CALIFORNIA DEPARTMENT OF TRANSPORTATION - CONTRACT COST DATA

Select Item No. / Description Unit Dist Qty Unit
Price
Adj
Price
Total Bid Open
Date
Contract
No.
Bid M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) M3 02 21000 $20.00 $63.71 $420000.00 04-13-2010 02-373104 1 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) M3 02 21000 $34.00 $108.30 $714000.00 04-13-2010 02-373104 2 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) M3 02 21000 $20.00 $63.71 $420000.00 04-13-2010 02-373104 3 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) M3 02 21000 $30.00 $95.56 $630000.00 04-13-2010 02-373104 4 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) M3 02 21000 $32.00 $101.93 $672000.00 04-13-2010 02-373104 5 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) M3 02 21000 $20.00 $63.71 $420000.00 04-13-2010 02-373104 6 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 03 8 $1580.00 $5032.99 $12640.00 09-21-2010 03-3C7604 1 M  
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 03 8 $1000.00 $3185.43 $8000.00 09-21-2010 03-3C7604 2 M  
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 10 9620 $125.00 $398.18 $1202500.00 09-29-2010 10-0S1704 1 M  
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 10 9620 $102.85 $327.62 $989417.00 09-29-2010 10-0S1704 2 M  
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 10 9620 $94.80 $301.98 $911976.00 09-29-2010 10-0S1704 3 M  
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 10 9620 $137.00 $436.40 $1317940.00 09-29-2010 10-0S1704 4 M  
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 10 9620 $122.00 $388.62 $1173640.00 09-29-2010 10-0S1704 5 M  
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 10 9620 $80.00 $254.83 $769600.00 09-29-2010 10-0S1704 6 M  
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 10 518000 $8.75 $24.85 $4532500.00 11-16-2011 10-340424 1 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 10 518000 $16.00 $45.44 $8288000.00 11-16-2011 10-340424 2 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 10 518000 $15.25 $43.31 $7899500.00 11-16-2011 10-340424 3 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 10 518000 $20.50 $58.21 $10619000.00 11-16-2011 10-340424 4 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 10 518000 $19.25 $54.66 $9971500.00 11-16-2011 10-340424 5 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 10 3850 $39.40 $111.89 $151690.00 12-07-2011 10-0Q6104 1 M  
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 10 3850 $16.50 $46.86 $63525.00 12-07-2011 10-0Q6104 2 M  
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 10 3850 $26.50 $75.25 $102025.00 12-07-2011 10-0Q6104 3 M  
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 10 3850 $26.00 $73.83 $100100.00 12-07-2011 10-0Q6104 4 M  
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 10 3850 $30.00 $85.19 $115500.00 12-07-2011 10-0Q6104 5 M  
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 10 3850 $65.00 $184.58 $250250.00 12-07-2011 10-0Q6104 6 M  
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 10 3850 $46.00 $130.63 $177100.00 12-07-2011 10-0Q6104 7 M  
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 10 3850 $50.00 $141.99 $192500.00 12-07-2011 10-0Q6104 8 M  
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 04 10000 $30.00 $85.19 $300000.00 12-13-2011 04-264144 1 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 04 10000 $20.00 $56.79 $200000.00 12-13-2011 04-264144 2 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 04 10000 $40.00 $113.59 $400000.00 12-13-2011 04-264144 3 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 04 10000 $11.50 $32.66 $115000.00 12-13-2011 04-264144 4 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 04 10000 $35.00 $99.39 $350000.00 12-13-2011 04-264144 5 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 04 10000 $17.50 $49.70 $175000.00 12-13-2011 04-264144 6 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 04 10000 $120.00 $340.77 $1200000.00 12-13-2011 04-264144 7 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 10 200 $235.50 $677.95 $47100.00 03-06-2012 10-0U6804 1 M  
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 10 200 $200.00 $575.76 $40000.00 03-06-2012 10-0U6804 2 M  
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 10 200 $225.00 $647.73 $45000.00 03-06-2012 10-0U6804 3 M  
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 10 200 $185.00 $532.57 $37000.00 03-06-2012 10-0U6804 4 M  
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 10 200 $50.00 $143.94 $10000.00 03-06-2012 10-0U6804 5 M  
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 10 200 $235.00 $676.51 $47000.00 03-06-2012 10-0U6804 6 M  
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 10 200 $50.00 $143.94 $10000.00 03-06-2012 10-0U6804 7 M  
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 04 42 $100.00 $323.47 $4200.00 08-14-2012 04-264074 1 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 04 42 $50.00 $161.73 $2100.00 08-14-2012 04-264074 2 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 04 42 $10.00 $32.35 $420.00 08-14-2012 04-264074 3 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 04 42 $200.00 $646.93 $8400.00 08-14-2012 04-264074 4 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 04 42 $2000.00 $6469.32 $84000.00 08-14-2012 04-264074 5 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 11 47100 $12.00 $27.63 $565200.00 06-19-2014 11-257154 1 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 11 47100 $14.50 $33.38 $682950.00 06-19-2014 11-257154 2 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 11 47100 $30.40 $69.98 $1431840.00 06-19-2014 11-257154 3 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 11 47100 $45.00 $103.60 $2119500.00 06-19-2014 11-257154 4 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 11 47100 $31.00 $71.37 $1460100.00 06-19-2014 11-257154 5 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 11 47100 $18.00 $41.44 $847800.00 06-19-2014 11-257154 6 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 11 47100 $18.91 $43.53 $890661.00 06-19-2014 11-257154 7 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 08 37500 $5.70 $12.67 $213750.00 07-24-2014 08-3401U4 1 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 08 37500 $1.00 $2.22 $37500.00 07-24-2014 08-3401U4 2 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 08 37500 $15.00 $33.35 $562500.00 07-24-2014 08-3401U4 3 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 08 37500 $20.00 $44.46 $750000.00 07-24-2014 08-3401U4 4 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 08 37500 $10.00 $22.23 $375000.00 07-24-2014 08-3401U4 5 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 08 37500 $6.00 $13.34 $225000.00 07-24-2014 08-3401U4 6 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 08 37500 $10.00 $22.23 $375000.00 07-24-2014 08-3401U4 7 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 08 37500 $26.60 $59.14 $997500.00 07-24-2014 08-3401U4 8 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 08 37500 $25.00 $55.58 $937500.00 07-24-2014 08-3401U4 9 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 08 37500 $30.00 $66.70 $1125000.00 07-24-2014 08-3401U4 10 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 08 37500 $15.00 $33.35 $562500.00 07-24-2014 08-3401U4 11 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 08 80300 $12.00 $23.40 $963600.00 11-14-2014 08-043514 1 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 08 80300 $16.55 $32.28 $1328965.00 11-14-2014 08-043514 2 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 08 80300 $6.00 $11.70 $481800.00 11-14-2014 08-043514 3 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 08 80300 $8.40 $16.38 $674520.00 11-14-2014 08-043514 4 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 08 80300 $5.30 $10.34 $425590.00 11-14-2014 08-043514 5 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 06 57800 $23.00 $48.86 $1329400.00 07-02-2015 06-0G9004 1 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 06 57800 $18.50 $39.30 $1069300.00 07-02-2015 06-0G9004 2 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 06 57800 $28.00 $59.48 $1618400.00 07-02-2015 06-0G9004 3 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 06 57800 $45.00 $95.59 $2601000.00 07-02-2015 06-0G9004 4 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 06 6600 $60.00 $127.45 $396000.00 08-13-2015 06-0M0504 1 M  
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 06 6600 $42.00 $89.22 $277200.00 08-13-2015 06-0M0504 2 M  
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 06 6600 $88.00 $186.93 $580800.00 08-13-2015 06-0M0504 3 M  
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 11 300 $275.00 $428.31 $82500.00 08-03-2016 11-295204 1 M  
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 11 300 $225.00 $350.44 $67500.00 08-03-2016 11-295204 2 M  
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 11 300 $80.00 $124.60 $24000.00 08-03-2016 11-295204 3 M  
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 11 300 $90.00 $140.18 $27000.00 08-03-2016 11-295204 4 M  
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 11 300 $165.00 $256.99 $49500.00 08-03-2016 11-295204 5 M  
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 03 134000 $23.00 $33.45 $3082000.00 05-03-2018 03-2F5904 1 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 03 134000 $29.00 $42.18 $3886000.00 05-03-2018 03-2F5904 2 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 03 134000 $37.00 $53.82 $4958000.00 05-03-2018 03-2F5904 3 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 03 134000 $24.50 $35.64 $3283000.00 05-03-2018 03-2F5904 4 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 03 134000 $33.00 $48.00 $4422000.00 05-03-2018 03-2F5904 5 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 03 134000 $26.00 $37.82 $3484000.00 05-03-2018 03-2F5904 6 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 03 21400 $66.00 $102.20 $1412400.00 10-16-2019 03-3F2504 1 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 03 21400 $59.60 $92.29 $1275440.00 10-16-2019 03-3F2504 2 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 03 21400 $60.00 $92.91 $1284000.00 10-16-2019 03-3F2504 3 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 03 21400 $91.00 $140.91 $1947400.00 10-16-2019 03-3F2504 4 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 03 21400 $65.00 $100.65 $1391000.00 10-16-2019 03-3F2504 5 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 03 21400 $80.00 $123.88 $1712000.00 10-16-2019 03-3F2504 6 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 03 21400 $74.00 $114.59 $1583600.00 10-16-2019 03-3F2504 7 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 03 21400 $114.75 $177.68 $2455650.00 10-16-2019 03-3F2504 8 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 01 40000 $23.00 $35.61 $920000.00 10-17-2019 01-2982U4 1 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 01 40000 $20.00 $30.97 $800000.00 10-17-2019 01-2982U4 2 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 01 40000 $27.00 $41.81 $1080000.00 10-17-2019 01-2982U4 3 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 01 40000 $40.00 $61.94 $1600000.00 10-17-2019 01-2982U4 4 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 01 40000 $61.00 $94.46 $2440000.00 10-17-2019 01-2982U4 5 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 10 79500 $18.00 $28.68 $1431000.00 06-16-2020 10-0Y2104 1 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 10 79500 $24.00 $38.24 $1908000.00 06-16-2020 10-0Y2104 2 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 10 79500 $38.00 $60.54 $3021000.00 06-16-2020 10-0Y2104 3 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 10 79500 $42.00 $66.92 $3339000.00 06-16-2020 10-0Y2104 4 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 01 3960 $70.00 $100.19 $277200.00 11-04-2020 01-0F4704 1 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 01 3960 $46.00 $65.84 $182160.00 11-04-2020 01-0F4704 2 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 01 3960 $65.00 $93.03 $257400.00 11-04-2020 01-0F4704 3 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 03 4980 $315.00 $343.23 $1568700.00 01-19-2023 03-3H5404 1 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 03 4980 $200.00 $217.92 $996000.00 01-19-2023 03-3H5404 2 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 03 4980 $280.00 $305.09 $1394400.00 01-19-2023 03-3H5404 3 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 08 1000 $345.00 $357.69 $345000.00 12-10-2024 08-1K6904 1 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 08 1000 $702.63 $728.48 $702630.00 12-10-2024 08-1K6904 2 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 06 9000 $92.00 $90.02 $828000.00 12-02-2025 06-1A0904 1 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 06 9000 $125.00 $122.30 $1125000.00 12-02-2025 06-1A0904 2 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 06 9000 $65.00 $63.60 $585000.00 12-02-2025 06-1A0904 3 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 06 9000 $55.00 $53.81 $495000.00 12-02-2025 06-1A0904 4 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 06 9000 $90.00 $88.06 $810000.00 12-02-2025 06-1A0904 5 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 06 9000 $55.00 $53.81 $495000.00 12-02-2025 06-1A0904 6 M TRO
190160 - ROCK EXCAVATION (CONTROLLED BLASTING) CY 06 9000 $55.00 $53.81 $495000.00 12-02-2025 06-1A0904 7 M TRO
SUMMARY Unmodified Adjusted    
Average Price/Unit: $ Avg No. Units
Std Dev. (of Unit Price): ±$ Rows Selected
Weighted Avg.: $ Rows Returned
Minimum Price/Unit: $    
Maximum Price/Unit: $    

| Back | New Search |

PARAMETERS: Item = 190160; District=All; Year=All; Convert=No; Bidders=All Bidders
TIMESTAMP: 11/13/2026 05:28:29
CURRENT 12-MO INDEX (CHCCI (2020 Base)): 146.53