 |
$14688.00 |
11-18-2015 |
07-287604 |
1 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
51 |
$250.00 |
$481.06 |
$12750.00 |
11-18-2015 |
07-287604 |
2 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
51 |
$290.00 |
$558.03 |
$14790.00 |
11-18-2015 |
07-287604 |
3 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
51 |
$532.00 |
$1023.69 |
$27132.00 |
11-18-2015 |
07-287604 |
4 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
51 |
$150.00 |
$288.63 |
$7650.00 |
11-18-2015 |
07-287604 |
5 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
51 |
$589.43 |
$1134.20 |
$30060.93 |
11-18-2015 |
07-287604 |
6 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
170 |
$450.00 |
$827.75 |
$76500.00 |
04-05-2016 |
07-2827U4 |
1 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
170 |
$350.39 |
$644.52 |
$59566.30 |
04-05-2016 |
07-2827U4 |
2 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
170 |
$170.00 |
$312.71 |
$28900.00 |
04-05-2016 |
07-2827U4 |
3 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
170 |
$205.00 |
$377.09 |
$34850.00 |
04-05-2016 |
07-2827U4 |
4 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
170 |
$178.00 |
$327.42 |
$30260.00 |
04-05-2016 |
07-2827U4 |
5 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
170 |
$350.00 |
$643.80 |
$59500.00 |
04-05-2016 |
07-2827U4 |
6 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
660 |
$164.00 |
$247.97 |
$108240.00 |
11-02-2016 |
07-281504 |
1 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
660 |
$190.00 |
$287.28 |
$125400.00 |
11-02-2016 |
07-281504 |
2 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
660 |
$150.00 |
$226.80 |
$99000.00 |
11-02-2016 |
07-281504 |
3 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
660 |
$280.00 |
$423.37 |
$184800.00 |
11-02-2016 |
07-281504 |
4 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
660 |
$175.00 |
$264.60 |
$115500.00 |
11-02-2016 |
07-281504 |
5 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
660 |
$150.00 |
$226.80 |
$99000.00 |
11-02-2016 |
07-281504 |
6 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
660 |
$205.00 |
$309.96 |
$135300.00 |
11-02-2016 |
07-281504 |
7 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
660 |
$362.00 |
$547.35 |
$238920.00 |
11-02-2016 |
07-281504 |
8 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
660 |
$230.00 |
$347.76 |
$151800.00 |
11-02-2016 |
07-281504 |
9 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
660 |
$270.00 |
$408.25 |
$178200.00 |
11-02-2016 |
07-281504 |
10 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
660 |
$130.00 |
$196.56 |
$85800.00 |
11-02-2016 |
07-281504 |
11 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
660 |
$324.00 |
$489.89 |
$213840.00 |
11-02-2016 |
07-281504 |
12 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
660 |
$212.07 |
$320.65 |
$139966.20 |
11-02-2016 |
07-281504 |
13 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
660 |
$215.00 |
$325.08 |
$141900.00 |
11-02-2016 |
07-281504 |
14 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
11 |
$350.00 |
$529.21 |
$3850.00 |
11-02-2016 |
07-305504 |
1 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
11 |
$150.00 |
$226.80 |
$1650.00 |
11-02-2016 |
07-305504 |
2 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
11 |
$975.80 |
$1475.43 |
$10733.80 |
11-02-2016 |
07-305504 |
3 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
04 |
290 |
$344.00 |
$502.36 |
$99760.00 |
06-27-2017 |
04-4G9704 |
1 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
04 |
290 |
$288.00 |
$420.58 |
$83520.00 |
06-27-2017 |
04-4G9704 |
2 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
04 |
290 |
$300.00 |
$438.10 |
$87000.00 |
06-27-2017 |
04-4G9704 |
3 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
04 |
290 |
$550.00 |
$803.18 |
$159500.00 |
06-27-2017 |
04-4G9704 |
4 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
1040 |
$380.00 |
$689.81 |
$395200.00 |
12-19-2017 |
07-296404 |
1 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
1040 |
$275.00 |
$499.20 |
$286000.00 |
12-19-2017 |
07-296404 |
2 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
1040 |
$485.00 |
$880.41 |
$504400.00 |
12-19-2017 |
07-296404 |
3 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
1040 |
$345.00 |
$626.27 |
$358800.00 |
12-19-2017 |
07-296404 |
4 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
330 |
$260.00 |
$405.55 |
$85800.00 |
01-10-2018 |
07-302204 |
1 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
330 |
$403.00 |
$628.61 |
$132990.00 |
01-10-2018 |
07-302204 |
2 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
330 |
$285.00 |
$444.55 |
$94050.00 |
01-10-2018 |
07-302204 |
3 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
330 |
$400.00 |
$623.93 |
$132000.00 |
01-10-2018 |
07-302204 |
4 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
330 |
$280.00 |
$436.75 |
$92400.00 |
01-10-2018 |
07-302204 |
5 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
330 |
$354.00 |
$552.18 |
$116820.00 |
01-10-2018 |
07-302204 |
6 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
110 |
$520.00 |
$718.56 |
$57200.00 |
10-31-2018 |
07-301504 |
1 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
110 |
$325.00 |
$449.10 |
$35750.00 |
10-31-2018 |
07-301504 |
2 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
110 |
$840.82 |
$1161.88 |
$92490.20 |
10-31-2018 |
07-301504 |
3 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
110 |
$420.00 |
$580.37 |
$46200.00 |
10-31-2018 |
07-301504 |
4 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
110 |
$450.00 |
$621.83 |
$49500.00 |
10-31-2018 |
07-301504 |
5 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
110 |
$430.00 |
$594.19 |
$47300.00 |
10-31-2018 |
07-301504 |
6 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
4.5 |
$1250.10 |
$1727.43 |
$5625.45 |
11-29-2018 |
07-340604 |
1 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
4.5 |
$1208.00 |
$1669.26 |
$5436.00 |
11-29-2018 |
07-340604 |
2 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
4.5 |
$1725.00 |
$2383.67 |
$7762.50 |
11-29-2018 |
07-340604 |
3 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
4.5 |
$1500.00 |
$2072.76 |
$6750.00 |
11-29-2018 |
07-340604 |
4 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
4.5 |
$1400.00 |
$1934.57 |
$6300.00 |
11-29-2018 |
07-340604 |
5 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
06 |
92 |
$275.00 |
$478.63 |
$25300.00 |
01-31-2019 |
06-0E3204 |
1 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
06 |
92 |
$210.00 |
$365.50 |
$19320.00 |
01-31-2019 |
06-0E3204 |
2 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
06 |
92 |
$504.56 |
$878.17 |
$46419.52 |
01-31-2019 |
06-0E3204 |
3 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
06 |
92 |
$315.00 |
$548.25 |
$28980.00 |
01-31-2019 |
06-0E3204 |
4 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
06 |
92 |
$503.00 |
$875.46 |
$46276.00 |
01-31-2019 |
06-0E3204 |
5 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
06 |
92 |
$500.00 |
$870.23 |
$46000.00 |
01-31-2019 |
06-0E3204 |
6 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
06 |
92 |
$311.00 |
$541.29 |
$28612.00 |
01-31-2019 |
06-0E3204 |
7 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
06 |
92 |
$660.00 |
$1148.71 |
$60720.00 |
01-31-2019 |
06-0E3204 |
8 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
06 |
92 |
$500.00 |
$870.23 |
$46000.00 |
01-31-2019 |
06-0E3204 |
9 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
04 |
300 |
$225.00 |
$277.40 |
$67500.00 |
04-09-2019 |
04-0J6604 |
1 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
04 |
300 |
$310.00 |
$382.20 |
$93000.00 |
04-09-2019 |
04-0J6604 |
2 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
04 |
300 |
$400.00 |
$493.16 |
$120000.00 |
04-09-2019 |
04-0J6604 |
3 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
04 |
300 |
$370.00 |
$456.17 |
$111000.00 |
04-09-2019 |
04-0J6604 |
4 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
04 |
300 |
$305.00 |
$376.03 |
$91500.00 |
04-09-2019 |
04-0J6604 |
5 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
4 |
$2500.00 |
$3082.25 |
$10000.00 |
06-19-2019 |
07-304404 |
1 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
4 |
$920.00 |
$1134.27 |
$3680.00 |
06-19-2019 |
07-304404 |
2 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
4 |
$422.85 |
$521.33 |
$1691.40 |
06-19-2019 |
07-304404 |
3 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
4 |
$2000.00 |
$2465.80 |
$8000.00 |
06-19-2019 |
07-304404 |
4 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
4 |
$729.09 |
$898.89 |
$2916.36 |
06-19-2019 |
07-304404 |
5 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
4 |
$600.00 |
$739.74 |
$2400.00 |
06-19-2019 |
07-304404 |
6 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
4 |
$500.00 |
$616.45 |
$2000.00 |
06-19-2019 |
07-304404 |
7 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
4 |
$1500.00 |
$1849.35 |
$6000.00 |
06-19-2019 |
07-304404 |
8 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
4 |
$325.00 |
$400.69 |
$1300.00 |
06-19-2019 |
07-304404 |
9 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
1120 |
$495.00 |
$648.36 |
$554400.00 |
09-12-2019 |
07-304204 |
1 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
1120 |
$300.00 |
$392.95 |
$336000.00 |
09-12-2019 |
07-304204 |
2 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
1120 |
$538.79 |
$705.72 |
$603444.80 |
09-12-2019 |
07-304204 |
3 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
1120 |
$622.52 |
$815.39 |
$697222.40 |
09-12-2019 |
07-304204 |
4 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
1120 |
$300.00 |
$392.95 |
$336000.00 |
09-12-2019 |
07-304204 |
5 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
1120 |
$580.00 |
$759.70 |
$649600.00 |
09-12-2019 |
07-304204 |
6 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
1120 |
$485.00 |
$635.26 |
$543200.00 |
09-12-2019 |
07-304204 |
7 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
1120 |
$395.00 |
$517.38 |
$442400.00 |
09-12-2019 |
07-304204 |
8 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
1120 |
$475.00 |
$622.17 |
$532000.00 |
09-12-2019 |
07-304204 |
9 |
M |
|
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
10 |
$860.00 |
$1230.86 |
$8600.00 |
10-27-2020 |
07-317304 |
1 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
10 |
$750.00 |
$1073.43 |
$7500.00 |
10-27-2020 |
07-317304 |
2 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
10 |
$330.00 |
$472.31 |
$3300.00 |
10-27-2020 |
07-317304 |
3 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
10 |
$1250.00 |
$1789.05 |
$12500.00 |
10-27-2020 |
07-317304 |
4 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
10 |
$500.00 |
$715.62 |
$5000.00 |
10-27-2020 |
07-317304 |
5 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
10 |
$400.00 |
$572.49 |
$4000.00 |
10-27-2020 |
07-317304 |
6 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
10 |
$1030.00 |
$1474.17 |
$10300.00 |
10-27-2020 |
07-317304 |
7 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
04 |
79 |
$450.00 |
$774.56 |
$35550.00 |
01-05-2021 |
04-4J3904 |
1 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
04 |
79 |
$400.00 |
$688.50 |
$31600.00 |
01-05-2021 |
04-4J3904 |
2 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
04 |
79 |
$265.00 |
$456.13 |
$20935.00 |
01-05-2021 |
04-4J3904 |
3 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
04 |
79 |
$580.00 |
$998.32 |
$45820.00 |
01-05-2021 |
04-4J3904 |
4 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
04 |
79 |
$270.00 |
$464.74 |
$21330.00 |
01-05-2021 |
04-4J3904 |
5 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
7 |
$160.00 |
$226.76 |
$1120.00 |
06-08-2021 |
07-327204 |
1 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
7 |
$945.00 |
$1339.31 |
$6615.00 |
06-08-2021 |
07-327204 |
2 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
7 |
$447.31 |
$633.95 |
$3131.17 |
06-08-2021 |
07-327204 |
3 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
7 |
$932.00 |
$1320.88 |
$6524.00 |
06-08-2021 |
07-327204 |
4 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
7 |
$135.00 |
$191.33 |
$945.00 |
06-08-2021 |
07-327204 |
5 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
7 |
$696.90 |
$987.69 |
$4878.30 |
06-08-2021 |
07-327204 |
6 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
12 |
$400.00 |
$696.35 |
$4800.00 |
10-27-2021 |
07-327104 |
1 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
12 |
$725.00 |
$1262.14 |
$8700.00 |
10-27-2021 |
07-327104 |
2 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
12 |
$330.00 |
$574.49 |
$3960.00 |
10-27-2021 |
07-327104 |
3 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
12 |
$1300.00 |
$2263.15 |
$15600.00 |
10-27-2021 |
07-327104 |
4 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
12 |
$1000.00 |
$1740.88 |
$12000.00 |
10-27-2021 |
07-327104 |
5 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
12 |
$345.00 |
$600.60 |
$4140.00 |
10-27-2021 |
07-327104 |
6 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
12 |
$538.00 |
$936.59 |
$6456.00 |
10-27-2021 |
07-327104 |
7 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
12 |
$680.00 |
$1183.80 |
$8160.00 |
10-27-2021 |
07-327104 |
8 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
12 |
$1242.00 |
$2162.17 |
$14904.00 |
10-27-2021 |
07-327104 |
9 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
12 |
$650.00 |
$1131.57 |
$7800.00 |
10-27-2021 |
07-327104 |
10 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) |
CY |
07 |
140 |
$388.80 |
$581.69 |
$54432.00 |
02-01-2022 |
07-319704 |
1 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) |
CY |
07 |
140 |
$311.00 |
$465.29 |
$43540.00 |
02-01-2022 |
07-319704 |
2 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) |
CY |
07 |
140 |
$250.00 |
$374.03 |
$35000.00 |
02-01-2022 |
07-319704 |
3 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) |
CY |
07 |
140 |
$295.00 |
$441.36 |
$41300.00 |
02-01-2022 |
07-319704 |
4 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) |
CY |
07 |
140 |
$235.00 |
$351.59 |
$32900.00 |
02-01-2022 |
07-319704 |
5 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) |
CY |
07 |
140 |
$157.50 |
$235.64 |
$22050.00 |
02-01-2022 |
07-319704 |
6 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) |
CY |
07 |
140 |
$255.00 |
$381.51 |
$35700.00 |
02-01-2022 |
07-319704 |
7 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) |
CY |
07 |
21 |
$190.00 |
$284.26 |
$3990.00 |
02-16-2022 |
07-336504 |
1 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) |
CY |
07 |
21 |
$350.00 |
$523.64 |
$7350.00 |
02-16-2022 |
07-336504 |
2 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) |
CY |
07 |
21 |
$200.00 |
$299.22 |
$4200.00 |
02-16-2022 |
07-336504 |
3 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) |
CY |
07 |
21 |
$400.00 |
$598.45 |
$8400.00 |
02-16-2022 |
07-336504 |
4 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) |
CY |
07 |
21 |
$416.00 |
$622.39 |
$8736.00 |
02-16-2022 |
07-336504 |
5 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) |
CY |
07 |
21 |
$170.00 |
$254.34 |
$3570.00 |
02-16-2022 |
07-336504 |
6 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) |
CY |
07 |
21 |
$420.00 |
$628.37 |
$8820.00 |
02-16-2022 |
07-336504 |
7 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) |
CY |
07 |
21 |
$440.00 |
$658.29 |
$9240.00 |
02-16-2022 |
07-336504 |
8 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) |
CY |
07 |
380 |
$300.00 |
$465.27 |
$114000.00 |
04-27-2022 |
07-323104 |
1 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) |
CY |
07 |
380 |
$270.00 |
$418.75 |
$102600.00 |
04-27-2022 |
07-323104 |
2 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) |
CY |
07 |
380 |
$210.00 |
$325.69 |
$79800.00 |
04-27-2022 |
07-323104 |
3 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) |
CY |
07 |
380 |
$405.64 |
$629.11 |
$154143.20 |
04-27-2022 |
07-323104 |
4 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) |
CY |
07 |
380 |
$410.00 |
$635.87 |
$155800.00 |
04-27-2022 |
07-323104 |
5 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) |
CY |
07 |
380 |
$329.59 |
$511.16 |
$125244.20 |
04-27-2022 |
07-323104 |
6 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) |
CY |
07 |
380 |
$395.00 |
$612.61 |
$150100.00 |
04-27-2022 |
07-323104 |
7 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) |
CY |
07 |
380 |
$472.50 |
$732.81 |
$179550.00 |
04-27-2022 |
07-323104 |
8 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) |
CY |
07 |
1 |
$480.00 |
$744.44 |
$480.00 |
06-16-2022 |
07-330504 |
1 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) |
CY |
07 |
1 |
$4260.00 |
$6606.88 |
$4260.00 |
06-16-2022 |
07-330504 |
2 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) |
CY |
07 |
1 |
$160.00 |
$248.15 |
$160.00 |
06-16-2022 |
07-330504 |
3 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) |
CY |
07 |
1 |
$1500.00 |
$2326.37 |
$1500.00 |
06-16-2022 |
07-330504 |
4 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) |
CY |
07 |
1 |
$1050.00 |
$1628.46 |
$1050.00 |
06-16-2022 |
07-330504 |
5 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) |
CY |
12 |
320 |
$850.00 |
$901.49 |
$272000.00 |
09-15-2022 |
12-0P68U4 |
1 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) |
CY |
07 |
48 |
$428.00 |
$453.93 |
$20544.00 |
09-28-2022 |
07-306614 |
1 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) |
CY |
07 |
48 |
$350.00 |
$371.20 |
$16800.00 |
09-28-2022 |
07-306614 |
2 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) |
CY |
07 |
48 |
$2500.00 |
$2651.45 |
$120000.00 |
09-28-2022 |
07-306614 |
3 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
04 |
350 |
$600.00 |
$667.46 |
$210000.00 |
12-13-2022 |
04-4J4904 |
1 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
04 |
350 |
$600.00 |
$667.46 |
$210000.00 |
12-13-2022 |
04-4J4904 |
2 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
04 |
350 |
$612.25 |
$681.09 |
$214287.50 |
12-13-2022 |
04-4J4904 |
3 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
04 |
350 |
$475.00 |
$528.41 |
$166250.00 |
12-13-2022 |
04-4J4904 |
4 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
04 |
350 |
$550.00 |
$611.84 |
$192500.00 |
12-13-2022 |
04-4J4904 |
5 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
04 |
350 |
$518.30 |
$576.58 |
$181405.00 |
12-13-2022 |
04-4J4904 |
6 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
04 |
350 |
$530.00 |
$589.59 |
$185500.00 |
12-13-2022 |
04-4J4904 |
7 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
04 |
350 |
$895.00 |
$995.63 |
$313250.00 |
12-13-2022 |
04-4J4904 |
8 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
04 |
350 |
$300.00 |
$333.73 |
$105000.00 |
12-13-2022 |
04-4J4904 |
9 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
12 |
320 |
$257.00 |
$300.28 |
$82240.00 |
04-20-2023 |
12-0P68U4 |
1 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
06 |
32 |
$750.00 |
$627.56 |
$24000.00 |
08-10-2023 |
06-0U4304 |
1 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
06 |
32 |
$420.00 |
$351.43 |
$13440.00 |
08-10-2023 |
06-0U4304 |
2 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
06 |
32 |
$525.00 |
$439.29 |
$16800.00 |
08-10-2023 |
06-0U4304 |
3 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
6 |
$3300.00 |
$2535.39 |
$19800.00 |
02-14-2024 |
07-322504 |
1 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
6 |
$2987.00 |
$2294.91 |
$17922.00 |
02-14-2024 |
07-322504 |
2 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
6 |
$2000.00 |
$1536.60 |
$12000.00 |
02-14-2024 |
07-322504 |
3 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
6 |
$250.00 |
$192.07 |
$1500.00 |
02-14-2024 |
07-322504 |
4 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
35 |
$475.00 |
$417.70 |
$16625.00 |
07-30-2025 |
07-319604 |
1 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
35 |
$600.00 |
$527.62 |
$21000.00 |
07-30-2025 |
07-319604 |
2 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
35 |
$580.00 |
$510.04 |
$20300.00 |
07-30-2025 |
07-319604 |
3 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
35 |
$776.00 |
$682.39 |
$27160.00 |
07-30-2025 |
07-319604 |
4 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
35 |
$600.00 |
$527.62 |
$21000.00 |
07-30-2025 |
07-319604 |
5 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
07 |
35 |
$452.00 |
$397.48 |
$15820.00 |
07-30-2025 |
07-319604 |
6 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
04 |
14 |
$1555.00 |
$1797.67 |
$21770.00 |
01-21-2026 |
04-4AC704 |
1 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
04 |
14 |
$1100.00 |
$1271.66 |
$15400.00 |
01-21-2026 |
04-4AC704 |
2 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
04 |
14 |
$869.14 |
$1004.77 |
$12167.96 |
01-21-2026 |
04-4AC704 |
3 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
04 |
14 |
$1000.00 |
$1156.06 |
$14000.00 |
01-21-2026 |
04-4AC704 |
4 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
04 |
14 |
$800.00 |
$924.84 |
$11200.00 |
01-21-2026 |
04-4AC704 |
5 |
M |
TRO |
|
| 190106 - ROADWAY EXCAVATION (TYPE Z-3) (AERIALLY DEPOSITED LEAD) |
CY |
04 |
14 |
$250.00 |
$289.01 |
$3500.00 |
01-21-2026 |
04-4AC704 |
6 |
M |
TRO |